AOS-TASKS Generated planning view

Canonical Task Catalog

Human-readable projection of the canonical task CSV, including descriptions, acceptance criteria, dependencies, evidence, and traceability.

Canonical Task Catalog

Table of Contents

Catalog Rules

docs/planning/tasks.csv is canonical. This Markdown view is generated from it. Dependencies use task IDs; specifications use stable AOS-*#anchor references; source, claim, and experiment IDs resolve through their registers.

Track Index

Task Catalog

AOS-CAM

AOS-CAM-000 — Camera Quality Program epic

Type / priority / status: Epic · P1 · Backlog Owner / workstream: Camera Lead · Program Schedule: 2026-09-07 → 2029-07-08 · 3 estimated days · Continuous Parent: none Dependencies: none Related tasks: none

Outcome. Build a portable measurable camera stack and quality path.

Scope. Produce and integrate: project charter; milestone map; owned backlog; status/evidence dashboard. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Implement against the portable camera contracts; reference implementations and vendor material are used only under approved provenance and legal boundaries.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Project has one accountable lead, an approved scope, milestone links, and no orphaned P0/P1 work
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: project charter; milestone map; owned backlog; status/evidence dashboard Verification: monthly project review and gate reconciliation Evidence: project update; dependency report; risk and budget delta Traceability: specs: AOS-HW-006#quality-definition; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CAM-001 — Define camera quality metrics and acceptance scenes

Type / priority / status: Task · P0 · Backlog Owner / workstream: Camera Lead · Camera Quality Schedule: 2026-09-07 → 2026-11-01 · 12 estimated days · M3 Parent: AOS-CAM-000 Dependencies: AOS-DOCS-004 Related tasks: none

Outcome. Turn “good camera” into measurable capture, 3A, color, texture, noise, dynamic range, motion, latency, video, stabilization, power and consistency targets.

Scope. Produce and integrate: metric catalog; controlled/natural scene set; reference devices; target ranges; human-review protocol; evidence schema. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Implement against the portable camera contracts; reference implementations and vendor material are used only under approved provenance and legal boundaries.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Each quality claim names a metric or structured review, capture conditions, reference, uncertainty and minimum acceptable outcome
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: metric catalog; controlled/natural scene set; reference devices; target ranges; human-review protocol; evidence schema Verification: camera/vision/product review and pilot captures on stock/reference hardware Evidence: quality plan; scene inventory; pilot metrics; known measurement limits Traceability: specs: AOS-HW-006#quality-definition;AOS-RES-003#camera-claims; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CAM-002 — Commission camera calibration and measurement lab

Type / priority / status: Purchase · P1 · Backlog Owner / workstream: Camera Lab Engineer · Camera Lab Schedule: 2026-09-21 → 2026-11-29 · 12 estimated days · M3 Parent: AOS-CAM-000 Dependencies: AOS-OPEN-002;AOS-OPEN-003 Related tasks: AOS-CAM-001

Outcome. Build controlled lighting, targets, fixtures, motion/flicker, reference capture, lux/color and data-management capability tied to quality experiments.

Scope. Produce and integrate: lab fixtures/targets/lights/meters; calibration records; scene procedures; asset/source rights; capture automation. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Implement against the portable camera contracts; reference implementations and vendor material are used only under approved provenance and legal boundaries.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Lab variance is characterized, every target/light/instrument is identified, and raw/reference assets have lawful provenance
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: lab fixtures/targets/lights/meters; calibration records; scene procedures; asset/source rights; capture automation Verification: repeat reference captures across days/operators and quantify variance Evidence: commissioning report; calibration certificates/status; repeatability statistics Traceability: specs: AOS-HW-009#camera-lab;AOS-RES-004#evidence-integrity; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CAM-010 — Freeze portable camera service API level 0

Type / priority / status: Decision · P0 · Backlog Owner / workstream: Camera Architect · Camera Architecture Schedule: 2027-03-22 → 2027-04-18 · 8 estimated days · M4 Parent: AOS-CAM-000 Dependencies: AOS-CAM-001 Related tasks: AOS-PLAT-039

Outcome. Approve stream/control/result, frame ownership, timestamps, calibration, 3A, processing, privacy, power, lifecycle and extension semantics.

Scope. Produce and integrate: camera API-level manifest; conformance cases; backend extension rules; unresolved-feature list. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Implement against the portable camera contracts; reference implementations and vendor material are used only under approved provenance and legal boundaries.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • API supports metadata-rich RAW/processed/video flows without encoding Linux media, Android Camera HAL, or one ISP’s control vocabulary
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: camera API-level manifest; conformance cases; backend extension rules; unresolved-feature list Verification: map virtual, Pi/reference, AM62A/i.MX and vendor-module paths and security review Evidence: API gate record; mapping report; conformance fixtures Traceability: specs: AOS-HW-006#portable-camera-stack; sources: none; claims: none; experiments: none Phase / volume: Phase 2 · Volume 03 Specialist review: none

AOS-CAM-011 — Define sensor, lens, calibration, and metadata model

Type / priority / status: Task · P0 · Backlog Owner / workstream: Camera Systems Engineer · Camera Architecture Schedule: 2027-04-05 → 2027-05-30 · 12 estimated days · M5 Parent: AOS-CAM-000 Dependencies: AOS-CAM-002 Related tasks: AOS-PLAT-039;AOS-CAM-010

Outcome. Represent sensor modes, exposure/gain/timing, CFA, black/white levels, lens/AF/OIS, temperature, defects, color/shading and per-module calibration provenance.

Scope. Produce and integrate: metadata/calibration schemas; module identity; control ranges; DNG mapping; validation fixtures. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Implement against the portable camera contracts; reference implementations and vendor material are used only under approved provenance and legal boundaries.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Every captured frame can be traced to exact mode/control/calibration/module and unknown calibration is explicit
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: metadata/calibration schemas; module identity; control ranges; DNG mapping; validation fixtures Verification: encode two sensors/modules and reject missing/inconsistent timing/color/calibration data Evidence: schema tests; module dossiers; DNG validation Traceability: specs: AOS-HW-006#sensor-and-module; sources: none; claims: none; experiments: none Phase / volume: Phase 2 · Volume 03 Specialist review: none

AOS-CAM-012 — Implement camera pipeline backend framework

Type / priority / status: Task · P0 · Backlog Owner / workstream: Camera Platform Engineer · Camera Platform Schedule: 2027-04-05 → 2027-06-27 · 20 estimated days · M5 Parent: AOS-CAM-000 Dependencies: AOS-PLAT-024 Related tasks: AOS-CAM-010;AOS-PLAT-023

Outcome. Compose sensor, receiver, capture, ISP, 3A, lens, stabilization, encoder and computational stages as replaceable isolated backends.

Scope. Produce and integrate: pipeline graph; backend interfaces; buffer/metadata synchronization; lifecycle/reset; software/reference backend; tests. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Implement against the portable camera contracts; reference implementations and vendor material are used only under approved provenance and legal boundaries.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Backends can be replaced without product API changes and frame/control/result ownership remains synchronized under failure
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: pipeline graph; backend interfaces; buffer/metadata synchronization; lifecycle/reset; software/reference backend; tests Verification: virtual and reference pipeline, stage crash/restart, buffer pressure, control/result timing and privacy indicator tests Evidence: pipeline conformance; timing diagrams; fault/recovery traces Traceability: specs: AOS-HW-006#portable-camera-stack;AOS-ARCH-006#camera-contract; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CAM-020 — Capture stable RAW frames on a documented camera platform

Type / priority / status: Experiment · P0 · Backlog Owner / workstream: Camera Bring-up Engineer · Capture Schedule: 2027-05-03 → 2027-08-22 · 25 estimated days · M5 Parent: AOS-CAM-000 Dependencies: none Related tasks: AOS-CAM-011;AOS-CAM-012;AOS-OPEN-031

Outcome. Acquire repeatable full-resolution RAW frames with complete exposure/gain/timing/lens/calibration metadata through native Agent OS services.

Scope. Produce and integrate: sensor/CSI/capture backends; RAW buffer path; metadata; controlled corpus; error/restart handling. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Implement against the portable camera contracts; reference implementations and vendor material are used only under approved provenance and legal boundaries.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Frames have stable dimensions/stride/timestamps, no silent corruption/drop, and controls/results match measured capture timing
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: sensor/CSI/capture backends; RAW buffer path; metadata; controlled corpus; error/restart handling Verification: EXP-050 across modes, exposures, frame rates, temperature, dropped/corrupt frames and repeated boots Evidence: RAW/DNG corpus; metadata validator; bandwidth/drop metrics; EXP-050 record Traceability: specs: AOS-HW-006#documented-camera-bench;AOS-HW-006#capture-path; sources: none; claims: CLM-012; experiments: EXP-050 Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CAM-021 — Implement DNG/portable RAW export and provenance

Type / priority / status: Task · P1 · Backlog Owner / workstream: Imaging Format Engineer · Capture Schedule: 2027-06-14 → 2027-08-01 · 10 estimated days · M5 Parent: AOS-CAM-000 Dependencies: AOS-CAM-011 Related tasks: AOS-CAM-020

Outcome. Export captured RAW, calibration, metadata, thumbnails and processing history in a documented interoperable format.

Scope. Produce and integrate: DNG writer/validator; metadata mapping; provenance/signature fields; sample assets; compatibility tests. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Implement against the portable camera contracts; reference implementations and vendor material are used only under approved provenance and legal boundaries.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Export preserves raw sample values and essential calibration/control metadata without private vendor dependencies
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: DNG writer/validator; metadata mapping; provenance/signature fields; sample assets; compatibility tests Verification: validate with independent readers and compare decoded raw/metadata round trip Evidence: DNG validation report; sample files; field coverage/gap list Traceability: specs: AOS-HW-006#raw-and-dng;AOS-PROD-004#backup-bundle; sources: SRC-044; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CAM-022 — Validate camera timestamp and sensor synchronization

Type / priority / status: Task · P1 · Backlog Owner / workstream: Camera Timing Engineer · Capture Schedule: 2027-06-14 → 2027-08-15 · 14 estimated days · M5 Parent: AOS-CAM-000 Dependencies: AOS-PLAT-013 Related tasks: AOS-PLAT-013;AOS-CAM-020;AOS-OPEN-054

Outcome. Align sensor exposure/readout, frame delivery, IMU/gyro, flash/flicker, audio and system time for motion, stabilization and video.

Scope. Produce and integrate: timestamp model; calibration procedure; synchronization service integration; flicker/motion tests; uncertainty fields. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Implement against the portable camera contracts; reference implementations and vendor material are used only under approved provenance and legal boundaries.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Consumers receive exposure interval and uncertainty, and synchronization drift remains within declared requirements
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: timestamp model; calibration procedure; synchronization service integration; flicker/motion tests; uncertainty fields Verification: LED/flicker/motion rig and cross-sensor/IMU/audio comparisons under load Evidence: timestamp offset/jitter report; calibration assets; failure cases Traceability: specs: AOS-HW-006#timing-and-motion; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CAM-030 — Implement reference 3A controller framework

Type / priority / status: Experiment · P0 · Backlog Owner / workstream: 3A Lead · 3A Schedule: 2027-06-14 → 2027-10-17 · 30 estimated days · M5 Parent: AOS-CAM-000 Dependencies: AOS-CAM-001 Related tasks: AOS-CAM-012;AOS-CAM-020

Outcome. Run isolated replaceable auto-exposure, auto-white-balance and autofocus algorithms with deterministic metadata, convergence, lock and scene-change behavior.

Scope. Produce and integrate: 3A host/runtime; statistics interface; AE/AWB/AF controllers; tuning/config; simulator/replay; metadata/diagnostics. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Implement against the portable camera contracts; reference implementations and vendor material are used only under approved provenance and legal boundaries.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • 3A decisions are reproducible from approved inputs, convergence/oscillation are measured, and algorithm failure does not deadlock capture
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: 3A host/runtime; statistics interface; AE/AWB/AF controllers; tuning/config; simulator/replay; metadata/diagnostics Verification: EXP-051 controlled brightness/color/depth/motion transitions, lock/unlock and failure behavior Evidence: convergence/stability plots; tuning files; traces; EXP-051 record Traceability: specs: AOS-HW-006#three-a; sources: SRC-040; claims: none; experiments: EXP-051 Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CAM-031 — Implement autofocus and lens/OIS control path

Type / priority / status: Task · P1 · Backlog Owner / workstream: Autofocus Engineer · 3A Schedule: 2027-07-12 → 2027-10-24 · 22 estimated days · M5 Parent: AOS-CAM-000 Dependencies: AOS-CAM-011 Related tasks: AOS-CAM-011;AOS-CAM-030

Outcome. Control focus actuators and optional stabilization with calibration, limits, feedback, failure detection and contrast/phase metrics where accessible.

Scope. Produce and integrate: lens/OIS driver contract; calibration; AF algorithms; focus metrics; safety limits; tests. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Implement against the portable camera contracts; reference implementations and vendor material are used only under approved provenance and legal boundaries.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Actuators remain within safe limits, focus state/confidence is exposed, and failed hardware cannot hang the pipeline
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: lens/OIS driver contract; calibration; AF algorithms; focus metrics; safety limits; tests Verification: near/far/low-light/low-texture/motion scenes, actuator limits/stall, restart and temperature variation Evidence: focus success/time/accuracy report; actuator traces; calibration data Traceability: specs: AOS-HW-006#three-a; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CAM-032 — Tune auto-exposure and auto-white-balance baseline

Type / priority / status: Task · P1 · Backlog Owner / workstream: Imaging/3A Engineer · 3A Schedule: 2027-07-26 → 2027-11-14 · 24 estimated days · M5 Parent: AOS-CAM-000 Dependencies: AOS-CAM-002 Related tasks: AOS-CAM-001;AOS-CAM-030

Outcome. Achieve stable exposure and neutral/intentional color behavior across dynamic range, mixed light, skin tones, flicker and scene transitions.

Scope. Produce and integrate: AE/AWB algorithms and tuning; flicker handling; scene statistics; test corpus; diagnostics. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Implement against the portable camera contracts; reference implementations and vendor material are used only under approved provenance and legal boundaries.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • AE/AWB meet declared convergence/stability/color targets and failure/uncertainty is visible in metadata
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: AE/AWB algorithms and tuning; flicker handling; scene statistics; test corpus; diagnostics Verification: controlled lux/CCT/mixed light/HDR/flicker/skin scenes and temporal transition analysis Evidence: exposure/color error and stability report; tuning revisions; visual review Traceability: specs: AOS-HW-006#three-a; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CAM-040 — Build per-module calibration and image pipeline baseline

Type / priority / status: Experiment · P0 · Backlog Owner / workstream: Image Quality Engineer · Calibration Schedule: 2027-07-12 → 2027-11-14 · 28 estimated days · M5 Parent: AOS-CAM-000 Dependencies: AOS-CAM-002 Related tasks: AOS-CAM-011;AOS-CAM-020;AOS-CAM-032

Outcome. Measure and apply black level, bad pixels, lens shading, geometric distortion, color matrix, noise, sharpness and tone behavior with traceable calibration.

Scope. Produce and integrate: calibration procedures/tools; per-module bundles; baseline demosaic/color/noise/tone pipeline; versioning/provenance. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Implement against the portable camera contracts; reference implementations and vendor material are used only under approved provenance and legal boundaries.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Calibration is tied to module identity/version, improves declared metrics, and invalid/missing data fails visibly rather than applying unsafe defaults
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: calibration procedures/tools; per-module bundles; baseline demosaic/color/noise/tone pipeline; versioning/provenance Verification: EXP-052 across multiple modules, temperatures, illuminants and repeat calibrations Evidence: calibration bundles; metric report; before/after corpus; EXP-052 record Traceability: specs: AOS-HW-006#calibration; sources: none; claims: none; experiments: EXP-052 Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CAM-041 — Implement repeatable image-quality comparison harness

Type / priority / status: Task · P1 · Backlog Owner / workstream: Camera QA Lead · Quality Evaluation Schedule: 2027-08-09 → 2027-11-14 · 18 estimated days · M5 Parent: AOS-CAM-000 Dependencies: AOS-CAM-001;AOS-CAM-002;AOS-P9-020 Related tasks: AOS-CAM-040

Outcome. Run objective metrics, blinded expert/user review, metadata validation and stock/reference comparison with controlled processing and versioning.

Scope. Produce and integrate: capture orchestration; scene database; metric pipeline; blinded review tool; report generator; versioned baselines. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Implement against the portable camera contracts; reference implementations and vendor material are used only under approved provenance and legal boundaries.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Every quality result can be reproduced from raw inputs/configuration and distinguishes objective metrics from subjective preference
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: capture orchestration; scene database; metric pipeline; blinded review tool; report generator; versioned baselines Verification: repeat one device/pipeline across days then compare two devices without leaking labels to reviewers Evidence: repeatability and comparison reports; scripts; dataset manifests Traceability: specs: AOS-HW-006#quality-definition;AOS-RES-004#evidence-integrity; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CAM-042 — Implement video and stabilization reference path

Type / priority / status: Task · P1 · Backlog Owner / workstream: Video Imaging Engineer · Video Schedule: 2027-09-06 → 2028-01-23 · 30 estimated days · M8 Parent: AOS-CAM-000 Dependencies: AOS-CAM-022;AOS-PLAT-036 Related tasks: AOS-PLAT-036;AOS-CAM-031;AOS-CAM-032

Outcome. Capture synchronized audio/video with exposure/focus continuity, frame pacing, rolling-shutter metadata, EIS/OIS hooks, encoding, thermal and storage behavior.

Scope. Produce and integrate: video capture graph; A/V sync; encoder interface; EIS reference; metadata; thermal/storage controls; test clips. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Implement against the portable camera contracts; reference implementations and vendor material are used only under approved provenance and legal boundaries.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Video reports dropped/duplicated frames and thermal degradation explicitly, maintains declared A/V sync, and safely stops on resource exhaustion
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: video capture graph; A/V sync; encoder interface; EIS reference; metadata; thermal/storage controls; test clips Verification: motion/rolling-shutter, low light, long duration, storage pressure, thermal throttle, route changes and restart tests Evidence: A/V sync/frame-drop/stabilization/thermal report; clips; traces Traceability: specs: AOS-HW-006#video-and-stabilization; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CAM-050 — Implement published-prior-art burst fusion pipeline

Type / priority / status: Experiment · P1 · Backlog Owner / workstream: Computational Photography Lead · Computational Photography Schedule: 2027-09-06 → 2028-02-20 · 35 estimated days · M8 Parent: AOS-CAM-000 Dependencies: AOS-CAM-022;AOS-LEGAL-004 Related tasks: AOS-CAM-040;AOS-CAM-041

Outcome. Build an original, documented burst alignment, rejection, merge and tone pipeline using lawful publications/data and native Agent OS captures.

Scope. Produce and integrate: algorithm spec; alignment/merge implementation; motion rejection; tuning; CPU/accelerator backends; A/B dataset. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Implement against the portable camera contracts; reference implementations and vendor material are used only under approved provenance and legal boundaries.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Improvements are measured against single-frame baseline, motion artifacts are bounded, and no private Pixel implementation is used or implied
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: algorithm spec; alignment/merge implementation; motion rejection; tuning; CPU/accelerator backends; A/B dataset Verification: EXP-053 controlled HDR/low-light/motion scenes, artifacts, performance/power and blinded review Evidence: A/B metrics/corpus; algorithm provenance; performance/power report; EXP-053 record Traceability: specs: AOS-HW-006#computational-pipeline;AOS-RES-001#camera-cellular; sources: SRC-043; claims: CLM-013; experiments: EXP-053 Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CAM-051 — Optimize low-light noise, detail, color, and motion behavior

Type / priority / status: Task · P2 · Backlog Owner / workstream: Computational Photography Engineer · Computational Photography Schedule: 2027-11-29 → 2028-04-02 · 28 estimated days · M8 Parent: AOS-CAM-000 Dependencies: AOS-CAM-032 Related tasks: AOS-CAM-001;AOS-CAM-050

Outcome. Improve low-light output through sensor-aware denoise, temporal fusion, color/tone and capture policy while controlling ghosting and latency.

Scope. Produce and integrate: noise model; temporal/spatial denoise; capture policy; tuning; artifact detector; benchmark set. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Implement against the portable camera contracts; reference implementations and vendor material are used only under approved provenance and legal boundaries.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Low-light gains do not hide unacceptable motion/texture/color regressions and fallback is deterministic when fusion confidence is low
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: noise model; temporal/spatial denoise; capture policy; tuning; artifact detector; benchmark set Verification: lux/motion/skin/texture/color scenes, handheld sequences, power/latency and failure-to-single-frame fallback Evidence: quality/latency/power report; artifact examples; tuning data Traceability: specs: AOS-HW-006#computational-pipeline; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CAM-052 — Optimize HDR and local tone mapping

Type / priority / status: Task · P2 · Backlog Owner / workstream: Computational Photography Engineer · Computational Photography Schedule: 2027-12-13 → 2028-04-02 · 24 estimated days · M8 Parent: AOS-CAM-000 Dependencies: AOS-CAM-041 Related tasks: AOS-CAM-001;AOS-CAM-050

Outcome. Extend usable dynamic range while preserving color, local contrast, natural highlights, faces and temporal stability.

Scope. Produce and integrate: exposure selection; merge/tone algorithms; face/highlight policies; temporal/preview strategy; benchmarks. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Implement against the portable camera contracts; reference implementations and vendor material are used only under approved provenance and legal boundaries.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • HDR improves declared highlight/shadow metrics without systematic halos, color shifts or unsafe capture latency
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: exposure selection; merge/tone algorithms; face/highlight policies; temporal/preview strategy; benchmarks Verification: backlit, specular, sky/interior, skin and motion scenes with halo/ghost/color/temporal metrics Evidence: HDR comparison report; artifact corpus; performance/power measurements Traceability: specs: AOS-HW-006#computational-pipeline; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CAM-053 — Evaluate optional ML imaging components under bounded policy

Type / priority / status: Spike · P3 · Backlog Owner / workstream: ML Imaging Engineer · Computational Photography Schedule: 2028-01-24 → 2028-04-30 · 18 estimated days · M9 Parent: AOS-CAM-000 Dependencies: AOS-CAM-041;AOS-SEC-061 Related tasks: none

Outcome. Assess whether segmentation, denoise, super-resolution, scene understanding or auto-edit models add measurable value with acceptable provenance, privacy, size, power and fallback.

Scope. Produce and integrate: candidate/model/data/license dossier; offline benchmark; privacy/energy analysis; deterministic fallback; decision. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Implement against the portable camera contracts; reference implementations and vendor material are used only under approved provenance and legal boundaries.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • No model ships without rights, data provenance, measured value, bias/robustness analysis, budget compliance and non-ML fallback
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: candidate/model/data/license dossier; offline benchmark; privacy/energy analysis; deterministic fallback; decision Verification: quality and robustness tests including out-of-distribution/skin-tone/privacy/thermal cases Evidence: model card; provenance/SBOM; benchmark; decision record Traceability: specs: AOS-HW-006#ml-policy;AOS-LEGAL-003#provenance-record; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CAM-060 — Prove camera API portability across two pipelines

Type / priority / status: Experiment · P0 · Backlog Owner / workstream: Camera Architect · Camera Portability Schedule: 2027-11-15 → 2028-02-20 · 18 estimated days · M9 Parent: AOS-CAM-000 Dependencies: AOS-CAM-020;AOS-CAM-040;AOS-OPEN-032 Related tasks: none

Outcome. Run the same capture application and conformance suite over two materially different sensor/ISP/software backends.

Scope. Produce and integrate: second backend; API conformance; optional-capability map; leakage report; migration/performance comparison. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Implement against the portable camera contracts; reference implementations and vendor material are used only under approved provenance and legal boundaries.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Client code is unchanged, backend-specific features are versioned optional capabilities, and common semantics match
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: second backend; API conformance; optional-capability map; leakage report; migration/performance comparison Verification: EXP-054 identical client workflows, metadata validation, failure/lifecycle and quality-harness execution Evidence: cross-backend matrix; source diff; EXP-054 record Traceability: specs: AOS-ARCH-001#portability-test;AOS-HW-006#portable-camera-stack; sources: none; claims: CLM-002;CLM-014; experiments: EXP-054 Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CAM-061 — Characterize and budget camera power, memory, bandwidth, and thermal cost

Type / priority / status: Task · P1 · Backlog Owner / workstream: Camera Performance Engineer · Camera Performance Schedule: 2027-11-29 → 2028-03-05 · 18 estimated days · M9 Parent: AOS-CAM-000 Dependencies: AOS-CAM-041;AOS-PLAT-041 Related tasks: AOS-CAM-042;AOS-CAM-050

Outcome. Measure preview/capture/video/computational workloads and enforce quality degradation strategies compatible with mobile thermal and battery limits.

Scope. Produce and integrate: resource budgets; measurements; quality/latency/power modes; thermal throttling/fallback policy; telemetry. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Implement against the portable camera contracts; reference implementations and vendor material are used only under approved provenance and legal boundaries.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Camera remains within declared safety/resource limits and quality changes are explicit rather than causing crashes or silent frame loss
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: resource budgets; measurements; quality/latency/power modes; thermal throttling/fallback policy; telemetry Verification: long-run and burst workloads at controlled ambient/battery states on reference/open hardware Evidence: power/thermal/bandwidth/memory report; degradation traces Traceability: specs: AOS-HW-006#power-and-performance;AOS-ARCH-014#energy-budgets; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CAM-070 — Issue controlled proprietary camera-module/ISP RFI

Type / priority / status: Contact · P1 · Backlog Owner / workstream: Camera Partnerships Lead · Camera Partnerships Schedule: 2027-11-29 → 2028-04-02 · 12 estimated days · M9 Parent: AOS-CAM-000 Dependencies: AOS-CAM-010;AOS-CAM-001;AOS-LEGAL-011 Related tasks: AOS-ODM-011

Outcome. Test whether a vendor can supply quality hardware and documentation/support under replaceable portable contracts without unacceptable cost or lock-in.

Scope. Produce and integrate: RFI; interface/quality/support/rights questionnaire; candidate list; NDA/legal flow; scorecard. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Implement against the portable camera contracts; reference implementations and vendor material are used only under approved provenance and legal boundaries.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Response is actionable only if implementation/deployment/update/calibration/testing/replacement rights and support lifecycle are explicit
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: RFI; interface/quality/support/rights questionnaire; candidate list; NDA/legal flow; scorecard Verification: EXP-055 with at least three credible vendors/integrators or documented market failure Evidence: responses; rights/quality/cost comparison; EXP-055 record Traceability: specs: AOS-HW-006#controlled-proprietary-option;AOS-LEGAL-005#contractual-and-technical-asks; sources: none; claims: CLM-014; experiments: EXP-055 Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CAM-071 — Evaluate vendor camera path against native reference

Type / priority / status: Experiment · P1 · Backlog Owner / workstream: Camera Lead · Camera Partnerships Schedule: 2028-04-17 → 2028-08-20 · 20 estimated days · M9 Parent: AOS-CAM-000 Dependencies: AOS-CAM-070;AOS-CAM-041;AOS-CAM-061;AOS-LEGAL-011 Related tasks: none

Outcome. Compare selected vendor module/ISP/backend quality, power, latency, control, security, rights, support and replacement cost to native documented pipelines.

Scope. Produce and integrate: evaluation integration; conformance wrapper; quality/resource comparison; legal/support score; exit plan. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Implement against the portable camera contracts; reference implementations and vendor material are used only under approved provenance and legal boundaries.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Selection cannot be based on stock marketing quality alone and must preserve replaceable Agent OS API, updates, calibration and long-term support
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: evaluation integration; conformance wrapper; quality/resource comparison; legal/support score; exit plan Verification: same scene/harness, failure/update, provenance/security and replacement exercises Evidence: comparison report; conformance results; contract gap list; recommendation Traceability: specs: AOS-HW-006#quality-decision;AOS-HW-010#decision-weights; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CAM-080 — Select camera route for quality-device track

Type / priority / status: Decision · P0 · Backlog Owner / workstream: Architecture Council / Product Lead · Camera Strategy Schedule: 2028-09-04 → 2028-09-24 · 6 estimated days · M9 Parent: AOS-CAM-000 Dependencies: AOS-CAM-060;AOS-CAM-061;AOS-CAM-071;AOS-P9-020 Related tasks: none

Outcome. Choose documented native, controlled proprietary, hybrid or deferred camera route based on measured quality, resources, rights, cost and lifecycle.

Scope. Produce and integrate: camera gate packet; selected route; residual gaps; budget/team/partner plan; fallback/replacement triggers. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Implement against the portable camera contracts; reference implementations and vendor material are used only under approved provenance and legal boundaries.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Decision names measurable target, implementation ownership, contractual rights, power/thermal budget, support term and stop/replacement criteria
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: camera gate packet; selected route; residual gaps; budget/team/partner plan; fallback/replacement triggers Verification: architecture, camera, product, security, legal and program review Evidence: signed decision; quality evidence references; cost/rights matrix Traceability: specs: AOS-HW-006#quality-decision;AOS-PLAN-006#camera-stop-criteria; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CAM-090 — Build a lawful Pixel-class camera quality oracle corpus

Type / priority / status: Task · P0 · Planned Owner / workstream: Camera Quality Lead · Quality Oracle Schedule: 2026-09-07 → 2026-11-01 · 20 estimated days · M1 Parent: AOS-CAM-000 Dependencies: none Related tasks: none

Outcome. Build a lawful Pixel-class camera quality oracle corpus.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-HW-012#pixel-oracle, AOS-HW-014#camera. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Build a lawful Pixel-class camera quality oracle corpus; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-HW-012#tracks;AOS-HW-014#experiments; sources: SRC-021;SRC-022; claims: none; experiments: none Phase / volume: Phase 1 · Volume 03 Specialist review: none

AOS-CAM-091 — Bring up a documented i.MX 8M Plus RAW and metadata bench

Type / priority / status: Experiment · P0 · Planned Owner / workstream: Camera Platform Engineer · Documented ISP Schedule: 2027-06-28 → 2027-10-17 · 40 estimated days · M5 Parent: AOS-CAM-000 Dependencies: none Related tasks: none

Outcome. Bring up a documented i.MX 8M Plus RAW and metadata bench.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-HW-012#documented-isp, AOS-VAL-004#matrix. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Bring up a documented i.MX 8M Plus RAW and metadata bench; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-HW-012#tracks;AOS-VAL-004#matrix; sources: SRC-089;SRC-090; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CAM-092 — Specify portable 3A, calibration, and capture-result contracts

Type / priority / status: Task · P0 · Planned Owner / workstream: Camera Architect · Camera Contracts Schedule: 2026-10-05 → 2026-12-13 · 25 estimated days · M2 Parent: AOS-CAM-000 Dependencies: none Related tasks: none

Outcome. Specify portable 3A, calibration, and capture-result contracts.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-HW-012#portable-contract, AOS-ARCH-020#contract-set. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Specify portable 3A, calibration, and capture-result contracts; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-HW-012#portable-pipeline;AOS-ARCH-020#contract-set; sources: none; claims: none; experiments: none Phase / volume: Phase 2 · Volume 02 Specialist review: none

AOS-CAM-093 — Establish a calibrated camera quality measurement laboratory

Type / priority / status: Purchase · P1 · Planned Owner / workstream: Camera Quality Lead · Camera Laboratory Schedule: 2027-05-17 → 2027-07-25 · 25 estimated days · M5 Parent: AOS-CAM-000 Dependencies: none Related tasks: none

Outcome. Establish a calibrated camera quality measurement laboratory.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-HW-015#camera, AOS-HW-012#quality-program. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Establish a calibrated camera quality measurement laboratory; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-HW-015#recommended;AOS-HW-012#quality-model; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 07 Specialist review: none

AOS-CAM-094 — Evaluate industrial and UVC camera modules as compromise reducers

Type / priority / status: Experiment · P1 · Planned Owner / workstream: Camera Systems Engineer · Alternative Capture Schedule: 2027-07-12 → 2027-09-19 · 25 estimated days · M5 Parent: AOS-CAM-000 Dependencies: none Related tasks: none

Outcome. Evaluate industrial and UVC camera modules as compromise reducers.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-HW-012#external-modules, AOS-HW-013#camera. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Evaluate industrial and UVC camera modules as compromise reducers; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-HW-012#tracks;AOS-HW-013#categories; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CELL

AOS-CELL-000 — Cellular and Telephony Program epic

Type / priority / status: Epic · P1 · Backlog Owner / workstream: Cellular Lead · Program Schedule: 2026-10-05 → 2030-01-20 · 3 estimated days · Continuous Parent: none Dependencies: none Related tasks: none

Outcome. Implement native cellular services and establish partner/certification routes.

Scope. Produce and integrate: project charter; milestone map; owned backlog; status/evidence dashboard. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep Linux reference APIs and vendor protocols behind native Agent OS cellular services; data, SMS, eSIM, voice, IMS, and emergency support remain separate claims.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Project has one accountable lead, an approved scope, milestone links, and no orphaned P0/P1 work
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: project charter; milestone map; owned backlog; status/evidence dashboard Verification: monthly project review and gate reconciliation Evidence: project update; dependency report; risk and budget delta Traceability: specs: AOS-HW-007#separate-capability-gates; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CELL-001 — Define cellular capability decomposition and product claims

Type / priority / status: Task · P0 · Backlog Owner / workstream: Cellular Lead · Cellular Architecture Schedule: 2026-10-05 → 2026-11-29 · 10 estimated days · M3 Parent: AOS-CELL-000 Dependencies: AOS-DOCS-005;AOS-PLAT-001 Related tasks: AOS-PLAT-040

Outcome. Separate transport, control, registration, packet data, SMS, SIM/eSIM, GNSS, voice, IMS, emergency, carrier and certification states.

Scope. Produce and integrate: capability/state matrix; claim language; service ownership; threat/data/power map; gate dependencies. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep Linux reference APIs and vendor protocols behind native Agent OS cellular services; data, SMS, eSIM, voice, IMS, and emergency support remain separate claims.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • No roadmap or UI can infer voice/emergency/eSIM/certification from packet data or SMS
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: capability/state matrix; claim language; service ownership; threat/data/power map; gate dependencies Verification: review against 3GPP/GSMA/Android decomposition and open module cases without importing their APIs Evidence: architecture matrix; contradicted-assumption list; review record Traceability: specs: AOS-HW-007#separate-capability-gates; sources: SRC-023;SRC-048;SRC-049; claims: CLM-009; experiments: none Phase / volume: Phase 1 · Volume 03 Specialist review: none

AOS-CELL-002 — Shortlist documented cellular modules and evaluation kits

Type / priority / status: Purchase · P0 · Backlog Owner / workstream: Cellular Hardware Lead · Module Selection Schedule: 2026-10-19 → 2026-12-27 · 10 estimated days · M3 Parent: AOS-CELL-000 Dependencies: AOS-OPEN-003 Related tasks: AOS-CELL-001;AOS-LEGAL-011

Outcome. Identify modules with usable MBIM/QMI/AT documentation, firmware/update support, USB/PCIe, regional bands, certification, lifecycle and vendor FAE access.

Scope. Produce and integrate: module scorecard; vendor questions; evaluation kits; rights/firmware/certification/lifecycle dossier; recommendation. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep Linux reference APIs and vendor protocols behind native Agent OS cellular services; data, SMS, eSIM, voice, IMS, and emergency support remain separate claims.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Shortlist contains at least two vendors or explicit sole-source risk and distinguishes public protocol support from vendor/carrier features
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: module scorecard; vendor questions; evaluation kits; rights/firmware/certification/lifecycle dossier; recommendation Verification: official-source/vendor-response review and sample availability/pricing check Evidence: scorecard; vendor replies; purchase records; unsupported-feature list Traceability: specs: AOS-HW-007#module-selection;AOS-LEGAL-005#priority-contacts; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CELL-003 — Commission lawful cellular test environment

Type / priority / status: Purchase · P1 · Backlog Owner / workstream: Cellular Lab Lead · Cellular Lab Schedule: 2026-12-28 → 2027-04-04 · 10 estimated days · M4 Parent: AOS-CELL-000 Dependencies: AOS-CELL-002;AOS-OPEN-002 Related tasks: AOS-LEGAL-010

Outcome. Provide shielded/controlled or operator-approved test options, SIMs/accounts, traffic capture, emergency-call safeguards, RF/power tools and data-handling rules.

Scope. Produce and integrate: test plans/accounts/SIMs; network/traffic/power capture; emergency-call lockout; RF/legal safety procedures; asset register. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep Linux reference APIs and vendor protocols behind native Agent OS cellular services; data, SMS, eSIM, voice, IMS, and emergency support remain separate claims.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Testing cannot accidentally place emergency calls or violate network terms, and sensitive subscriber data has scoped retention/access
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: test plans/accounts/SIMs; network/traffic/power capture; emergency-call lockout; RF/legal safety procedures; asset register Verification: controlled registration/data/SMS test and emergency-path tabletop with counsel/lab guidance Evidence: lab commissioning; approvals; sample traces; safety checklist Traceability: specs: AOS-HW-007#test-environment;AOS-LEGAL-004#cellular-path; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CELL-010 — Implement native USB/serial/AT modem transport

Type / priority / status: Task · P0 · Backlog Owner / workstream: Cellular Protocol Engineer · Modem Transport Schedule: 2027-02-22 → 2027-05-16 · 20 estimated days · M5 Parent: AOS-CELL-000 Dependencies: AOS-CELL-002 Related tasks: AOS-PLAT-034;AOS-PLAT-024

Outcome. Communicate with documented module control/data endpoints through native USB/serial services with framing, timeouts, reset and diagnostics.

Scope. Produce and integrate: transport service; AT/framing engine; endpoint discovery; reset/power hooks; simulator/fuzzer; trace sanitizer. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep Linux reference APIs and vendor protocols behind native Agent OS cellular services; data, SMS, eSIM, voice, IMS, and emergency support remain separate claims.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Parser is bounded/fuzzed, secrets are redacted, module reset recovers, and no Linux serial/network API leaks above backend
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: transport service; AT/framing engine; endpoint discovery; reset/power hooks; simulator/fuzzer; trace sanitizer Verification: malformed/partial/unsolicited/timeout/reset/replug/driver-crash and command-injection tests Evidence: transport conformance; fuzz report; module traces; dependency scan Traceability: specs: AOS-HW-007#native-cellular-stack;AOS-ARCH-006#cellular-contract; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CELL-020 — Implement native MBIM/QMI transport and control proof

Type / priority / status: Experiment · P0 · Backlog Owner / workstream: Cellular Protocol Engineer · Modem Protocols Schedule: 2027-04-19 → 2027-08-22 · 30 estimated days · M5 Parent: AOS-CELL-000 Dependencies: AOS-LEGAL-005 Related tasks: AOS-PLAT-040;AOS-CELL-010

Outcome. Control at least one documented modem protocol and expose portable registration/session operations without a Linux runtime dependency.

Scope. Produce and integrate: MBIM or QMI codec/state engine; capability service adapter; simulator/traces; module integration; provenance review. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep Linux reference APIs and vendor protocols behind native Agent OS cellular services; data, SMS, eSIM, voice, IMS, and emergency support remain separate claims.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Agent OS performs protocol operations natively, malformed module responses are contained, and Linux D-Bus/libqmi/libmbim APIs are not native dependencies
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: MBIM or QMI codec/state engine; capability service adapter; simulator/traces; module integration; provenance review Verification: EXP-041 connect/register/session/status/reset/invalid-message scenarios and forbidden-dependency scan Evidence: protocol traces; state tests; EXP-041 record; clean-room/provenance sign-off Traceability: specs: AOS-HW-007#native-cellular-stack; sources: SRC-045;SRC-046;SRC-047; claims: CLM-008; experiments: EXP-041 Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CELL-021 — Implement modem registration and lifecycle state machine

Type / priority / status: Task · P0 · Backlog Owner / workstream: Cellular Service Engineer · Cellular Service Schedule: 2027-05-31 → 2027-09-05 · 22 estimated days · M6 Parent: AOS-CELL-000 Dependencies: none Related tasks: AOS-PLAT-024;AOS-CELL-020;AOS-CELL-022;AOS-PLAT-041

Outcome. Manage power, initialization, SIM state, network scan/selection, registration, roaming, loss, retry, reset, firmware status and diagnostics explicitly.

Scope. Produce and integrate: registration/lifecycle service; retry/backoff; policy hooks; status/errors; simulator; persistence rules. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep Linux reference APIs and vendor protocols behind native Agent OS cellular services; data, SMS, eSIM, voice, IMS, and emergency support remain separate claims.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • User/product sees truthful state and reason, retries are bounded, and modem failure cannot create hidden infinite power/network loops
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: registration/lifecycle service; retry/backoff; policy hooks; status/errors; simulator; persistence rules Verification: SIM absent/locked, denied/roaming, coverage loss, modem crash/reset, suspend, firmware mismatch and rapid toggling Evidence: state transition coverage; power/retry traces; user-status examples Traceability: specs: AOS-HW-007#modem-state-machine; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CELL-022 — Implement physical SIM access and secret boundary

Type / priority / status: Task · P0 · Backlog Owner / workstream: SIM/Security Engineer · SIM Schedule: 2027-04-19 → 2027-07-11 · 18 estimated days · M5 Parent: AOS-CELL-000 Dependencies: none Related tasks: AOS-CELL-010;AOS-SEC-022

Outcome. Expose SIM presence, PIN/PUK, subscriber/application state and approved operations without leaking credentials or raw APDU authority to ordinary clients.

Scope. Produce and integrate: SIM service; PIN/PUK trusted UI; application/status model; APDU broker policy; redaction/audit; tests. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep Linux reference APIs and vendor protocols behind native Agent OS cellular services; data, SMS, eSIM, voice, IMS, and emergency support remain separate claims.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • PIN/PUK never enters general history/logs, retry counters are accurate, and arbitrary APDU access requires separate privileged grant
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: SIM service; PIN/PUK trusted UI; application/status model; APDU broker policy; redaction/audit; tests Verification: wrong PIN/PUK, brute-force/rate, process crash, removal, secure-input/journal and unauthorized APDU tests Evidence: SIM security review; state tests; redaction scan; user flows Traceability: specs: AOS-HW-007#sim-and-esim;AOS-ARCH-012#sensitive-data; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CELL-030 — Deliver native cellular data and SMS prototype

Type / priority / status: Experiment · P0 · Backlog Owner / workstream: Cellular Service Engineer · Data and SMS Schedule: 2027-07-26 → 2027-11-14 · 25 estimated days · M6 Parent: AOS-CELL-000 Dependencies: AOS-PROD-012;AOS-CELL-003 Related tasks: AOS-CELL-021;AOS-PLAT-033

Outcome. Register a module, establish packet data, route network service, send/receive SMS, persist receipts, and recover from loss/reset.

Scope. Produce and integrate: data session backend; IP/DNS integration; SMS encode/store/action provider; usage/roaming policy; UI/status; tests. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep Linux reference APIs and vendor protocols behind native Agent OS cellular services; data, SMS, eSIM, voice, IMS, and emergency support remain separate claims.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Data and SMS work natively on supported module, duplicates/loss are handled visibly, and no voice/IMS claim is made
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: data session backend; IP/DNS integration; SMS encode/store/action provider; usage/roaming policy; UI/status; tests Verification: EXP-042 registration/data/DNS/large transfer/SMS send-receive/duplicate/loss/reset/roaming policy cases Evidence: network traces; SMS receipts; usage/power logs; EXP-042 record Traceability: specs: AOS-HW-007#data-and-sms;AOS-PROD-006#tier-two; sources: none; claims: none; experiments: EXP-042 Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CELL-031 — Harden cellular recovery, suspend, roaming, and power behavior

Type / priority / status: Task · P1 · Backlog Owner / workstream: Cellular Reliability Engineer · Data and SMS Schedule: 2027-09-20 → 2027-12-26 · 20 estimated days · M8 Parent: AOS-CELL-000 Dependencies: AOS-CELL-021;AOS-PLAT-041 Related tasks: AOS-CELL-030

Outcome. Make connectivity resilient and bounded across coverage changes, modem resets, SIM changes, suspend/wake, roaming policy and data limits.

Scope. Produce and integrate: recovery/backoff policy; suspend integration; usage budgets; roaming/user controls; long-run tests; diagnostics. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep Linux reference APIs and vendor protocols behind native Agent OS cellular services; data, SMS, eSIM, voice, IMS, and emergency support remain separate claims.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • No uncontrolled reconnect/power loop occurs, user policy is respected, and session/SMS state reconciles after reset
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: recovery/backoff policy; suspend integration; usage budgets; roaming/user controls; long-run tests; diagnostics Verification: hours-long coverage/modem/suspend/roaming/data-limit fault campaign with power measurement Evidence: reliability/power report; failure traces; policy UX review Traceability: specs: AOS-HW-007#reliability-and-power;AOS-ARCH-014#background-policy; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CELL-040 — Model and evaluate eSIM lifecycle and partner requirements

Type / priority / status: Experiment · P1 · Backlog Owner / workstream: eSIM Product/Security Lead · eSIM Schedule: 2027-08-23 → 2027-12-12 · 18 estimated days · M9 Parent: AOS-CELL-000 Dependencies: AOS-CELL-001;AOS-CELL-022;AOS-LEGAL-010;AOS-LEGAL-011 Related tasks: none

Outcome. Define eUICC discovery, profile download/enable/disable/delete, credentials, user consent, recovery, device migration and GSMA/vendor/operator dependencies.

Scope. Produce and integrate: lifecycle/state/threat model; UI/confirmation; data-class/recovery plan; vendor/operator/GSMA gap analysis; partner asks. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep Linux reference APIs and vendor protocols behind native Agent OS cellular services; data, SMS, eSIM, voice, IMS, and emergency support remain separate claims.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Plan identifies which functions require certified components/agreements and never treats profile secrets as portable backup data
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: lifecycle/state/threat model; UI/confirmation; data-class/recovery plan; vendor/operator/GSMA gap analysis; partner asks Verification: EXP-043 tabletop and available evaluation path; lost device, transfer, rollback and malicious profile scenarios Evidence: eSIM gap report; partner responses; EXP-043 record Traceability: specs: AOS-HW-007#sim-and-esim;AOS-PROD-004#data-classes; sources: SRC-049; claims: none; experiments: EXP-043 Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CELL-041 — Integrate modem-assisted GNSS where supportable

Type / priority / status: Task · P3 · Backlog Owner / workstream: GNSS Engineer · GNSS Schedule: 2027-10-04 → 2027-12-26 · 14 estimated days · M8 Parent: AOS-CELL-000 Dependencies: AOS-CELL-020;AOS-PLAT-013 Related tasks: AOS-OPEN-054

Outcome. Expose location/time observations from a supported modem or separate GNSS path with permissions, accuracy, assistance-data, offline and power semantics.

Scope. Produce and integrate: GNSS backend; assistance-data policy; location/time metadata; power modes; privacy tests. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep Linux reference APIs and vendor protocols behind native Agent OS cellular services; data, SMS, eSIM, voice, IMS, and emergency support remain separate claims.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Consumers receive accuracy/freshness/source, assistance data destinations are disclosed, and background location is separately authorized
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: GNSS backend; assistance-data policy; location/time metadata; power modes; privacy tests Verification: known-location/time comparison, cold/warm start, denial/background, no-network and suspend tests Evidence: accuracy/TTFF/power report; privacy review; conformance Traceability: specs: AOS-HW-007#gnss;AOS-ARCH-012#location-privacy; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CELL-042 — Define emergency-calling safety boundary before voice work

Type / priority / status: Review · P0 · Backlog Owner / workstream: Telephony Safety Lead · Voice and Emergency Schedule: 2027-08-23 → 2027-11-14 · 12 estimated days · M9 Parent: AOS-CELL-000 Dependencies: AOS-CELL-001;AOS-LEGAL-010;AOS-CELL-003 Related tasks: none

Outcome. Prevent misleading or accidental emergency behavior and specify requirements, test methods, UI, fallback, location and regulatory/operator dependencies.

Scope. Produce and integrate: emergency requirements; test-network/lab procedure; UI/support language; disable/guard controls; partner/certification checklist. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep Linux reference APIs and vendor protocols behind native Agent OS cellular services; data, SMS, eSIM, voice, IMS, and emergency support remain separate claims.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • No build advertises phone/emergency readiness before a lawful tested route passes its separate gate
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: emergency requirements; test-network/lab procedure; UI/support language; disable/guard controls; partner/certification checklist Verification: tabletop and accredited/operator consultation without live unauthorized emergency calls Evidence: safety review; lab/operator guidance; blocked release language Traceability: specs: AOS-HW-007#emergency-calling;AOS-LEGAL-004#cellular-path; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CELL-050 — Establish native voice and IMS feasibility

Type / priority / status: Experiment · P0 · Backlog Owner / workstream: IMS/Telephony Lead · Voice and IMS Schedule: 2027-11-29 → 2028-06-11 · 30 estimated days · M9 Parent: AOS-CELL-000 Dependencies: AOS-CELL-042;AOS-LEGAL-010;AOS-LEGAL-011;AOS-CELL-060 Related tasks: AOS-CELL-040

Outcome. Determine whether vendor/carrier-supported voice, IMS registration, audio routing, SMS over IMS, provisioning, handover and emergency behavior can be implemented and maintained.

Scope. Produce and integrate: vendor/carrier architecture; interface/support/rights matrix; call-flow/provisioning model; test plan; cost/schedule; continue/stop recommendation. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep Linux reference APIs and vendor protocols behind native Agent OS cellular services; data, SMS, eSIM, voice, IMS, and emergency support remain separate claims.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • A positive result requires named supported modem/vendor/carrier path, emergency/audio/provisioning coverage and lifecycle commitment—not SIP theory alone
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: vendor/carrier architecture; interface/support/rights matrix; call-flow/provisioning model; test plan; cost/schedule; continue/stop recommendation Verification: EXP-044 with written partner evidence and lawful lab/test-network demonstration where available Evidence: partner responses; call-flow traces; gap/certification report; EXP-044 record Traceability: specs: AOS-HW-007#voice-and-ims;AOS-PLAN-006#cellular-and-voice-criteria; sources: SRC-023;SRC-048; claims: CLM-009; experiments: EXP-044 Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CELL-051 — Implement telephony audio-routing contract and test path

Type / priority / status: Task · P1 · Backlog Owner / workstream: Telephony Audio Engineer · Voice and IMS Schedule: 2028-03-20 → 2028-07-23 · 22 estimated days · M9 Parent: AOS-CELL-000 Dependencies: AOS-PLAT-036 Related tasks: AOS-PLAT-036;AOS-CELL-050

Outcome. Route microphone, speaker/earpiece, Bluetooth/USB, modem/IMS streams, tones, mute, volume and privacy through native audio policy.

Scope. Produce and integrate: telephony audio endpoints; route/policy state; timing/echo/noise hooks; privacy UI; loopback/test-call fixtures. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep Linux reference APIs and vendor protocols behind native Agent OS cellular services; data, SMS, eSIM, voice, IMS, and emergency support remain separate claims.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Call audio cannot be captured/routed by ungranted clients, route state is visible, and failures never leave microphone active silently
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: telephony audio endpoints; route/policy state; timing/echo/noise hooks; privacy UI; loopback/test-call fixtures Verification: route changes, mute/privacy, echo/latency, device loss, suspend, call interruption and failure tests Evidence: audio route matrix; latency/quality metrics; privacy review Traceability: specs: AOS-HW-007#audio-routing; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CELL-052 — Build cellular certification and carrier engagement plan

Type / priority / status: Task · P1 · Backlog Owner / workstream: Cellular Certification Lead · Certification Schedule: 2028-04-03 → 2028-08-06 · 15 estimated days · M9 Parent: AOS-CELL-000 Dependencies: AOS-CELL-002;AOS-LEGAL-010 Related tasks: AOS-CELL-050

Outcome. Map module/final-device approvals, PTCRB/GCF, operator acceptance, IMS profiles, emergency, RF/SAR, OTA, variants, updates and regression responsibility.

Scope. Produce and integrate: certification matrix; operator/lab contact plan; test builds/data; budget/lead time; change-control and support obligations. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep Linux reference APIs and vendor protocols behind native Agent OS cellular services; data, SMS, eSIM, voice, IMS, and emergency support remain separate claims.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Plan states which approvals are inherited, invalidated or repeated and who owns failures/updates through product lifetime
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: certification matrix; operator/lab contact plan; test builds/data; budget/lead time; change-control and support obligations Verification: authorized lab and module vendor review; compare at least two market routes Evidence: review notes; budget/schedule; responsibility matrix; open blockers Traceability: specs: AOS-LEGAL-004#cellular-and-carrier-path;AOS-HW-007#certification-consequences; sources: SRC-050;SRC-051; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CELL-060 — Secure cellular module vendor and FAE relationships

Type / priority / status: Contact · P1 · Backlog Owner / workstream: Cellular Partnerships Lead · Partnerships Schedule: 2026-12-14 → 2027-05-30 · 10 estimated days · M5 Parent: AOS-CELL-000 Dependencies: AOS-LEGAL-011 Related tasks: AOS-CELL-002

Outcome. Obtain documentation, firmware/update policy, samples, support, certification data and a route for Linux-independent native integration.

Scope. Produce and integrate: outreach dossiers; meetings; NDA/legal review; sample/support quotes; lifecycle/rights responses; contact register. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep Linux reference APIs and vendor protocols behind native Agent OS cellular services; data, SMS, eSIM, voice, IMS, and emergency support remain separate claims.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Selected module path has a named support contact or a documented self-support/public-spec rationale and replacement candidate
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: outreach dossiers; meetings; NDA/legal review; sample/support quotes; lifecycle/rights responses; contact register Verification: at least three qualified vendors/integrators contacted and responses scored Evidence: public-safe contact outcomes; response scorecard; agreements/limitations Traceability: specs: AOS-LEGAL-005#priority-contacts;AOS-HW-007#module-selection; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CELL-070 — Integrate cellular data/SMS into open-phone product experience

Type / priority / status: Task · P0 · Backlog Owner / workstream: Connected Product Lead · Connected Product Schedule: 2027-10-04 → 2028-01-09 · 20 estimated days · M6 Parent: AOS-CELL-000 Dependencies: AOS-PROD-012;AOS-PROD-050 Related tasks: AOS-CELL-030;AOS-OPEN-057

Outcome. Expose honest signal/registration/data/SMS/SIM/roaming/usage state and actions in the entity shell with recovery and migration behavior.

Scope. Produce and integrate: connectivity/SIM/message entities; actions/receipts; status/errors; usage/roaming controls; backup/migration rules; limitations UI. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep Linux reference APIs and vendor protocols behind native Agent OS cellular services; data, SMS, eSIM, voice, IMS, and emergency support remain separate claims.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • UI distinguishes data/SMS from voice/IMS, exposes provider/network state, and never hides billing/roaming or unsupported emergency status
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: connectivity/SIM/message entities; actions/receipts; status/errors; usage/roaming controls; backup/migration rules; limitations UI Verification: normal/loss/reset/SIM change/duplicate SMS/denied action/restore and accessibility workflows Evidence: product demo; action receipts; support matrix; user comprehension review Traceability: specs: AOS-PROD-006#tier-two;AOS-HW-003#modem-role; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-CELL-080 — Decide connected-device versus full-phone product route

Type / priority / status: Decision · P0 · Backlog Owner / workstream: Program Lead / Product Lead · Cellular Strategy Schedule: 2028-09-04 → 2028-09-24 · 6 estimated days · M9 Parent: AOS-CELL-000 Dependencies: AOS-CELL-031;AOS-CELL-040;AOS-CELL-050;AOS-CELL-052;AOS-LEGAL-013 Related tasks: none

Outcome. Select supported cellular claims and investment based on module, data/SMS, eSIM, voice/IMS, emergency, certification, cost and partner evidence.

Scope. Produce and integrate: cellular gate packet; supported claim level; partner/certification budget; unsupported/fallback behavior; stop/revisit criteria. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep Linux reference APIs and vendor protocols behind native Agent OS cellular services; data, SMS, eSIM, voice, IMS, and emergency support remain separate claims.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Decision never labels VoIP as native carrier telephony and names emergency/certification limitations explicitly
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: cellular gate packet; supported claim level; partner/certification budget; unsupported/fallback behavior; stop/revisit criteria Verification: product, cellular, legal, regulatory, security and program review Evidence: signed decision; evidence links; public wording; updated roadmap Traceability: specs: AOS-PLAN-006#cellular-and-voice-criteria;AOS-HW-007#product-claim-levels; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-COMM

AOS-COMM-000 — Community and Ecosystem epic

Type / priority / status: Epic · P1 · Backlog Owner / workstream: Community Lead · Program Schedule: 2026-07-13 → 2030-01-20 · 3 estimated days · Continuous Parent: none Dependencies: none Related tasks: none

Outcome. Build contributor governance, partnerships, funding, and reproducible community hardware support.

Scope. Produce and integrate: project charter; milestone map; owned backlog; status/evidence dashboard. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Publish only releasable evidence and distinguish funded ownership, maintained support, community support, and experiments.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Project has one accountable lead, an approved scope, milestone links, and no orphaned P0/P1 work
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: project charter; milestone map; owned backlog; status/evidence dashboard Verification: monthly project review and gate reconciliation Evidence: project update; dependency report; risk and budget delta Traceability: specs: AOS-GOV-002#community-principles; sources: none; claims: none; experiments: none Phase / volume: Phase 8 · Volume 08 Specialist review: none

AOS-COMM-001 — Ratify governance and specification lifecycle

Type / priority / status: Decision · P0 · Backlog Owner / workstream: Community/Governance Lead · Governance Schedule: 2026-07-13 → 2026-08-09 · 8 estimated days · M0 Parent: AOS-COMM-000 Dependencies: none Related tasks: AOS-LEGAL-001;AOS-DOCS-012

Outcome. Establish decision authority, maintainer roles, change states, review requirements, conflicts, succession and public transparency.

Scope. Produce and integrate: governance charter; steering/maintainer scopes; decision/appeal/conflict rules; lifecycle policy. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Publish only releasable evidence and distinguish funded ownership, maintained support, community support, and experiments.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Decision authority and succession are explicit and no single actor can silently change license, trust roots or accepted architecture
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: governance charter; steering/maintainer scopes; decision/appeal/conflict rules; lifecycle policy Verification: founder/core-team/legal review and two simulated architecture/community disputes Evidence: ratified charter; role registry; exercise findings Traceability: specs: AOS-GOV-001#document-states;AOS-GOV-002#maintainer-model; sources: none; claims: none; experiments: none Phase / volume: Phase 8 · Volume 08 Specialist review: none

AOS-COMM-002 — Adopt code of conduct and moderation process

Type / priority / status: Task · P0 · Backlog Owner / workstream: Community Lead · Governance Schedule: 2026-07-13 → 2026-08-02 · 5 estimated days · M0 Parent: AOS-COMM-000 Dependencies: none Related tasks: AOS-COMM-001;AOS-LEGAL-001

Outcome. Create enforceable participation, reporting, moderation, appeal, privacy and conflict-of-interest rules for technical and community spaces.

Scope. Produce and integrate: code of conduct; reporting channels; response roles; moderation/appeal/confidentiality process. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Publish only releasable evidence and distinguish funded ownership, maintained support, community support, and experiments.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Reports have confidential intake, accountable response, appeal path and separation from technical gate authority
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: code of conduct; reporting channels; response roles; moderation/appeal/confidentiality process Verification: scenario review including harassment, unsafe instructions, provenance evasion and vendor conflict Evidence: approved policy; moderator roster/training; exercise notes Traceability: specs: AOS-GOV-002#decision-and-conduct; sources: none; claims: none; experiments: none Phase / volume: Phase 8 · Volume 08 Specialist review: none

AOS-COMM-003 — Publish contributor onboarding, DCO, and clean-room disclosure flow

Type / priority / status: Task · P0 · Backlog Owner / workstream: Developer Relations Lead · Contributors Schedule: 2026-07-20 → 2026-08-23 · 10 estimated days · M0 Parent: AOS-COMM-000 Dependencies: none Related tasks: AOS-COMM-001;AOS-LEGAL-003;AOS-LEGAL-005;AOS-DOCS-011

Outcome. Enable lawful, secure, architecture-aligned contributions with explicit source provenance and proprietary-exposure handling.

Scope. Produce and integrate: CONTRIBUTING; DCO check; source/proprietary exposure form; clean-room routing; issue/PR templates; reviewer map. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Publish only releasable evidence and distinguish funded ownership, maintained support, community support, and experiments.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • A contributor can determine permitted sources/tasks and disallowed/uncertain contributions are blocked before merge
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: CONTRIBUTING; DCO check; source/proprietary exposure form; clean-room routing; issue/PR templates; reviewer map Verification: new-contributor walkthrough and seeded missing signoff/unknown source/taint cases Evidence: onboarding report; CI results; routed scenario records Traceability: specs: AOS-GOV-002#contribution-path;AOS-LEGAL-002#contributor-onboarding;AOS-LEGAL-003#contributions; sources: none; claims: none; experiments: none Phase / volume: Phase 8 · Volume 08 Specialist review: none

AOS-COMM-004 — Publish evidence-based public roadmap and support labels

Type / priority / status: Task · P1 · Backlog Owner / workstream: Community Lead · Communications Schedule: 2026-08-03 → 2026-09-06 · 6 estimated days · M1 Parent: AOS-COMM-000 Dependencies: none Related tasks: AOS-DOCS-012;AOS-COMM-001

Outcome. Expose funded/owned work, hypotheses, gates, target support, limitations and stop decisions without promising unsupported phone features.

Scope. Produce and integrate: public roadmap view; support-level definitions; limitations dashboard; claim/experiment links; update cadence. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Publish only releasable evidence and distinguish funded ownership, maintained support, community support, and experiments.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Every public target/feature is labelled Reference/Maintained/Community/Experimental/Retired and ties to evidence or explicit hypothesis
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: public roadmap view; support-level definitions; limitations dashboard; claim/experiment links; update cadence Verification: architecture/product/legal review and reader comprehension sample Evidence: published preview; review record; corrected ambiguity list Traceability: specs: AOS-GOV-002#community-principles;AOS-PLAN-006#release-language; sources: none; claims: none; experiments: none Phase / volume: Phase 8 · Volume 08 Specialist review: none

AOS-COMM-010 — Build documentation site and Wiki publication pipeline

Type / priority / status: Task · P1 · Backlog Owner / workstream: Documentation/Web Lead · Documentation Schedule: 2026-08-10 → 2026-10-18 · 15 estimated days · M2 Parent: AOS-COMM-000 Dependencies: AOS-DOCS-011 Related tasks: AOS-COMM-003;AOS-LEGAL-002

Outcome. Publish searchable linked specifications, glossary, prior art, tasks, evidence and onboarding while keeping Git source authoritative.

Scope. Produce and integrate: site/wiki generator; navigation/search; version selector; xref/link validation; generated notices; deployment/release process. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Publish only releasable evidence and distinguish funded ownership, maintained support, community support, and experiments.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Public pages preserve canonical IDs/anchors and clearly identify generated status/version and non-final working name
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: site/wiki generator; navigation/search; version selector; xref/link validation; generated notices; deployment/release process Verification: build from clean source, crawl links, test mobile/accessibility/search/versioned anchors Evidence: site build; link/accessibility report; deployment manifest Traceability: specs: AOS-META-001#publishing-flow;AOS-META-004#generated-artifacts; sources: none; claims: none; experiments: none Phase / volume: Phase 8 · Volume 08 Specialist review: none

AOS-COMM-011 — Create contributor starter tasks and learning paths

Type / priority / status: Task · P2 · Backlog Owner / workstream: Developer Relations Lead · Contributors Schedule: 2027-03-22 → 2027-06-13 · 12 estimated days · M8 Parent: AOS-COMM-000 Dependencies: AOS-COMM-003;AOS-DOCS-006 Related tasks: AOS-PLAT-090

Outcome. Turn architecture, docs, tests, emulation and hardware evidence into safe bounded entry points by skill level.

Scope. Produce and integrate: starter issue set; kernel/platform/product/docs/hardware learning paths; mentor/reviewer assignment; expected evidence. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Publish only releasable evidence and distinguish funded ownership, maintained support, community support, and experiments.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Starter tasks do not require private artifacts, have tests/acceptance, and leave an owned maintainable result
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: starter issue set; kernel/platform/product/docs/hardware learning paths; mentor/reviewer assignment; expected evidence Verification: three external-style contributors complete different paths with measured friction Evidence: onboarding timings; issue outcomes; documentation fixes; mentor capacity report Traceability: specs: AOS-GOV-002#community-infrastructure;AOS-PLAN-003#completion-rules; sources: none; claims: none; experiments: none Phase / volume: Phase 8 · Volume 08 Specialist review: none

AOS-COMM-020 — Run prioritized technical and vendor outreach campaign

Type / priority / status: Contact · P1 · Backlog Owner / workstream: Partnerships Lead · Partnerships Schedule: 2026-08-10 → 2027-04-18 · 15 estimated days · M5 Parent: AOS-COMM-000 Dependencies: AOS-DOCS-010;AOS-OPEN-001 Related tasks: AOS-LEGAL-011

Outcome. Contact capability experts, board/silicon vendors, open-phone communities, camera/modem vendors, labs and funding programs with precise asks.

Scope. Produce and integrate: contact dossiers; private contact register; outreach/follow-up; response/commitment matrix; fallback tasks. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Publish only releasable evidence and distinguish funded ownership, maintained support, community support, and experiments.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Every outreach has one owner, precise ask, desired artifact/agreement, deadline and fallback
  • no personal/NDA data enters public docs
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: contact dossiers; private contact register; outreach/follow-up; response/commitment matrix; fallback tasks Verification: monthly review of response quality, commitments, artifacts/restrictions and next actions Evidence: public-safe outcome log; partner response score; agreements/tasks created Traceability: specs: AOS-LEGAL-005#priority-contacts;AOS-LEGAL-005#contact-sequence; sources: none; claims: none; experiments: none Phase / volume: Phase 8 · Volume 08 Specialist review: none

AOS-COMM-021 — Commission capability/microkernel architecture review

Type / priority / status: Contact · P1 · Backlog Owner / workstream: Architecture Council · Expert Review Schedule: 2026-11-30 → 2027-02-21 · 8 estimated days · M2 Parent: AOS-COMM-000 Dependencies: none Related tasks: AOS-CORE-032;AOS-SEC-010;AOS-COMM-020

Outcome. Obtain expert feedback on object, capability, IPC, revocation, scheduling, resource and assurance semantics before public API stabilization.

Scope. Produce and integrate: review brief; model/code/evidence access; written findings; response/ADR changes; ongoing relationship proposal. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Publish only releasable evidence and distinguish funded ownership, maintained support, community support, and experiments.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Critical semantics are reviewed outside the implementation team and disagreements become tests/ADRs rather than informal opinion
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: review brief; model/code/evidence access; written findings; response/ADR changes; ongoing relationship proposal Verification: reviewer independence/qualifications and finding closure review Evidence: review report; disposition matrix; API changes; public summary where allowed Traceability: specs: AOS-ARCH-002#assurance-boundary;AOS-ARCH-004#security-properties; sources: none; claims: none; experiments: none Phase / volume: Phase 2 · Volume 08 Specialist review: none

AOS-COMM-030 — Create grant and sponsor pipeline

Type / priority / status: Task · P1 · Backlog Owner / workstream: Funding Lead · Funding Schedule: 2026-08-24 → 2027-01-10 · 10 estimated days · M3 Parent: AOS-COMM-000 Dependencies: AOS-COMM-001;AOS-DOCS-009 Related tasks: AOS-LEGAL-009

Outcome. Identify aligned public-interest, research, hardware and commercial funding with transparent scope, IP/governance and reporting cost.

Scope. Produce and integrate: funder database; eligibility/calendar; reusable proposal materials; conflict/IP checklist; application priorities. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Publish only releasable evidence and distinguish funded ownership, maintained support, community support, and experiments.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • No funding term controls license/trust/architecture secretly and every promised deliverable maps to owned tasks/gates
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: funder database; eligibility/calendar; reusable proposal materials; conflict/IP checklist; application priorities Verification: review at least ten candidates and submit only evidence-backed scoped proposals Evidence: pipeline; submissions/results; reporting burden and conflict assessments Traceability: specs: AOS-GOV-003#funding-sources;AOS-GOV-003#transparency; sources: none; claims: none; experiments: none Phase / volume: Phase 8 · Volume 08 Specialist review: none

AOS-COMM-031 — Adopt sponsorship and commercial-conflict policy

Type / priority / status: Task · P1 · Backlog Owner / workstream: Governance/Legal Lead · Funding Schedule: 2026-08-24 → 2026-10-18 · 6 estimated days · M3 Parent: AOS-COMM-000 Dependencies: AOS-COMM-001;AOS-LEGAL-001 Related tasks: none

Outcome. Define disclosure, recusal, technical independence, branding, data, exclusivity and public-reporting rules for sponsors and partners.

Scope. Produce and integrate: sponsor policy; agreement checklist; disclosure/recusal register; prohibited control terms; public acknowledgement rules. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Publish only releasable evidence and distinguish funded ownership, maintained support, community support, and experiments.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • A sponsor cannot suppress evidence, alter support claims, obtain hidden roadmap priority or control security disclosure
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: sponsor policy; agreement checklist; disclosure/recusal register; prohibited control terms; public acknowledgement rules Verification: tabletop vendor-funded target and security finding scenarios Evidence: approved policy; exercise findings; disclosure template Traceability: specs: AOS-GOV-003#funding-principles;AOS-GOV-003#transparency; sources: none; claims: none; experiments: none Phase / volume: Phase 8 · Volume 08 Specialist review: none

AOS-COMM-040 — Launch bounded bounty program after review capacity exists

Type / priority / status: Task · P2 · Backlog Owner / workstream: Community Funding Lead · Bounties Schedule: 2027-08-09 → 2027-11-28 · 10 estimated days · M8 Parent: AOS-COMM-000 Dependencies: AOS-COMM-011;AOS-COMM-031;AOS-LEGAL-009 Related tasks: AOS-SEC-090

Outcome. Fund well-specified tests, drivers, tooling, documentation and experiments without incentivizing unsafe or legally uncertain work.

Scope. Produce and integrate: bounty policy/templates; review/payment/tax/sanctions flow; initial bounded bounties; maintainer assignments; dispute path. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Publish only releasable evidence and distinguish funded ownership, maintained support, community support, and experiments.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Bounties have tests/evidence/legal source class and a maintainer
  • Pixel/IMS/security-critical unknowns are excluded unless specifically reviewed
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: bounty policy/templates; review/payment/tax/sanctions flow; initial bounded bounties; maintainer assignments; dispute path Verification: pilot two low-risk bounties through acceptance/payment/maintenance handoff Evidence: pilot records; review hours; quality/maintenance outcomes; policy changes Traceability: specs: AOS-GOV-003#bounty-policy;AOS-LEGAL-002#source-classes; sources: none; claims: none; experiments: none Phase / volume: Phase 8 · Volume 08 Specialist review: none

AOS-COMM-050 — Establish hardware maintainer and CI specimen program

Type / priority / status: Task · P1 · Backlog Owner / workstream: Community Hardware Lead · Hardware Community Schedule: 2027-06-14 → 2027-10-03 · 12 estimated days · M8 Parent: AOS-COMM-000 Dependencies: AOS-OPEN-001;AOS-COMM-001 Related tasks: AOS-PLAT-080

Outcome. Assign target owners, support levels, specimens, revisions, lab access, release tests, security/update responsibility and succession.

Scope. Produce and integrate: maintainer charter; target owner/revision/specimen registry; CI/lab schedule; support/deprecation process; access/safety training. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Publish only releasable evidence and distinguish funded ownership, maintained support, community support, and experiments.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • No target is Maintained without owner, tested specimen/revision, recovery, release tests, update path and successor/deprecation plan
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: maintainer charter; target owner/revision/specimen registry; CI/lab schedule; support/deprecation process; access/safety training Verification: audit each maintained target and simulate maintainer departure/revision change/security update Evidence: target ownership matrix; succession drill; support status dashboard Traceability: specs: AOS-GOV-002#hardware-maintainers;AOS-HW-001#support-levels; sources: none; claims: none; experiments: none Phase / volume: Phase 8 · Volume 08 Specialist review: none

AOS-COMM-060 — Run external community hardware-kit reproduction pilot

Type / priority / status: Experiment · P0 · Backlog Owner / workstream: Community Hardware Lead · Hardware Community Schedule: 2029-01-22 → 2029-06-10 · 15 estimated days · M10 Parent: AOS-COMM-000 Dependencies: AOS-OPEN-060;AOS-COMM-050;AOS-PLAT-090;AOS-COMM-010 Related tasks: none

Outcome. Have independent maintainers build, flash, boot, test, update and recover the selected kit from public documentation and tools.

Scope. Produce and integrate: pilot cohort; kits or purchase guidance; onboarding support; issue/reproduction metrics; maintainer sign-off; revised docs. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Publish only releasable evidence and distinguish funded ownership, maintained support, community support, and experiments.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • External participants reproduce supported outcomes without private help/artifacts and resulting maintenance ownership is explicit
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: pilot cohort; kits or purchase guidance; onboarding support; issue/reproduction metrics; maintainer sign-off; revised docs Verification: EXP-090 by multiple independent environments and at least one non-core maintainer Evidence: onboarding/test/recovery logs; issue statistics; EXP-090 record Traceability: specs: AOS-GOV-002#hardware-maintainers;AOS-HW-008#community-reference-kit; sources: none; claims: CLM-021; experiments: EXP-090 Phase / volume: Phase 8 · Volume 08 Specialist review: none

AOS-COMM-070 — Establish translation and accessibility contribution workflow

Type / priority / status: Task · P2 · Backlog Owner / workstream: Localization/Accessibility Community Lead · Inclusive Community Schedule: 2027-08-09 → 2027-12-12 · 10 estimated days · M8 Parent: AOS-COMM-000 Dependencies: AOS-PROD-070;AOS-COMM-003 Related tasks: AOS-PROD-071

Outcome. Enable reviewed translations, terminology, pseudolocalization fixes, accessibility audits and assistive-technology contributions with safe release ownership.

Scope. Produce and integrate: translation platform/process; glossary/term memory; review roles; accessibility issue templates; locale release gates. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Publish only releasable evidence and distinguish funded ownership, maintained support, community support, and experiments.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Safety/recovery/legal language has qualified review and no locale is marked supported solely from machine translation
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: translation platform/process; glossary/term memory; review roles; accessibility issue templates; locale release gates Verification: pilot two non-English locales and one assistive-technology contribution through release Evidence: translation quality/review report; accessibility fix; contributor feedback Traceability: specs: AOS-PROD-005#localization;AOS-PROD-005#acceptance-requirements; sources: none; claims: none; experiments: none Phase / volume: Phase 8 · Volume 08 Specialist review: none

AOS-COMM-080 — Publish security contact, safe-harbor, and researcher workflow

Type / priority / status: Task · P0 · Backlog Owner / workstream: Security Community Manager · Security Community Schedule: 2026-09-07 → 2026-10-18 · 6 estimated days · M2 Parent: AOS-COMM-000 Dependencies: AOS-LEGAL-001 Related tasks: AOS-SEC-090;AOS-COMM-010

Outcome. Give researchers a clear private reporting and authorized-testing path aligned with incident response and legal constraints.

Scope. Produce and integrate: security.txt; contact/key; supported-scope page; safe-harbor policy; acknowledgement/coordination templates. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Publish only releasable evidence and distinguish funded ownership, maintained support, community support, and experiments.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Researchers can report privately, know authorized scope/response expectations, and reports reach accountable technical/security owners
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: security.txt; contact/key; supported-scope page; safe-harbor policy; acknowledgement/coordination templates Verification: seed report from public page through triage and coordinated response Evidence: exercise metrics; policy/legal approval; public page/archive Traceability: specs: AOS-GOV-004#reporting-vulnerabilities;AOS-GOV-004#researcher-safe-harbor; sources: none; claims: none; experiments: none Phase / volume: Phase 1 · Volume 04 Specialist review: none

AOS-COMM-090 — Prepare evidence-backed public project launch

Type / priority / status: Decision · P1 · Backlog Owner / workstream: Program/Community Lead · Launch Schedule: 2026-10-05 → 2026-12-13 · 12 estimated days · M2 Parent: AOS-COMM-000 Dependencies: AOS-LEGAL-002;AOS-COMM-003;AOS-COMM-004;AOS-CORE-010 Related tasks: AOS-COMM-010;AOS-COMM-080

Outcome. Publish the cleared brand, mission, architecture, limitations, governance, licenses, security contact, roadmap, starter paths and reproducible first artifact.

Scope. Produce and integrate: launch checklist/site/repositories; first reproducible image/test; press/FAQ; trademark/no-endorsement notices; limitations/support. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Publish only releasable evidence and distinguish funded ownership, maintained support, community support, and experiments.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Launch makes no phone/daily-driver/Pixel/carrier/security claim beyond evidence and contributors can reproduce the announced artifact
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: launch checklist/site/repositories; first reproducible image/test; press/FAQ; trademark/no-endorsement notices; limitations/support Verification: legal/security/architecture/product/community launch review and external fresh-clone test Evidence: signed launch decision; reproducibility result; claim audit; issue response plan Traceability: specs: AOS-LEGAL-006#communications-standard;AOS-README#repository-artifacts; sources: none; claims: none; experiments: none Phase / volume: Phase 8 · Volume 08 Specialist review: none

AOS-COMM-100 — Build the prioritized partner and specialist contact graph

Type / priority / status: Task · P1 · Planned Owner / workstream: Partnerships Lead · Contact Acquisition Schedule: 2026-08-10 → 2026-09-20 · 15 estimated days · M1 Parent: AOS-COMM-000 Dependencies: none Related tasks: none

Outcome. Build the prioritized partner and specialist contact graph.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-GOV-006#categories, AOS-LEGAL-005#contact-groups. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Build the prioritized partner and specialist contact graph; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-GOV-006#categories;AOS-LEGAL-005#priority-contacts; sources: none; claims: none; experiments: none Phase / volume: Phase 1 · Volume 08 Specialist review: none

AOS-COMM-101 — Prepare role-specific outreach packets and evidence briefs

Type / priority / status: Task · P1 · Planned Owner / workstream: Partnerships Lead · Outreach Schedule: 2026-08-24 → 2026-10-04 · 15 estimated days · M1 Parent: AOS-COMM-000 Dependencies: none Related tasks: none

Outcome. Prepare role-specific outreach packets and evidence briefs.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-GOV-006#packet, AOS-PLAN-015#briefing. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Prepare role-specific outreach packets and evidence briefs; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-GOV-006#outreach;AOS-PLAN-015#briefing; sources: none; claims: none; experiments: none Phase / volume: Phase 1 · Volume 08 Specialist review: none

AOS-COMM-102 — Recruit initial kernel, camera, hardware, legal, and documentation advisers

Type / priority / status: Contact · P0 · Planned Owner / workstream: Project Lead · Adviser Network Schedule: 2026-09-07 → 2026-11-15 · 25 estimated days · M2 Parent: AOS-COMM-000 Dependencies: none Related tasks: none

Outcome. Recruit initial kernel, camera, hardware, legal, and documentation advisers.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-GOV-006#prioritization, AOS-GOV-005#maintainers. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Recruit initial kernel, camera, hardware, legal, and documentation advisers; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-GOV-006#qualification;AOS-GOV-005#maintainers; sources: none; claims: none; experiments: none Phase / volume: Phase 1 · Volume 08 Specialist review: none

AOS-COMM-103 — Publish an honest public roadmap and contribution boundary

Type / priority / status: Task · P1 · Planned Owner / workstream: Community Lead · Community Launch Schedule: 2027-10-18 → 2027-12-12 · 20 estimated days · M8 Parent: AOS-COMM-000 Dependencies: none Related tasks: none

Outcome. Publish an honest public roadmap and contribution boundary.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-GOV-005#launch-gates, AOS-GOV-005#roadmap. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Publish an honest public roadmap and contribution boundary; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-GOV-005#launch-gate;AOS-GOV-005#narrative; sources: none; claims: none; experiments: none Phase / volume: Phase 8 · Volume 08 Specialist review: none

AOS-COMM-104 — Create university and research-lab collaboration proposals

Type / priority / status: Contact · P2 · Planned Owner / workstream: Research Lead · Research Partnerships Schedule: 2027-11-15 → 2028-02-06 · 30 estimated days · M10 Parent: AOS-COMM-000 Dependencies: none Related tasks: none

Outcome. Create university and research-lab collaboration proposals.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-GOV-006#categories, AOS-RES-009#reproduction. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Create university and research-lab collaboration proposals; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-GOV-006#categories;AOS-RES-009#reproduction; sources: none; claims: none; experiments: none Phase / volume: Phase 8 · Volume 08 Specialist review: none

AOS-CORE

AOS-CORE-000 — Microkernel Core epic

Type / priority / status: Epic · P1 · Backlog Owner / workstream: Kernel Lead · Program Schedule: 2026-07-13 → 2028-07-09 · 3 estimated days · Continuous Parent: none Dependencies: none Related tasks: none

Outcome. Implement and assure the native Agent OS microkernel and architecture ports.

Scope. Produce and integrate: project charter; milestone map; owned backlog; status/evidence dashboard. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep policy, drivers, compatibility, filesystems, networking, graphics, and product behavior outside the minimal kernel boundary.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Project has one accountable lead, an approved scope, milestone links, and no orphaned P0/P1 work
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: project charter; milestone map; owned backlog; status/evidence dashboard Verification: monthly project review and gate reconciliation Evidence: project update; dependency report; risk and budget delta Traceability: specs: AOS-ARCH-002#kernel-scope; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-CORE-001 — Freeze executable kernel semantics v0

Type / priority / status: Task · P0 · Backlog Owner / workstream: Kernel Lead · Kernel Semantics Schedule: 2026-07-20 → 2026-08-16 · 12 estimated days · M1 Parent: AOS-CORE-000 Dependencies: none Related tasks: AOS-DOCS-012

Outcome. Translate kernel object, authority, lifecycle, error, concurrency, and resource rules into executable reference models and tests.

Scope. Produce and integrate: reference model; object/state diagrams; syscall draft; property catalog; unsafe invariants. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep policy, drivers, compatibility, filesystems, networking, graphics, and product behavior outside the minimal kernel boundary.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Objects, rights, lifetime, cancellation, errors, and resource ownership are unambiguous before implementation expands
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: reference model; object/state diagrams; syscall draft; property catalog; unsafe invariants Verification: model review and property tests including invalid transitions Evidence: model test report; approved semantics record Traceability: specs: AOS-ARCH-002#kernel-objects;AOS-ARCH-004#capability-semantics;AOS-ADR-0001#decision; sources: SRC-001;SRC-002;SRC-003;SRC-007;SRC-008; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-CORE-002 — Establish freestanding Rust toolchain and target definitions

Type / priority / status: Task · P0 · Backlog Owner / workstream: Kernel Build Engineer · Build Schedule: 2026-07-13 → 2026-08-02 · 8 estimated days · M1 Parent: AOS-CORE-000 Dependencies: none Related tasks: AOS-DOCS-001;AOS-LEGAL-012

Outcome. Produce reproducible no_std builds for AArch64 and x86-64 with controlled compiler/linker/runtime inputs.

Scope. Produce and integrate: toolchain manifest; target JSON; linker scripts; runtime stubs; container/runner; symbol artifacts. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep policy, drivers, compatibility, filesystems, networking, graphics, and product behavior outside the minimal kernel boundary.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • A contributor can build both targets from a documented fresh environment without host libraries leaking into images
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: toolchain manifest; target JSON; linker scripts; runtime stubs; container/runner; symbol artifacts Verification: clean builds on two runners with matching declared inputs and bootable images Evidence: build manifests; hashes; compiler/linker versions; CI logs Traceability: specs: AOS-ARCH-002#implementation-language;AOS-ARCH-015#reproducible-builds; sources: none; claims: none; experiments: none Phase / volume: Phase 4 · Volume 02 Specialist review: none

AOS-CORE-010 — Boot Agent OS in QEMU AArch64

Type / priority / status: Experiment · P0 · Backlog Owner / workstream: AArch64 Kernel Engineer · AArch64 Schedule: 2026-07-20 → 2026-08-23 · 12 estimated days · M1 Parent: AOS-CORE-000 Dependencies: none Related tasks: AOS-CORE-002;AOS-CORE-001

Outcome. Reach deterministic structured early console, boot-info parsing, memory discovery, and controlled halt on the primary emulated architecture.

Scope. Produce and integrate: QEMU virt boot path; early console; boot manifest parser; panic/halt path; CI launcher. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep policy, drivers, compatibility, filesystems, networking, graphics, and product behavior outside the minimal kernel boundary.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • AArch64 image boots in CI, emits machine-parseable stages, rejects invalid descriptors, and halts without undefined reset loops
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: QEMU virt boot path; early console; boot manifest parser; panic/halt path; CI launcher Verification: EXP-001 across repeated clean CI runs and malformed boot descriptors Evidence: UART logs; build manifests; reproducibility comparison; EXP-001 record Traceability: specs: AOS-ARCH-002#boot-and-architecture;AOS-ARCH-015#emulation; sources: none; claims: CLM-001; experiments: EXP-001 Phase / volume: Phase 5 · Volume 02 Specialist review: none

AOS-CORE-011 — Boot Agent OS in QEMU x86-64

Type / priority / status: Experiment · P1 · Backlog Owner / workstream: x86-64 Kernel Engineer · x86-64 Schedule: 2026-08-03 → 2026-09-13 · 12 estimated days · M1 Parent: AOS-CORE-000 Dependencies: AOS-CORE-002 Related tasks: AOS-CORE-010

Outcome. Prove architecture separation with a second ISA and the same kernel object/service semantics.

Scope. Produce and integrate: x86-64 boot/console/interrupt skeleton; shared architecture traits; conformance harness. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep policy, drivers, compatibility, filesystems, networking, graphics, and product behavior outside the minimal kernel boundary.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Both ISAs execute the same architecture-independent kernel tests and target-specific code remains under declared modules
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: x86-64 boot/console/interrupt skeleton; shared architecture traits; conformance harness Verification: EXP-002 and source-dependency comparison against AArch64 Evidence: boot logs; architecture boundary report; EXP-002 record Traceability: specs: AOS-ARCH-002#boot-and-architecture;AOS-ARCH-001#portability-test; sources: none; claims: CLM-002; experiments: EXP-002 Phase / volume: Phase 5 · Volume 02 Specialist review: none

AOS-CORE-012 — Define boot handoff and platform description contract

Type / priority / status: Task · P0 · Backlog Owner / workstream: Kernel Architect · Boot Schedule: 2026-07-27 → 2026-08-23 · 7 estimated days · M1 Parent: AOS-CORE-000 Dependencies: none Related tasks: AOS-CORE-010

Outcome. Specify the trusted data passed from loader/firmware into the kernel without binding to one firmware or device tree representation.

Scope. Produce and integrate: boot handoff schema; memory/CPU/device seed records; integrity/version rules; parser tests. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep policy, drivers, compatibility, filesystems, networking, graphics, and product behavior outside the minimal kernel boundary.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • UEFI, device tree, board loader, or future secure loader can normalize into one versioned bounded handoff
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: boot handoff schema; memory/CPU/device seed records; integrity/version rules; parser tests Verification: fuzz parser and adapt both QEMU architectures without changing kernel-neutral fields Evidence: schema; fuzz report; compatibility test Traceability: specs: AOS-ARCH-002#boot-and-architecture;AOS-ARCH-013#boot-chain; sources: none; claims: none; experiments: none Phase / volume: Phase 2 · Volume 02 Specialist review: none

AOS-CORE-013 — Implement physical memory manager

Type / priority / status: Task · P0 · Backlog Owner / workstream: Kernel Memory Engineer · Memory Schedule: 2026-08-03 → 2026-09-13 · 12 estimated days · M1 Parent: AOS-CORE-000 Dependencies: none Related tasks: AOS-CORE-012

Outcome. Track usable, reserved, device, firmware, secure, persistent, and crash memory with bounded allocation behavior.

Scope. Produce and integrate: frame allocator; region database; reservation API; poisoning/debug modes; statistics. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep policy, drivers, compatibility, filesystems, networking, graphics, and product behavior outside the minimal kernel boundary.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • No frame is simultaneously owned, reserved frames are never allocated, exhaustion is explicit, and statistics reconcile
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: frame allocator; region database; reservation API; poisoning/debug modes; statistics Verification: property tests, exhaustion, overlap, fragmentation and malformed-map tests Evidence: allocation invariant report; stress logs; memory map artifacts Traceability: specs: AOS-ARCH-003#physical-memory;AOS-ARCH-012#memory-safety; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-CORE-014 — Implement virtual address spaces and mappings

Type / priority / status: Task · P0 · Backlog Owner / workstream: Kernel Memory Engineer · Memory Schedule: 2026-08-10 → 2026-10-04 · 16 estimated days · M1 Parent: AOS-CORE-000 Dependencies: none Related tasks: AOS-CORE-013

Outcome. Create architecture-independent address-space objects with explicit mapping rights, ownership, invalidation, and teardown.

Scope. Produce and integrate: address-space object; page-table backends; map/unmap/protect; shootdown hooks; tests. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep policy, drivers, compatibility, filesystems, networking, graphics, and product behavior outside the minimal kernel boundary.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Mappings cannot exceed memory-object rights, stale translations are invalidated, and teardown returns every owned resource
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: address-space object; page-table backends; map/unmap/protect; shootdown hooks; tests Verification: randomized mapping model comparison and permission/fault tests on both QEMU targets Evidence: differential test report; fault traces; leak accounting Traceability: specs: AOS-ARCH-003#address-spaces;AOS-ARCH-004#memory-capabilities; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-CORE-015 — Enter user mode and launch initial process

Type / priority / status: Task · P0 · Backlog Owner / workstream: Kernel Runtime Engineer · Processes Schedule: 2026-08-24 → 2026-10-04 · 12 estimated days · M1 Parent: AOS-CORE-000 Dependencies: none Related tasks: AOS-CORE-014;AOS-CORE-016

Outcome. Load a signed/test user image, create its address space and handles, enter user mode, and receive syscalls/exceptions safely.

Scope. Produce and integrate: image loader subset; initial process creation; user entry/exit; syscall ABI; startup handle table. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep policy, drivers, compatibility, filesystems, networking, graphics, and product behavior outside the minimal kernel boundary.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • User code cannot execute with kernel privilege, malformed images fail before execution, and startup authority is explicit
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: image loader subset; initial process creation; user entry/exit; syscall ABI; startup handle table Verification: launch valid/invalid images, fault user code, and inspect isolation/crash artifacts Evidence: user boot trace; invalid-image results; syscall conformance log Traceability: specs: AOS-ARCH-003#process-model;AOS-ARCH-013#initial-system-image; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-CORE-016 — Implement exceptions, interrupts, timers, and CPU-local state

Type / priority / status: Task · P0 · Backlog Owner / workstream: Kernel Architecture Engineer · Architecture Schedule: 2026-08-03 → 2026-09-20 · 15 estimated days · M1 Parent: AOS-CORE-000 Dependencies: none Related tasks: AOS-CORE-010;AOS-CORE-011

Outcome. Handle synchronous faults, interrupts, timers, inter-processor hooks, and per-CPU state through bounded architecture backends.

Scope. Produce and integrate: vector/IDT code; exception frames; interrupt controller abstraction; monotonic timer; CPU-local storage. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep policy, drivers, compatibility, filesystems, networking, graphics, and product behavior outside the minimal kernel boundary.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Fault origin and recovery policy are explicit, timer is monotonic within contract, and unhandled interrupts cannot livelock silently
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: vector/IDT code; exception frames; interrupt controller abstraction; monotonic timer; CPU-local storage Verification: inject each exception/IRQ class, timer wrap/bounds, nested/disabled states and malformed returns Evidence: interrupt/fault matrix; latency samples; architecture review Traceability: specs: AOS-ARCH-003#exceptions-and-interrupts;AOS-ARCH-003#time; sources: none; claims: none; experiments: none Phase / volume: Phase 2 · Volume 02 Specialist review: none

AOS-CORE-017 — Implement kernel object and lifetime framework

Type / priority / status: Task · P0 · Backlog Owner / workstream: Kernel Runtime Engineer · Kernel Objects Schedule: 2026-08-17 → 2026-09-27 · 12 estimated days · M2 Parent: AOS-CORE-000 Dependencies: AOS-CORE-001 Related tasks: AOS-CORE-013

Outcome. Provide typed reference-counted kernel objects with stable IDs, rights checks, wait signals, destruction, and diagnostic state.

Scope. Produce and integrate: object base; type registry; lifecycle hooks; signals; object stats; tests. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep policy, drivers, compatibility, filesystems, networking, graphics, and product behavior outside the minimal kernel boundary.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Object destruction is deterministic under the contract, stale handles fail, and object resources reconcile after stress
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: object base; type registry; lifecycle hooks; signals; object stats; tests Verification: lifetime/refcount/model properties, concurrent close/use, and leak detection Evidence: object lifecycle report; sanitizer/model logs; object inventory Traceability: specs: AOS-ARCH-002#kernel-objects;AOS-ARCH-004#object-rights; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-CORE-018 — Implement process and thread lifecycle

Type / priority / status: Task · P0 · Backlog Owner / workstream: Kernel Runtime Engineer · Processes Schedule: 2026-08-31 → 2026-10-18 · 15 estimated days · M2 Parent: AOS-CORE-000 Dependencies: none Related tasks: AOS-CORE-015;AOS-CORE-017

Outcome. Create, start, stop, kill, wait, inspect, and reap processes/threads with bounded authority and resources.

Scope. Produce and integrate: process/thread objects; lifecycle syscalls; exit reasons; parent/job ownership; reaper. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep policy, drivers, compatibility, filesystems, networking, graphics, and product behavior outside the minimal kernel boundary.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Every lifecycle transition has one outcome, waiters observe consistent exit state, and terminated work cannot retain authority
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: process/thread objects; lifecycle syscalls; exit reasons; parent/job ownership; reaper Verification: state-machine tests, concurrent kill/wait, crash storms, orphan/reaping and quota tests Evidence: lifecycle trace; stress report; resource reconciliation Traceability: specs: AOS-ARCH-003#process-model;AOS-ARCH-003#thread-model; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-CORE-020 — Prove user-process isolation and fault containment

Type / priority / status: Experiment · P0 · Backlog Owner / workstream: Kernel Security Engineer · Isolation Schedule: 2026-09-14 → 2026-10-11 · 8 estimated days · M1 Parent: AOS-CORE-000 Dependencies: none Related tasks: AOS-CORE-014;AOS-CORE-018

Outcome. Demonstrate that memory, illegal instruction, syscall, resource, and crash faults remain within defined process/job boundaries.

Scope. Produce and integrate: fault injector; adversarial user programs; kernel-integrity checks; crash evidence. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep policy, drivers, compatibility, filesystems, networking, graphics, and product behavior outside the minimal kernel boundary.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Faulting process terminates or receives a defined exception without reading/writing another address space or destabilizing kernel progress
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: fault injector; adversarial user programs; kernel-integrity checks; crash evidence Verification: EXP-003 across both QEMU architectures Evidence: fault traces; kernel/state integrity report; EXP-003 record Traceability: specs: AOS-ARCH-003#fault-containment;AOS-ARCH-012#isolation-goals; sources: none; claims: CLM-001; experiments: EXP-003 Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-CORE-021 — Implement monotonic time, deadlines, and timer objects

Type / priority / status: Task · P1 · Backlog Owner / workstream: Kernel Runtime Engineer · Time Schedule: 2026-09-07 → 2026-10-11 · 9 estimated days · M2 Parent: AOS-CORE-000 Dependencies: none Related tasks: AOS-CORE-016;AOS-CORE-017

Outcome. Expose monotonic clocks, bounded deadlines, cancellation, timer objects, and time-source quality to user space.

Scope. Produce and integrate: clock API; timer object; deadline queue; cancellation; calibration/quality fields. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep policy, drivers, compatibility, filesystems, networking, graphics, and product behavior outside the minimal kernel boundary.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Deadlines use one documented monotonic domain, cancellation has a defined race outcome, and timer resources are quota-accounted
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: clock API; timer object; deadline queue; cancellation; calibration/quality fields Verification: ordering, cancellation races, overflow, suspend adjustment contract and load tests Evidence: timer conformance; latency/error histograms; race test logs Traceability: specs: AOS-ARCH-003#time;AOS-ARCH-007#time-service; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-CORE-022 — Implement baseline scheduler

Type / priority / status: Task · P0 · Backlog Owner / workstream: Kernel Scheduling Engineer · Scheduling Schedule: 2026-09-21 → 2026-11-22 · 18 estimated days · M2 Parent: AOS-CORE-000 Dependencies: none Related tasks: AOS-CORE-018;AOS-CORE-021

Outcome. Schedule runnable threads with bounded classes, fairness, affinity, accounting, preemption, and idle behavior.

Scope. Produce and integrate: run queues; priority/weight classes; preemption; affinity; CPU-time accounting; idle hooks. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep policy, drivers, compatibility, filesystems, networking, graphics, and product behavior outside the minimal kernel boundary.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Runnable work makes progress under policy, CPU accounting reconciles, and class/priority behavior is documented rather than accidental
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: run queues; priority/weight classes; preemption; affinity; CPU-time accounting; idle hooks Verification: deterministic model tests plus fairness, starvation, latency and overload workloads Evidence: scheduler traces; latency/fairness report; accounting reconciliation Traceability: specs: AOS-ARCH-003#scheduler;AOS-ARCH-014#scheduler-energy-contract; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-CORE-023 — Implement synchronization primitives and futex-like wait

Type / priority / status: Task · P0 · Backlog Owner / workstream: Kernel Concurrency Engineer · Synchronization Schedule: 2026-10-05 → 2026-11-22 · 14 estimated days · M2 Parent: AOS-CORE-000 Dependencies: none Related tasks: AOS-CORE-021;AOS-CORE-022

Outcome. Provide minimal kernel-assisted blocking for user-space mutexes/conditions with cancellation and priority policy.

Scope. Produce and integrate: wait-on-word primitive; wake/requeue; robust cancellation; ownership metadata; tests. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep policy, drivers, compatibility, filesystems, networking, graphics, and product behavior outside the minimal kernel boundary.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • No lost wakeup under specified memory ordering, wait is tied to mapped ownership, and cancellation/exit cannot strand kernel resources
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: wait-on-word primitive; wake/requeue; robust cancellation; ownership metadata; tests Verification: race model, lost-wakeup, ABA/address reuse, timeout, process exit and contention tests Evidence: concurrency test report; scheduler traces; invariant notes Traceability: specs: AOS-ARCH-003#synchronization;AOS-ARCH-003#priority-inversion; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-CORE-030 — Implement capability spaces and handle operations

Type / priority / status: Task · P0 · Backlog Owner / workstream: Kernel Capability Engineer · Capabilities Schedule: 2026-09-14 → 2026-11-01 · 15 estimated days · M2 Parent: AOS-CORE-000 Dependencies: none Related tasks: AOS-CORE-017;AOS-CORE-018

Outcome. Represent explicit per-process authority with typed handles, rights, duplication, transfer preparation, close, and introspection.

Scope. Produce and integrate: capability space; handle encoding; rights/type checks; duplicate/close; audit hooks; tests. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep policy, drivers, compatibility, filesystems, networking, graphics, and product behavior outside the minimal kernel boundary.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Handles cannot be forged or widened, type/rights checks precede use, and table exhaustion/failure is bounded
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: capability space; handle encoding; rights/type checks; duplicate/close; audit hooks; tests Verification: model comparison, stale/forged handles, concurrency, exhaustion and enumeration-authority tests Evidence: capability conformance report; fuzz corpus; audit sample Traceability: specs: AOS-ARCH-004#capability-semantics;AOS-ARCH-004#handle-tables; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-CORE-031 — Implement synchronous IPC channel and message transfer

Type / priority / status: Task · P0 · Backlog Owner / workstream: Kernel IPC Engineer · IPC Schedule: 2026-10-05 → 2026-11-29 · 18 estimated days · M2 Parent: AOS-CORE-000 Dependencies: none Related tasks: AOS-CORE-030;AOS-CORE-023

Outcome. Transfer bounded typed bytes and capabilities between endpoints with clear ownership, cancellation, timeout, and peer-close behavior.

Scope. Produce and integrate: channel endpoint object; send/call/reply; handle transfer; buffers; cancellation; peer signals. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep policy, drivers, compatibility, filesystems, networking, graphics, and product behavior outside the minimal kernel boundary.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • A handle has one defined owner after transfer, malformed messages cannot mutate authority, and blocked calls terminate under timeout/peer death
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: channel endpoint object; send/call/reply; handle transfer; buffers; cancellation; peer signals Verification: message/handle fuzzing, races, peer death, timeout, quota and model tests Evidence: IPC conformance; throughput/latency baseline; fault traces Traceability: specs: AOS-ARCH-004#ipc-model;AOS-ARCH-005#wire-format; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-CORE-032 — Implement rights attenuation, delegation, and revocation model

Type / priority / status: Experiment · P0 · Backlog Owner / workstream: Kernel Capability Engineer · Capabilities Schedule: 2026-10-26 → 2026-12-20 · 15 estimated days · M2 Parent: AOS-CORE-000 Dependencies: none Related tasks: AOS-CORE-030;AOS-CORE-031

Outcome. Make delegated authority monotonically narrower and revoke future use according to an explicit scalable model.

Scope. Produce and integrate: attenuation rules; derivation/revocation objects; IPC integration; revocation cost/latency tests; policy docs. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep policy, drivers, compatibility, filesystems, networking, graphics, and product behavior outside the minimal kernel boundary.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • No derivation gains rights, revocation has documented in-flight semantics, and completion/resource costs are bounded or explicitly limited
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: attenuation rules; derivation/revocation objects; IPC integration; revocation cost/latency tests; policy docs Verification: EXP-004 property/model tests under concurrent use and deep delegation Evidence: revocation trace; complexity/latency report; EXP-004 record Traceability: specs: AOS-ARCH-004#delegation-and-attenuation;AOS-ARCH-004#revocation; sources: SRC-001;SRC-002;SRC-007;SRC-008; claims: none; experiments: EXP-004 Phase / volume: Phase 2 · Volume 02 Specialist review: none

AOS-CORE-033 — Implement wait sets and asynchronous notification objects

Type / priority / status: Task · P1 · Backlog Owner / workstream: Kernel IPC Engineer · IPC Schedule: 2026-11-02 → 2026-12-20 · 12 estimated days · M2 Parent: AOS-CORE-000 Dependencies: AOS-CORE-021 Related tasks: AOS-CORE-031

Outcome. Allow services to wait on bounded sets of signals, interrupts, channels, timers, and lifecycle events without polling.

Scope. Produce and integrate: wait set/port object; registration tokens; edge/level policy; cancellation; batching; tests. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep policy, drivers, compatibility, filesystems, networking, graphics, and product behavior outside the minimal kernel boundary.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Services can multiplex events without busy waiting and event delivery/cancellation semantics are deterministic
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: wait set/port object; registration tokens; edge/level policy; cancellation; batching; tests Verification: lost/duplicate event, unregister race, peer death, overload and fairness tests Evidence: event conformance report; stress traces; memory/accounting report Traceability: specs: AOS-ARCH-004#waiting-and-signals;AOS-ARCH-007#event-loop; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-CORE-034 — Implement jobs, quotas, and resource accounting

Type / priority / status: Task · P0 · Backlog Owner / workstream: Kernel Runtime Engineer · Resources Schedule: 2026-11-02 → 2026-12-20 · 14 estimated days · M2 Parent: AOS-CORE-000 Dependencies: AOS-CORE-018;AOS-CORE-030 Related tasks: AOS-CORE-022

Outcome. Bound processes and services by memory, handles, threads, IPC, CPU time and kernel-resource budgets.

Scope. Produce and integrate: job/resource domain; quota counters; inheritance; denial reasons; metrics; tests. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep policy, drivers, compatibility, filesystems, networking, graphics, and product behavior outside the minimal kernel boundary.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Every scarce kernel object is charged, denial is explicit, and termination/revocation returns charges without underflow/overflow
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: job/resource domain; quota counters; inheritance; denial reasons; metrics; tests Verification: exhaust each resource, nested domains, concurrent charge/release, process death and accounting reconciliation Evidence: quota test matrix; denial logs; leak report Traceability: specs: AOS-ARCH-003#resource-accounting;AOS-ARCH-010#agent-budgets; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-CORE-035 — Enable symmetric multiprocessing and cross-CPU coordination

Type / priority / status: Task · P1 · Backlog Owner / workstream: Kernel Architecture Engineer · Symmetric Multiprocessing Schedule: 2026-12-14 → 2027-03-21 · 25 estimated days · M3 Parent: AOS-CORE-000 Dependencies: AOS-CORE-022;AOS-CORE-023 Related tasks: AOS-CORE-034

Outcome. Run processes across multiple CPUs with correct interrupt routing, scheduling, TLB invalidation, object synchronization, and hot/offline policy.

Scope. Produce and integrate: CPU discovery/start; per-CPU queues; IPIs; shootdowns; lock strategy; stress tests. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep policy, drivers, compatibility, filesystems, networking, graphics, and product behavior outside the minimal kernel boundary.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • No single-core assumptions remain in portable kernel code and multicore results preserve isolation/accounting invariants
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: CPU discovery/start; per-CPU queues; IPIs; shootdowns; lock strategy; stress tests Verification: multicore stress, randomized scheduling, TLB/mapping races, CPU offline/failure injection Evidence: Agent OS correctness report; race traces; scaling baseline Traceability: specs: AOS-ARCH-003#aos-model;AOS-ARCH-003#address-spaces; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-CORE-036 — Validate IPC priority propagation and deadline behavior

Type / priority / status: Experiment · P1 · Backlog Owner / workstream: Kernel Scheduling Engineer · Performance Schedule: 2026-11-30 → 2027-01-17 · 12 estimated days · M2 Parent: AOS-CORE-000 Dependencies: AOS-CORE-022;AOS-CORE-031 Related tasks: AOS-CORE-033

Outcome. Prevent unbounded priority inversion and characterize IPC/scheduler latency under adversarial service graphs.

Scope. Produce and integrate: priority/deadline policy; adversarial workload generator; trace analysis; limits. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep policy, drivers, compatibility, filesystems, networking, graphics, and product behavior outside the minimal kernel boundary.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • The design bounds or explicitly rejects problematic call chains and reports violated deadlines/accounting accurately
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: priority/deadline policy; adversarial workload generator; trace analysis; limits Verification: EXP-005 across nested calls, cancellation, overload and malicious servers Evidence: latency histograms; dependency-chain traces; EXP-005 record Traceability: specs: AOS-ARCH-003#priority-inversion;AOS-ARCH-004#ipc-scheduling; sources: SRC-010; claims: none; experiments: EXP-005 Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-CORE-037 — Implement IOMMU and DMA ownership primitives

Type / priority / status: Task · P1 · Backlog Owner / workstream: Kernel I/O Engineer · I/O Security Schedule: 2027-01-25 → 2027-04-18 · 20 estimated days · M3 Parent: AOS-CORE-000 Dependencies: AOS-CORE-014;AOS-CORE-030 Related tasks: AOS-CORE-035

Outcome. Give user-space driver domains safe, bounded DMA mappings and interrupt resources without general physical-memory authority.

Scope. Produce and integrate: DMA domain object; pinned memory; IOVA allocator; IOMMU backend hooks; cache/coherency contract; tests. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep policy, drivers, compatibility, filesystems, networking, graphics, and product behavior outside the minimal kernel boundary.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • A driver can DMA only to granted mappings and device/domain teardown revokes access before memory reuse
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: DMA domain object; pinned memory; IOVA allocator; IOMMU backend hooks; cache/coherency contract; tests Verification: invalid DMA, teardown, device reset, concurrent mapping and no-IOMMU fallback policy tests Evidence: DMA isolation report; IOMMU traces; residual-risk record Traceability: specs: AOS-ARCH-006#dma-and-iommu;AOS-ARCH-012#dma-threat; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-CORE-038 — Implement structured crash records and kernel diagnostics

Type / priority / status: Task · P1 · Backlog Owner / workstream: Kernel Diagnostics Engineer · Diagnostics Schedule: 2026-09-21 → 2026-11-01 · 10 estimated days · M2 Parent: AOS-CORE-000 Dependencies: AOS-CORE-016 Related tasks: AOS-CORE-018;AOS-CORE-034

Outcome. Produce bounded, privacy-aware crash evidence sufficient for remote debugging without requiring a live debugger.

Scope. Produce and integrate: crash record format; stack/symbol IDs; object/process summaries; persistent ring buffer; extraction tool. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep policy, drivers, compatibility, filesystems, networking, graphics, and product behavior outside the minimal kernel boundary.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Crash evidence identifies build/target/failure context, is bounded and extractable after reboot, and excludes unapproved payloads
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: crash record format; stack/symbol IDs; object/process summaries; persistent ring buffer; extraction tool Verification: panic/process/interrupt/OOM crash scenarios and redaction/bounds tests Evidence: sample crash bundles; size/overhead metrics; privacy review Traceability: specs: AOS-ARCH-015#crash-evidence;AOS-ARCH-012#diagnostic-data; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-CORE-039 — Fuzz and property-test kernel syscall surface

Type / priority / status: Task · P0 · Backlog Owner / workstream: Kernel Verification Engineer · Assurance Schedule: 2026-11-30 → 2027-04-18 · 20 estimated days · M3 Parent: AOS-CORE-000 Dependencies: AOS-CORE-020;AOS-CORE-038 Related tasks: AOS-CORE-032;AOS-CORE-034

Outcome. Continuously exercise syscall decoding, object lifecycle, IPC, memory mappings, handles, cancellation and quotas against executable models.

Scope. Produce and integrate: host/model fuzzers; in-VM syscall fuzzer; corpus; differential oracle; minimizer; CI tiers. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep policy, drivers, compatibility, filesystems, networking, graphics, and product behavior outside the minimal kernel boundary.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • All public syscalls have negative/fuzz coverage and every unique crash produces a minimized reproducible artifact
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: host/model fuzzers; in-VM syscall fuzzer; corpus; differential oracle; minimizer; CI tiers Verification: seeded defects, coverage targets, crash deduplication and reproduction from corpus Evidence: coverage/trend report; discovered/fixed defects; corpus manifest Traceability: specs: AOS-ARCH-015#fuzzing;AOS-ARCH-002#assurance-boundary; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-CORE-040 — Freeze kernel API level 0 at capability vertical-slice gate

Type / priority / status: Decision · P0 · Backlog Owner / workstream: Architecture Council · API Governance Schedule: 2027-01-18 → 2027-01-31 · 5 estimated days · M2 Parent: AOS-CORE-000 Dependencies: AOS-CORE-032;AOS-CORE-033;AOS-CORE-034;AOS-CORE-036 Related tasks: AOS-CORE-039;AOS-PLAT-012

Outcome. Approve the first coherent experimental kernel ABI only after object, IPC, resource, failure, and versioning semantics pass G2.

Scope. Produce and integrate: G2 packet; API-level manifest; compatibility/deprecation policy; residual risks; next-level proposal. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep policy, drivers, compatibility, filesystems, networking, graphics, and product behavior outside the minimal kernel boundary.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • No ambient privilege, unbounded resource path, unresolved message-ownership ambiguity, or undocumented ABI enters API level 0
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: G2 packet; API-level manifest; compatibility/deprecation policy; residual risks; next-level proposal Verification: architecture/security/platform review of evidence and independent rebuild Evidence: signed gate decision; conformance bundle; rejected/deferred item list Traceability: specs: AOS-GOV-001#api-levels;AOS-PLAN-006#technical-gates; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-DOCS

AOS-DOCS-000 — Program Operations and Specifications epic

Type / priority / status: Epic · P1 · Backlog Owner / workstream: Program Lead · Program Schedule: 2026-07-13 → 2030-07-07 · 3 estimated days · Continuous Parent: none Dependencies: none Related tasks: none

Outcome. Maintain normative specifications, evidence, task data, budgets, risks, gates, and publication.

Scope. Produce and integrate: project charter; milestone map; owned backlog; status/evidence dashboard. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Treat specifications and canonical data as generated/reviewed source artifacts with stable IDs, validation, and no undocumented tracker-only truth.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Project has one accountable lead, an approved scope, milestone links, and no orphaned P0/P1 work
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: project charter; milestone map; owned backlog; status/evidence dashboard Verification: monthly project review and gate reconciliation Evidence: project update; dependency report; risk and budget delta Traceability: specs: AOS-META-002#document-contract; sources: none; claims: none; experiments: none Phase / volume: Phase 0 · Volume 06 Specialist review: none

AOS-DOCS-001 — Create repository and document topology

Type / priority / status: Task · P0 · Backlog Owner / workstream: Program Operations Lead · Documentation Schedule: 2026-07-13 → 2026-07-19 · 3 estimated days · M0 Parent: AOS-DOCS-000 Dependencies: none Related tasks: none

Outcome. Create the authoritative repository layout, document IDs, templates, and ownership boundaries.

Scope. Produce and integrate: repository directories; CODEOWNERS; templates; README; document registry. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Treat specifications and canonical data as generated/reviewed source artifacts with stable IDs, validation, and no undocumented tracker-only truth.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • A fresh clone exposes every canonical area and no authoritative artifact exists only in a private tracker
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: repository directories; CODEOWNERS; templates; README; document registry Verification: fresh-clone structure and ownership review Evidence: tree listing; review record; validation log Traceability: specs: AOS-META-004#target-layout;AOS-META-002#document-contract; sources: none; claims: none; experiments: none Phase / volume: Phase 0 · Volume 06 Specialist review: none

AOS-DOCS-002 — Implement cross-reference and Wiki publishing convention

Type / priority / status: Task · P0 · Backlog Owner / workstream: Documentation Engineer · Documentation Schedule: 2026-07-13 → 2026-07-26 · 5 estimated days · M0 Parent: AOS-DOCS-000 Dependencies: none Related tasks: AOS-DOCS-001

Outcome. Make document and task links stable in Git repositories and transformable for GitHub Wiki publication.

Scope. Produce and integrate: xref syntax; link map; renderer; redirect rules; test fixtures. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Treat specifications and canonical data as generated/reviewed source artifacts with stable IDs, validation, and no undocumented tracker-only truth.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Repository-relative links and machine xrefs resolve to the same target and explicit anchor
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: xref syntax; link map; renderer; redirect rules; test fixtures Verification: render repository docs into flat Wiki preview and crawl links Evidence: renderer log; broken-link count zero; sample redirects Traceability: specs: AOS-META-001#xref-syntax;AOS-META-001#publishing-flow; sources: none; claims: none; experiments: none Phase / volume: Phase 0 · Volume 06 Specialist review: none

AOS-DOCS-003 — Normalize source archive into normative specifications

Type / priority / status: Task · P0 · Backlog Owner / workstream: Lead Technical Writer · Documentation Schedule: 2026-07-13 → 2026-08-02 · 10 estimated days · M0 Parent: AOS-DOCS-000 Dependencies: none Related tasks: AOS-DOCS-001

Outcome. Extract valid requirements and evidence from the supplied archive without retaining contradictory historical narrative.

Scope. Produce and integrate: normalized specs; provenance note; supersession map; unresolved-claim list. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Treat specifications and canonical data as generated/reviewed source artifacts with stable IDs, validation, and no undocumented tracker-only truth.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Every retained requirement has a destination and every materially changed claim is represented normatively or in the claim register
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: normalized specs; provenance note; supersession map; unresolved-claim list Verification: architecture and product reviewers sample every source family Evidence: review checklist; mapping table; rejected/retained claim list Traceability: specs: AOS-META-003#claim-discipline;AOS-GOV-001#change-types; sources: none; claims: none; experiments: none Phase / volume: Phase 0 · Volume 06 Specialist review: none

AOS-DOCS-004 — Establish source and literature register

Type / priority / status: Task · P0 · Backlog Owner / workstream: Research Lead · Research Schedule: 2026-07-13 → 2026-08-02 · 8 estimated days · M0 Parent: AOS-DOCS-000 Dependencies: none Related tasks: AOS-DOCS-001

Outcome. Create a maintainable official-source register for architecture, hardware, legal, standards, tooling, and prior art.

Scope. Produce and integrate: source-register.yaml; annotated source table; freshness policy. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Treat specifications and canonical data as generated/reviewed source artifacts with stable IDs, validation, and no undocumented tracker-only truth.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Every time-sensitive or non-obvious planning fact cites an identified source with authority and scope limitation
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: source-register.yaml; annotated source table; freshness policy Verification: URL/schema validation and authority/source-scope review Evidence: source validation report; review comments Traceability: specs: AOS-RES-002#source-register;AOS-META-003#source-record; sources: none; claims: none; experiments: none Phase / volume: Phase 0 · Volume 04 Specialist review: none

AOS-DOCS-005 — Establish claim verification register

Type / priority / status: Task · P0 · Backlog Owner / workstream: Evidence Lead · Research Schedule: 2026-07-20 → 2026-08-02 · 7 estimated days · M0 Parent: AOS-DOCS-000 Dependencies: none Related tasks: AOS-DOCS-003;AOS-DOCS-004

Outcome. Convert assumptions and absolute statements into bounded, testable, state-controlled claims.

Scope. Produce and integrate: claim register; owner/gate mappings; change procedure. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Treat specifications and canonical data as generated/reviewed source artifacts with stable IDs, validation, and no undocumented tracker-only truth.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Every hypothesis has an experiment or decision task and every contradicted claim is absent from normative promises
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: claim register; owner/gate mappings; change procedure Verification: review all hardware, camera, cellular, backup, agent, and portability claims Evidence: claim coverage report; unowned-claim list zero Traceability: specs: AOS-RES-003#claim-states;AOS-META-003#claim-discipline; sources: none; claims: none; experiments: none Phase / volume: Phase 0 · Volume 04 Specialist review: none

AOS-DOCS-006 — Generate canonical task and import datasets

Type / priority / status: Task · P0 · Backlog Owner / workstream: Program Operations Lead · Planning Schedule: 2026-07-20 → 2026-08-02 · 8 estimated days · M0 Parent: AOS-DOCS-000 Dependencies: AOS-DOCS-001 Related tasks: AOS-DOCS-003

Outcome. Create tracker-neutral work data with detailed scope, acceptance, dependencies, dates, milestones, and specification links.

Scope. Produce and integrate: tasks.csv; Linear/GitHub imports; projects/milestones/dependencies CSVs; task catalog. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Treat specifications and canonical data as generated/reviewed source artifacts with stable IDs, validation, and no undocumented tracker-only truth.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • All IDs are unique, all dependencies resolve without cycles, and each non-epic has detailed acceptance/evidence fields
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: tasks.csv; Linear/GitHub imports; projects/milestones/dependencies CSVs; task catalog Verification: schema/dependency/date/xref validator and sample import reconciliation Evidence: validation log; row counts; reconciliation sample Traceability: specs: AOS-PLAN-009#canonical-schema;AOS-PLAN-008#import-flow; sources: none; claims: none; experiments: none Phase / volume: Phase 0 · Volume 06 Specialist review: none

AOS-DOCS-007 — Implement document and task validators

Type / priority / status: Task · P0 · Backlog Owner / workstream: Build/Documentation Engineer · Tooling Schedule: 2026-07-20 → 2026-08-02 · 6 estimated days · M0 Parent: AOS-DOCS-000 Dependencies: none Related tasks: AOS-DOCS-002;AOS-DOCS-006

Outcome. Fail CI on broken cross-references, anchors, task edges, schema drift, weak required fields, and generated-artifact mismatch.

Scope. Produce and integrate: validate_docs.py; validate_tasks.py; CI workflow example; fixtures. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Treat specifications and canonical data as generated/reviewed source artifacts with stable IDs, validation, and no undocumented tracker-only truth.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Validator detects unknown documents/anchors/tasks, cycles, duplicate IDs, invalid dates and missing acceptance evidence
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: validate_docs.py; validate_tasks.py; CI workflow example; fixtures Verification: positive and intentionally broken fixture runs Evidence: CI logs proving expected pass/fail cases Traceability: specs: AOS-META-001#validation;AOS-PLAN-009#validation; sources: none; claims: none; experiments: none Phase / volume: Phase 0 · Volume 06 Specialist review: none

AOS-DOCS-008 — Baseline roadmap, Gantt, milestones, and dependency model

Type / priority / status: Task · P1 · Backlog Owner / workstream: Program Lead · Planning Schedule: 2026-07-20 → 2026-08-02 · 5 estimated days · M0 Parent: AOS-DOCS-000 Dependencies: none Related tasks: AOS-DOCS-006

Outcome. Publish a dependency-driven multi-track schedule that can be rendered in Markdown and Linear.

Scope. Produce and integrate: Mermaid Gantt; milestone table; project date ranges; dependency view. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Treat specifications and canonical data as generated/reviewed source artifacts with stable IDs, validation, and no undocumented tracker-only truth.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Milestones have dated exit evidence and no hardware target is the sole dependency for core/product progress
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: Mermaid Gantt; milestone table; project date ranges; dependency view Verification: schedule consistency and critical-dependency review Evidence: baseline schedule export; review decision Traceability: specs: AOS-PLAN-002#gantt;AOS-PLAN-008#gantt-in-linear; sources: none; claims: none; experiments: none Phase / volume: Phase 0 · Volume 06 Specialist review: none

AOS-DOCS-009 — Baseline budget, procurement, risk, and gate registers

Type / priority / status: Task · P1 · Backlog Owner / workstream: Program Lead · Program Controls Schedule: 2026-07-20 → 2026-08-09 · 6 estimated days · M0 Parent: AOS-DOCS-000 Dependencies: none Related tasks: AOS-DOCS-005;AOS-DOCS-008

Outcome. Tie money, equipment, risks, stop criteria, and funding tranches to evidence-producing work.

Scope. Produce and integrate: budget ranges; first order; risk register; gate packets; approval thresholds. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Treat specifications and canonical data as generated/reviewed source artifacts with stable IDs, validation, and no undocumented tracker-only truth.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Every first purchase and Critical/High risk maps to a task, owner, experiment/gate, and contingency
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: budget ranges; first order; risk register; gate packets; approval thresholds Verification: finance/procurement/technical/legal review Evidence: approved tranche; risk owner list; gate checklist Traceability: specs: AOS-HW-009#budget-scenarios;AOS-PLAN-005#top-risks;AOS-PLAN-006#technical-gates; sources: none; claims: none; experiments: none Phase / volume: Phase 0 · Volume 07 Specialist review: none

AOS-DOCS-010 — Publish executive briefing and onboarding path

Type / priority / status: Task · P1 · Backlog Owner / workstream: Program Lead · Documentation Schedule: 2026-07-27 → 2026-08-02 · 3 estimated days · M0 Parent: AOS-DOCS-000 Dependencies: none Related tasks: AOS-DOCS-003;AOS-DOCS-008;AOS-DOCS-009

Outcome. Provide a decision-ready summary and reading path for engineers, partners, counsel, funders, and contributors.

Scope. Produce and integrate: BRIEFING.md; README reading path; audience-specific links. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Treat specifications and canonical data as generated/reviewed source artifacts with stable IDs, validation, and no undocumented tracker-only truth.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • A reader can identify the decision, constraints, hardware tracks, first 90 days, budget range, legal boundary, and next gate without oral context
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: BRIEFING.md; README reading path; audience-specific links Verification: review by architecture, product, hardware, security, legal, and community leads Evidence: sign-off list; unresolved questions Traceability: specs: AOS-BRIEF#executive-decision;AOS-README#start-here; sources: none; claims: none; experiments: none Phase / volume: Phase 0 · Volume 06 Specialist review: none

AOS-DOCS-011 — Generate and review Wiki publication preview

Type / priority / status: Task · P2 · Backlog Owner / workstream: Documentation Engineer · Publication Schedule: 2026-07-27 → 2026-08-02 · 4 estimated days · M0 Parent: AOS-DOCS-000 Dependencies: AOS-DOCS-002 Related tasks: AOS-DOCS-007;AOS-DOCS-010

Outcome. Create a flat GitHub-Wiki-compatible preview while preserving source IDs, anchors, links, and provenance.

Scope. Produce and integrate: wiki directory; Home page; sidebar/index; redirect map; publication report. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Treat specifications and canonical data as generated/reviewed source artifacts with stable IDs, validation, and no undocumented tracker-only truth.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Generated Wiki has no broken internal link and contains a visible generated/non-authoritative notice
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: wiki directory; Home page; sidebar/index; redirect map; publication report Verification: crawl all generated pages and compare xref targets to source Evidence: publication report; link graph; file hash list Traceability: specs: AOS-META-001#publishing-flow;AOS-META-004#generated-artifacts; sources: none; claims: none; experiments: none Phase / volume: Phase 0 · Volume 10 Specialist review: none

AOS-DOCS-012 — Tag documentation baseline release

Type / priority / status: Decision · P0 · Backlog Owner / workstream: Program Lead · Publication Schedule: 2026-08-03 → 2026-08-09 · 2 estimated days · M0 Parent: AOS-DOCS-000 Dependencies: AOS-DOCS-004;AOS-DOCS-005;AOS-DOCS-006;AOS-DOCS-007;AOS-DOCS-011 Related tasks: none

Outcome. Bind the normative document set, task data, source/claim/experiment registers, and validation results to a release.

Scope. Produce and integrate: versioned archive; manifest; checksums; signed/tagged release plan. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Treat specifications and canonical data as generated/reviewed source artifacts with stable IDs, validation, and no undocumented tracker-only truth.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • The archive rebuilds deterministically enough to reproduce all generated documents and CSV row counts
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: versioned archive; manifest; checksums; signed/tagged release plan Verification: clean rebuild and validation from packaged source Evidence: release manifest; checksums; validator outputs Traceability: specs: AOS-GOV-001#release-baseline;AOS-MANIFEST#validation-status; sources: none; claims: none; experiments: none Phase / volume: Phase 0 · Volume 10 Specialist review: none

AOS-DOCS-013 — Operate monthly documentation and tracker reconciliation

Type / priority / status: Review · P2 · Backlog Owner / workstream: Program Operations Lead · Program Controls Schedule: 2026-08-10 → 2030-07-07 · 2 estimated days · Continuous Parent: AOS-DOCS-000 Dependencies: AOS-DOCS-012 Related tasks: none

Outcome. Detect drift among specifications, canonical CSV, GitHub, Linear, milestones, evidence, risks, and budgets.

Scope. Produce and integrate: monthly drift report; proposed source updates; orphaned/overdue relationship list. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Treat specifications and canonical data as generated/reviewed source artifacts with stable IDs, validation, and no undocumented tracker-only truth.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • No P0/P1 issue, gate, risk, or accepted specification remains inconsistent across systems for more than one review cycle
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: monthly drift report; proposed source updates; orphaned/overdue relationship list Verification: compare IDs, states, dates, dependencies and links across systems Evidence: dated reconciliation report and approved changes Traceability: specs: AOS-PLAN-008#agent-rules;AOS-GOV-001#release-baseline; sources: none; claims: none; experiments: none Phase / volume: Phase 0 · Volume 06 Specialist review: none

AOS-DOCS-020 — Freeze and checksum the complete AgentOS/Agent OS source corpus

Type / priority / status: Task · P0 · Planned Owner / workstream: Documentation Lead · Source Corpus Schedule: 2026-07-13 → 2026-07-26 · 5 estimated days · M0 Parent: AOS-DOCS-000 Dependencies: none Related tasks: none

Outcome. Freeze and checksum the complete AgentOS/Agent OS source corpus.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-SRC-README#immutability, AOS-RES-005#authority. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Freeze and checksum the complete AgentOS/Agent OS source corpus; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-SRC-README#immutability;AOS-RES-005#authority; sources: AOS-SRC-NINDEX; claims: none; experiments: none Phase / volume: Phase 0 · Volume 01 Specialist review: none

AOS-DOCS-021 — Normalize the product vision into English source digests

Type / priority / status: Task · P0 · Planned Owner / workstream: Product Research Lead · Source Normalization Schedule: 2026-07-13 → 2026-08-02 · 8 estimated days · M0 Parent: AOS-DOCS-000 Dependencies: none Related tasks: AOS-DOCS-020

Outcome. Normalize the product vision into English source digests.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-SRC-N001#product-thesis, AOS-SRC-N002#implications. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Normalize the product vision into English source digests; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-SRC-N001#thesis;AOS-SRC-N002#downstream; sources: AOS-SRC-N001;AOS-SRC-N002; claims: none; experiments: none Phase / volume: Phase 0 · Volume 01 Specialist review: none

AOS-DOCS-022 — Publish the source authority and conflict map

Type / priority / status: Review · P0 · Planned Owner / workstream: Architecture Lead · Source Governance Schedule: 2026-07-20 → 2026-08-09 · 8 estimated days · M0 Parent: AOS-DOCS-000 Dependencies: none Related tasks: AOS-DOCS-020;AOS-DOCS-021

Outcome. Publish the source authority and conflict map.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-RES-005#authority, AOS-RES-005#conflicts. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Publish the source authority and conflict map; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-RES-005#authority;AOS-RES-005#conflicts; sources: AOS-SRC-NINDEX; claims: CLM-001; experiments: none Phase / volume: Phase 0 · Volume 04 Specialist review: architecture;product

AOS-DOCS-023 — Define canonical cross-reference and anchor syntax

Type / priority / status: Decision · P0 · Planned Owner / workstream: Documentation Lead · Documentation System Schedule: 2026-07-13 → 2026-07-26 · 5 estimated days · M0 Parent: AOS-DOCS-000 Dependencies: none Related tasks: AOS-DOCS-002

Outcome. Define canonical cross-reference and anchor syntax.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-META-001#xref-syntax, AOS-VAL-003#checks. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Define canonical cross-reference and anchor syntax; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-META-001#xref-syntax;AOS-VAL-003#checks; sources: none; claims: none; experiments: none Phase / volume: Phase 0 · Volume 01 Specialist review: none

AOS-DOCS-024 — Build the ten-volume coverage and ownership matrix

Type / priority / status: Task · P0 · Planned Owner / workstream: Program Lead · Documentation Program Schedule: 2026-07-20 → 2026-08-09 · 8 estimated days · M0 Parent: AOS-DOCS-000 Dependencies: none Related tasks: AOS-DOCS-022

Outcome. Build the ten-volume coverage and ownership matrix.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-PLAN-011#volumes, AOS-PLAN-011#completion. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Build the ten-volume coverage and ownership matrix; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-PLAN-011#volumes;AOS-PLAN-011#definition-of-done; sources: none; claims: none; experiments: none Phase / volume: Phase 0 · Volume 06 Specialist review: none

AOS-DOCS-025 — Build the Phase 0–8 execution and gate matrix

Type / priority / status: Task · P0 · Planned Owner / workstream: Program Lead · Program Model Schedule: 2026-07-20 → 2026-08-09 · 8 estimated days · M0 Parent: AOS-DOCS-000 Dependencies: none Related tasks: AOS-DOCS-024

Outcome. Build the Phase 0–8 execution and gate matrix.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-PLAN-010#phase-table, AOS-PLAN-010#gates. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Build the Phase 0–8 execution and gate matrix; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-PLAN-010#phase-table;AOS-PLAN-010#gates; sources: none; claims: none; experiments: none Phase / volume: Phase 0 · Volume 06 Specialist review: none

AOS-DOCS-026 — Create the specialist review responsibility matrix

Type / priority / status: Task · P1 · Planned Owner / workstream: Program Lead · Review Governance Schedule: 2026-07-27 → 2026-08-16 · 8 estimated days · M0 Parent: AOS-DOCS-000 Dependencies: none Related tasks: AOS-DOCS-024

Outcome. Create the specialist review responsibility matrix.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-PLAN-015#reviews, AOS-VAL-003#review-status. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Create the specialist review responsibility matrix; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-PLAN-015#weekly;AOS-VAL-003#review-status; sources: none; claims: none; experiments: none Phase / volume: Phase 0 · Volume 06 Specialist review: none

AOS-DOCS-027 — Validate glossary definitions and exact usage references

Type / priority / status: Review · P1 · Planned Owner / workstream: Technical Editor · Knowledge Base Schedule: 2026-07-27 → 2026-08-23 · 10 estimated days · M0 Parent: AOS-DOCS-000 Dependencies: none Related tasks: AOS-DOCS-023

Outcome. Validate glossary definitions and exact usage references.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-GLOSSARY#how-to-use, AOS-VAL-003#checks. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Validate glossary definitions and exact usage references; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-GLOSSARY#how-to-use;AOS-VAL-003#checks; sources: none; claims: none; experiments: none Phase / volume: Phase 0 · Volume 09 Specialist review: none

AOS-DOCS-028 — Generate and verify GitHub Wiki publication views

Type / priority / status: Task · P1 · Planned Owner / workstream: Documentation Lead · Publishing Schedule: 2027-10-04 → 2027-11-07 · 12 estimated days · M8 Parent: AOS-DOCS-000 Dependencies: none Related tasks: AOS-DOCS-023

Outcome. Generate and verify GitHub Wiki publication views.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-META-001#publishing-flow, AOS-VAL-003#publication. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Generate and verify GitHub Wiki publication views; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-META-001#publishing-flow;AOS-VAL-003#publication; sources: none; claims: none; experiments: none Phase / volume: Phase 8 · Volume 10 Specialist review: none

AOS-DOCS-029 — Implement canonical task-to-spec-to-claim traceability

Type / priority / status: Task · P0 · Planned Owner / workstream: Program Data Lead · Traceability Schedule: 2026-07-27 → 2026-08-23 · 10 estimated days · M0 Parent: AOS-DOCS-000 Dependencies: none Related tasks: AOS-DOCS-025

Outcome. Implement canonical task-to-spec-to-claim traceability.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-PLAN-009#canonical-schema, AOS-VAL-003#checks, AOS-RES-010#matrix. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Implement canonical task-to-spec-to-claim traceability; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-PLAN-009#canonical-schema;AOS-VAL-003#checks;AOS-RES-010#matrix; sources: none; claims: none; experiments: EXP-109 Phase / volume: Phase 0 · Volume 10 Specialist review: program-data

AOS-DOCS-030 — Define public, internal, restricted, and counsel evidence bundles

Type / priority / status: Decision · P0 · Planned Owner / workstream: Security and Legal Leads · Evidence Governance Schedule: 2026-07-20 → 2026-08-16 · 10 estimated days · M0 Parent: AOS-DOCS-000 Dependencies: none Related tasks: AOS-DOCS-020

Outcome. Define public, internal, restricted, and counsel evidence bundles.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-VAL-002#integrity, AOS-ARCH-018#taint. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Define public, internal, restricted, and counsel evidence bundles; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-VAL-002#integrity;AOS-ARCH-018#taint; sources: none; claims: none; experiments: none Phase / volume: Phase 0 · Volume 10 Specialist review: security;legal

AOS-DOCS-031 — Package the Foundation release with reproducible validation

Type / priority / status: Task · P0 · Planned Owner / workstream: Release Engineer · Release Packaging Schedule: 2026-08-03 → 2026-08-16 · 5 estimated days · M0 Parent: AOS-DOCS-000 Dependencies: none Related tasks: AOS-DOCS-023;AOS-DOCS-029;AOS-DOCS-030

Outcome. Package the Foundation release with reproducible validation.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-VAL-003#publication, AOS-PLAN-016#operation. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Package the Foundation release with reproducible validation; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-VAL-003#publication;AOS-PLAN-016#workflow; sources: none; claims: none; experiments: none Phase / volume: Phase 0 · Volume 10 Specialist review: none

AOS-DOCS-032 — Reconcile Linear and GitHub imports against canonical task IDs

Type / priority / status: Task · P1 · Planned Owner / workstream: Program Automation Engineer · Tracker Automation Schedule: 2026-08-03 → 2026-08-23 · 8 estimated days · M0 Parent: AOS-DOCS-000 Dependencies: none Related tasks: AOS-DOCS-029

Outcome. Reconcile Linear and GitHub imports against canonical task IDs.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-PLAN-014#reconciliation, AOS-PLAN-009#validation. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Reconcile Linear and GitHub imports against canonical task IDs; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-PLAN-014#reconciliation;AOS-PLAN-009#validation; sources: none; claims: none; experiments: none Phase / volume: Phase 0 · Volume 06 Specialist review: none

AOS-DOCS-033 — Create paragraph-level source citations for normalized digests

Type / priority / status: Task · P1 · Planned Owner / workstream: Research Librarian · Source Traceability Schedule: 2026-08-03 → 2026-09-06 · 12 estimated days · M1 Parent: AOS-DOCS-000 Dependencies: none Related tasks: AOS-DOCS-021;AOS-DOCS-023

Outcome. Create paragraph-level source citations for normalized digests.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-SRC-NINDEX#normalized-source-digests, AOS-RES-002#source-register. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Create paragraph-level source citations for normalized digests; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-SRC-NINDEX#digests;AOS-RES-002#source-register; sources: none; claims: none; experiments: none Phase / volume: Phase 1 · Volume 04 Specialist review: none

AOS-DOCS-034 — Audit normative documents for transient narrative and unsupported absolutes

Type / priority / status: Review · P0 · Planned Owner / workstream: Technical Editor · Editorial Assurance Schedule: 2026-08-03 → 2026-08-30 · 10 estimated days · M0 Parent: AOS-DOCS-000 Dependencies: none Related tasks: AOS-DOCS-022

Outcome. Audit normative documents for transient narrative and unsupported absolutes.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-VAL-003#editorial, AOS-META-002#document-contract. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Audit normative documents for transient narrative and unsupported absolutes; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-VAL-003#editorial;AOS-META-002#document-contract; sources: none; claims: none; experiments: none Phase / volume: Phase 0 · Volume 10 Specialist review: none

AOS-DOCS-035 — Publish the project briefing, first steps, budget, and purchase gates

Type / priority / status: Task · P0 · Planned Owner / workstream: Program Lead · Briefing Schedule: 2026-07-27 → 2026-08-16 · 8 estimated days · M0 Parent: AOS-DOCS-000 Dependencies: none Related tasks: AOS-DOCS-025

Outcome. Publish the project briefing, first steps, budget, and purchase gates.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-BRIEF#executive-decision, AOS-PLAN-013#first-thirty-days. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Publish the project briefing, first steps, budget, and purchase gates; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-BRIEF#executive-decision;AOS-PLAN-013#first-30; sources: none; claims: none; experiments: none Phase / volume: Phase 0 · Volume 01 Specialist review: none

AOS-LEGAL

AOS-LEGAL-000 — Legal, IP, and Compliance epic

Type / priority / status: Epic · P1 · Backlog Owner / workstream: Legal/Compliance Lead · Program Schedule: 2026-07-13 → 2030-01-20 · 3 estimated days · Continuous Parent: none Dependencies: none Related tasks: none

Outcome. Establish lawful research, provenance, contracts, branding, and certification paths.

Scope. Produce and integrate: project charter; milestone map; owned backlog; status/evidence dashboard. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record jurisdiction, source class, privilege/publication boundary, and counsel or accountable review; do not infer legal permission from technical access.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Project has one accountable lead, an approved scope, milestone links, and no orphaned P0/P1 work
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: project charter; milestone map; owned backlog; status/evidence dashboard Verification: monthly project review and gate reconciliation Evidence: project update; dependency report; risk and budget delta Traceability: specs: AOS-LEGAL-001#legal-workstreams; sources: none; claims: none; experiments: none Phase / volume: Phase 0 · Volume 05 Specialist review: none

AOS-LEGAL-001 — Establish entity, IP ownership, and confidentiality baseline

Type / priority / status: Review · P0 · Backlog Owner / workstream: Legal/Compliance Lead · IP Foundation Schedule: 2026-07-13 → 2026-08-02 · 5 estimated days · M0 Parent: AOS-LEGAL-000 Dependencies: none Related tasks: AOS-DOCS-001

Outcome. Ensure founders, employees, contractors, repositories, domains, and project assets have clear ownership and authority.

Scope. Produce and integrate: entity/ownership checklist; assignment templates; contractor terms; confidentiality and asset authority map. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record jurisdiction, source class, privilege/publication boundary, and counsel or accountable review; do not infer legal permission from technical access.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Every person and entity able to contribute or contract has an explicit IP/confidentiality path before material work
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: entity/ownership checklist; assignment templates; contractor terms; confidentiality and asset authority map Verification: qualified counsel review and signed/recorded instruments Evidence: privileged legal completion record; public-safe policy summary Traceability: specs: AOS-LEGAL-001#legal-workstreams;AOS-LEGAL-003#contributions; sources: none; claims: none; experiments: none Phase / volume: Phase 0 · Volume 05 Specialist review: none

AOS-LEGAL-002 — Conduct trademark and naming clearance

Type / priority / status: Review · P0 · Backlog Owner / workstream: Trademark Counsel · Brand Schedule: 2026-07-13 → 2026-08-23 · 4 estimated days · M0 Parent: AOS-LEGAL-000 Dependencies: none Related tasks: AOS-LEGAL-001

Outcome. Clear a final or fallback project mark and prevent public use of AgentOS or another conflicting designation.

Scope. Produce and integrate: knockout search; professional search scope; mark shortlist; namespace/domain plan; usage restrictions. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record jurisdiction, source class, privilege/publication boundary, and counsel or accountable review; do not infer legal permission from technical access.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Public identity uses an approved mark or explicitly remains private/working, and prohibited names are removed from publication artifacts
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: knockout search; professional search scope; mark shortlist; namespace/domain plan; usage restrictions Verification: counsel opinion and program decision Evidence: privileged opinion reference; approved public naming record Traceability: specs: AOS-LEGAL-006#clearance-process;AOS-ADR-0006#decision; sources: SRC-021; claims: none; experiments: none Phase / volume: Phase 0 · Volume 05 Specialist review: none

AOS-LEGAL-003 — Approve project licenses, DCO, and contribution terms

Type / priority / status: Decision · P0 · Backlog Owner / workstream: Open Source Counsel · Open Source Schedule: 2026-07-13 → 2026-08-09 · 5 estimated days · M0 Parent: AOS-LEGAL-000 Dependencies: none Related tasks: AOS-LEGAL-001

Outcome. Select compatible licenses and contributor certification before accepting public code, specifications, hardware files, or data.

Scope. Produce and integrate: license ADR; DCO policy; contribution guide clauses; hardware/docs license matrix. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record jurisdiction, source class, privilege/publication boundary, and counsel or accountable review; do not infer legal permission from technical access.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Every canonical artifact class has a declared license/provenance rule and contribution route
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: license ADR; DCO policy; contribution guide clauses; hardware/docs license matrix Verification: counsel and governance approval plus repository checks Evidence: decision record; license files; DCO test Traceability: specs: AOS-LEGAL-003#licensing-baseline;AOS-LEGAL-003#contributions; sources: SRC-060;SRC-063;SRC-064;SRC-066;SRC-067;SRC-068; claims: none; experiments: none Phase / volume: Phase 0 · Volume 05 Specialist review: none

AOS-LEGAL-004 — Implement source and artifact provenance controls

Type / priority / status: Task · P0 · Backlog Owner / workstream: Open Source Program Manager · Open Source Schedule: 2026-07-20 → 2026-08-16 · 8 estimated days · M0 Parent: AOS-LEGAL-000 Dependencies: none Related tasks: AOS-LEGAL-003;AOS-DOCS-004

Outcome. Prevent unknown, leaked, unlicensed, or non-redistributable material from contaminating public implementation and releases.

Scope. Produce and integrate: source classes; artifact inventory; REUSE/SPDX rules; binary/firmware record; quarantine procedure. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record jurisdiction, source class, privilege/publication boundary, and counsel or accountable review; do not infer legal permission from technical access.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Unknown-provenance and disallowed artifacts fail merge/release and have a controlled escalation path
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: source classes; artifact inventory; REUSE/SPDX rules; binary/firmware record; quarantine procedure Verification: scan seeded fixtures and sample imported dependencies/assets Evidence: provenance audit; quarantine exercise; CI report Traceability: specs: AOS-LEGAL-003#provenance-record;AOS-META-003#source-record; sources: SRC-060;SRC-061;SRC-062; claims: none; experiments: none Phase / volume: Phase 0 · Volume 05 Specialist review: none

AOS-LEGAL-005 — Approve clean-room interoperability protocol

Type / priority / status: Decision · P0 · Backlog Owner / workstream: IP/Interoperability Counsel · Reverse Engineering Schedule: 2026-07-20 → 2026-08-23 · 8 estimated days · M0 Parent: AOS-LEGAL-000 Dependencies: none Related tasks: AOS-LEGAL-001;AOS-LEGAL-004

Outcome. Create role-separated lawful methods for undocumented protocol and hardware behavior work.

Scope. Produce and integrate: clean-room policy; role/eligibility forms; observation/specification templates; artifact controls; stop rules. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record jurisdiction, source class, privilege/publication boundary, and counsel or accountable review; do not infer legal permission from technical access.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • No protected-protocol task can begin without source class, method, roles, publication rule, and counsel/accountable approval
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: clean-room policy; role/eligibility forms; observation/specification templates; artifact controls; stop rules Verification: tabletop exercise using a fictional protocol and contributor-taint scenario Evidence: counsel approval; exercise findings; public-safe protocol Traceability: specs: AOS-LEGAL-002#workflow;AOS-LEGAL-002#source-classes; sources: SRC-052;SRC-053; claims: none; experiments: none Phase / volume: Phase 0 · Volume 05 Specialist review: none

AOS-LEGAL-006 — Review device terms, acquisition, unlock, and firmware use

Type / priority / status: Review · P0 · Backlog Owner / workstream: Technology Transactions Counsel · Device Research Schedule: 2026-07-27 → 2026-09-20 · 7 estimated days · M1 Parent: AOS-LEGAL-000 Dependencies: none Related tasks: AOS-LEGAL-005;AOS-OPEN-003

Outcome. Define permissible purchase, unlock, restoration, firmware, warranty, redistribution, and publication behavior for every phone track.

Scope. Produce and integrate: per-device terms matrix; approved methods; firmware/artifact handling; resale/return/warranty guidance. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record jurisdiction, source class, privilege/publication boundary, and counsel or accountable review; do not infer legal permission from technical access.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Every acquired phone has an approved research and artifact-handling path before modification
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: per-device terms matrix; approved methods; firmware/artifact handling; resale/return/warranty guidance Verification: counsel review of exact SKU/source/terms and engineering procedure Evidence: public-safe device boundary record; privileged legal references Traceability: specs: AOS-LEGAL-001#device-and-protocol-work;AOS-HW-001#target-dossier; sources: SRC-019;SRC-020;SRC-027;SRC-028;SRC-029;SRC-031; claims: none; experiments: none Phase / volume: Phase 1 · Volume 04 Specialist review: none

AOS-LEGAL-007 — Approve Pixel 9 research boundary

Type / priority / status: Decision · P0 · Backlog Owner / workstream: IP/Interoperability Counsel · Pixel Legal Schedule: 2026-08-03 → 2026-09-27 · 6 estimated days · M1 Parent: AOS-LEGAL-000 Dependencies: none Related tasks: AOS-LEGAL-006;AOS-P9-001

Outcome. Authorize only the minimum Android/Linux stock-oracle, trace, sidecar, recovery, and feasibility uses that can be lawfully supported.

Scope. Produce and integrate: method matrix; source classes; team separation decision; publication/trace rules; adapter retirement obligations. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record jurisdiction, source class, privilege/publication boundary, and counsel or accountable review; do not infer legal permission from technical access.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Each Pixel task identifies allowed inputs, implementer eligibility, output restrictions, and stop condition before execution
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: method matrix; source classes; team separation decision; publication/trace rules; adapter retirement obligations Verification: counsel and architecture review against proposed Pixel experiments Evidence: approved boundary record; blocked-method list Traceability: specs: AOS-LEGAL-002#pixel-application;AOS-HW-002#allowed-legacy-uses; sources: SRC-019;SRC-020;SRC-021;SRC-052;SRC-053; claims: none; experiments: none Phase / volume: Phase 1 · Volume 04 Specialist review: none

AOS-LEGAL-008 — Create privacy, telemetry, biometrics, and user-study framework

Type / priority / status: Task · P1 · Backlog Owner / workstream: Privacy Counsel / DPO · Privacy Schedule: 2026-09-07 → 2026-11-29 · 10 estimated days · M2 Parent: AOS-LEGAL-000 Dependencies: AOS-LEGAL-001 Related tasks: AOS-SEC-050

Outcome. Define lawful and privacy-preserving handling of semantic history, diagnostics, agent evaluation, biometrics, and research participants.

Scope. Produce and integrate: data map; retention/deletion policy; consent/notice templates; DPIA triggers; processor/transfer controls; user-study protocol. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record jurisdiction, source class, privilege/publication boundary, and counsel or accountable review; do not infer legal permission from technical access.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • No user study or diagnostic sync begins without data purpose, minimization, retention, access, deletion, and incident ownership
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: data map; retention/deletion policy; consent/notice templates; DPIA triggers; processor/transfer controls; user-study protocol Verification: privacy/security/product review and tabletop data-subject request Evidence: data inventory; review record; deletion/export test result Traceability: specs: AOS-LEGAL-001#privacy-and-product-claims;AOS-PROD-002#privacy-controls;AOS-ARCH-012#sensitive-data; sources: SRC-057; claims: none; experiments: none Phase / volume: Phase 1 · Volume 05 Specialist review: none

AOS-LEGAL-009 — Establish export, sanctions, cryptography, and bounty screening

Type / priority / status: Task · P1 · Backlog Owner / workstream: Trade Compliance Counsel · Trade Compliance Schedule: 2026-09-07 → 2026-11-15 · 6 estimated days · M2 Parent: AOS-LEGAL-000 Dependencies: AOS-LEGAL-001 Related tasks: AOS-COMM-030

Outcome. Control code/device/cryptography exports, restricted parties, contractor access, grants, and payments.

Scope. Produce and integrate: jurisdiction/party screening workflow; release checklist; encryption classification record; payment controls. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record jurisdiction, source class, privilege/publication boundary, and counsel or accountable review; do not infer legal permission from technical access.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Releases and paid contributions have documented destination, party, encryption, and escalation checks
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: jurisdiction/party screening workflow; release checklist; encryption classification record; payment controls Verification: sample release and bounty tabletop across two jurisdictions Evidence: screening logs; exception/escalation procedure Traceability: specs: AOS-LEGAL-001#jurisdiction-matrix;AOS-GOV-003#funding-sources; sources: none; claims: none; experiments: none Phase / volume: Phase 1 · Volume 05 Specialist review: none

AOS-LEGAL-010 — Build regulatory and certification market matrix

Type / priority / status: Task · P1 · Backlog Owner / workstream: Regulatory Lead · Regulatory Schedule: 2026-12-28 → 2027-04-18 · 12 estimated days · M3 Parent: AOS-LEGAL-000 Dependencies: AOS-LEGAL-001;AOS-CELL-001 Related tasks: AOS-ODM-011

Outcome. Map radio, safety, environmental, privacy, cybersecurity, accessibility, carrier, battery, and consumer obligations by product stage and market.

Scope. Produce and integrate: US/EU initial matrix; stage checklist; variant/change-control rules; evidence-file skeleton. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record jurisdiction, source class, privilege/publication boundary, and counsel or accountable review; do not infer legal permission from technical access.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Each intended device stage and market has an accountable requirement owner and no radio/cellular claim relies on module certification alone
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: US/EU initial matrix; stage checklist; variant/change-control rules; evidence-file skeleton Verification: regulatory counsel and accredited-lab consultation Evidence: reviewed matrix; assumptions/open questions; lab notes Traceability: specs: AOS-LEGAL-004#market-matrix;AOS-LEGAL-004#development-stages; sources: SRC-050;SRC-051;SRC-054;SRC-055;SRC-056;SRC-057; claims: none; experiments: none Phase / volume: Phase 3 · Volume 05 Specialist review: none

AOS-LEGAL-011 — Create vendor, partner, NDA, and documentation agreement playbook

Type / priority / status: Task · P1 · Backlog Owner / workstream: Technology Transactions Counsel · Contracts Schedule: 2026-08-10 → 2026-11-01 · 8 estimated days · M2 Parent: AOS-LEGAL-000 Dependencies: AOS-LEGAL-001 Related tasks: AOS-LEGAL-004

Outcome. Standardize technical asks and contract terms for silicon, board, camera, modem, lab, security, and manufacturing partners.

Scope. Produce and integrate: NDA review checklist; evaluation agreement; documentation/firmware/support clauses; artifact intake workflow. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record jurisdiction, source class, privilege/publication boundary, and counsel or accountable review; do not infer legal permission from technical access.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Critical vendor dependencies have explicit rights for implementation, deployment, updates, publication, replacement, and termination assistance
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: NDA review checklist; evaluation agreement; documentation/firmware/support clauses; artifact intake workflow Verification: apply playbook to two mock or live vendor engagements Evidence: redline checklist; issue log; approved clause library Traceability: specs: AOS-LEGAL-001#contract-principles;AOS-LEGAL-005#contract-asks; sources: none; claims: none; experiments: none Phase / volume: Phase 2 · Volume 05 Specialist review: none

AOS-LEGAL-012 — Implement OSS/SBOM release compliance pipeline

Type / priority / status: Task · P1 · Backlog Owner / workstream: Open Source Program Manager · Open Source Schedule: 2026-10-05 → 2026-12-27 · 10 estimated days · M2 Parent: AOS-LEGAL-000 Dependencies: AOS-LEGAL-003;AOS-LEGAL-004 Related tasks: AOS-SEC-060

Outcome. Automate per-file licensing, dependency review, SBOM, notices, source offers, provenance, and release approval.

Scope. Produce and integrate: CI policy; SPDX SBOM; notices/source-offer generator; exception workflow; audit dashboard. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record jurisdiction, source class, privilege/publication boundary, and counsel or accountable review; do not infer legal permission from technical access.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • A release cannot be produced with unknown license/provenance or missing required notices/source offers
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: CI policy; SPDX SBOM; notices/source-offer generator; exception workflow; audit dashboard Verification: release a fixture with permissive, copyleft, binary and generated components Evidence: SBOM; notices; policy pass/fail logs; exception record Traceability: specs: AOS-LEGAL-003#compliance-tooling;AOS-ARCH-015#release-evidence; sources: SRC-059;SRC-060;SRC-061;SRC-062; claims: none; experiments: none Phase / volume: Phase 2 · Volume 05 Specialist review: none

AOS-LEGAL-013 — Obtain certification laboratory architecture consultation

Type / priority / status: Contact · P1 · Backlog Owner / workstream: Regulatory Lead · Regulatory Schedule: 2027-12-27 → 2028-03-19 · 5 estimated days · M9 Parent: AOS-LEGAL-000 Dependencies: AOS-LEGAL-010;AOS-CELL-002 Related tasks: AOS-ODM-021

Outcome. Validate the proposed module, antenna, battery, enclosure, software-update, and market assumptions before custom hardware freeze.

Scope. Produce and integrate: lab briefing; staged test plan; inheritance assumptions; budget/lead times; evidence requirements. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record jurisdiction, source class, privilege/publication boundary, and counsel or accountable review; do not infer legal permission from technical access.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Product-hardware plan records which certifications can be inherited and which are invalidated by board/antenna/enclosure/software changes
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: lab briefing; staged test plan; inheritance assumptions; budget/lead times; evidence requirements Verification: written lab response reviewed by hardware, cellular, security and legal leads Evidence: consultation report; architecture changes; certification budget Traceability: specs: AOS-LEGAL-004#evidence-package;AOS-HW-008#certification-readiness; sources: SRC-050;SRC-051;SRC-054;SRC-055; claims: none; experiments: none Phase / volume: Phase 8 · Volume 05 Specialist review: none

AOS-LEGAL-014 — Prepare ODM/JDM/EMS contract and IP responsibility matrix

Type / priority / status: Task · P1 · Backlog Owner / workstream: Commercial/Technology Counsel · ODM Contracts Schedule: 2029-05-28 → 2029-11-11 · 12 estimated days · M11 Parent: AOS-LEGAL-000 Dependencies: AOS-LEGAL-011;AOS-LEGAL-010 Related tasks: AOS-ODM-060

Outcome. Define ownership, documentation, firmware, tooling, certification, quality, supply, security, and exit terms before an RFI.

Scope. Produce and integrate: RFI legal schedule; IP/tooling matrix; warranty/quality clauses; security/update obligations; termination/escrow options. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record jurisdiction, source class, privilege/publication boundary, and counsel or accountable review; do not infer legal permission from technical access.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • RFI can compare vendors on rights and lifecycle obligations without conceding portable interfaces or update control
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: RFI legal schedule; IP/tooling matrix; warranty/quality clauses; security/update obligations; termination/escrow options Verification: cross-functional review and red-team of vendor-failure scenarios Evidence: approved RFI attachments; risk acceptance record Traceability: specs: AOS-HW-008#contract-requirements;AOS-LEGAL-005#contractual-and-technical-asks; sources: none; claims: none; experiments: none Phase / volume: Phase 8 · Volume 05 Specialist review: none

AOS-LEGAL-020 — Retain software interoperability and reverse-engineering counsel

Type / priority / status: Contact · P0 · Planned Owner / workstream: Legal Lead · Counsel Schedule: 2026-07-20 → 2026-08-23 · 12 estimated days · M0 Parent: AOS-LEGAL-000 Dependencies: none Related tasks: none

Outcome. Retain software interoperability and reverse-engineering counsel.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-LEGAL-008#counsel-questions, AOS-LEGAL-001#legal-workstreams. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Retain software interoperability and reverse-engineering counsel; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-LEGAL-008#matrix;AOS-LEGAL-001#legal-workstreams; sources: none; claims: none; experiments: none Phase / volume: Phase 0 · Volume 05 Specialist review: none

AOS-LEGAL-021 — Run trademark clearance for Agent OS and naming candidates

Type / priority / status: Task · P0 · Planned Owner / workstream: Trademark Counsel · Trademark Schedule: 2026-07-20 → 2026-08-30 · 15 estimated days · M0 Parent: AOS-LEGAL-000 Dependencies: none Related tasks: none

Outcome. Run trademark clearance for Agent OS and naming candidates.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-LEGAL-003#clearance-process, AOS-SRC-N005#decision. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Run trademark clearance for Agent OS and naming candidates; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-LEGAL-003#release-gate;AOS-SRC-N005#codename; sources: SRC-098;SRC-099; claims: none; experiments: none Phase / volume: Phase 0 · Volume 05 Specialist review: none

AOS-LEGAL-022 — Implement clean-room roles, repositories, and taint labels

Type / priority / status: Task · P0 · Planned Owner / workstream: Legal and Security Leads · Clean Room Schedule: 2026-07-27 → 2026-08-30 · 12 estimated days · M0 Parent: AOS-LEGAL-000 Dependencies: none Related tasks: none

Outcome. Implement clean-room roles, repositories, and taint labels.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-LEGAL-002#roles, AOS-ARCH-018#taint. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Implement clean-room roles, repositories, and taint labels; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-LEGAL-002#roles;AOS-ARCH-018#taint; sources: none; claims: none; experiments: none Phase / volume: Phase 0 · Volume 05 Specialist review: none

AOS-LEGAL-023 — Prepare vendor NDA, evaluation, source, firmware, and escrow checklist

Type / priority / status: Task · P1 · Planned Owner / workstream: Commercial Counsel · Vendor Contracts Schedule: 2026-08-10 → 2026-09-20 · 15 estimated days · M1 Parent: AOS-LEGAL-000 Dependencies: none Related tasks: none

Outcome. Prepare vendor NDA, evaluation, source, firmware, and escrow checklist.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-LEGAL-007#checklist, AOS-HW-016#access-ladder. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Prepare vendor NDA, evaluation, source, firmware, and escrow checklist; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-LEGAL-007#nda;AOS-HW-016#information; sources: none; claims: none; experiments: none Phase / volume: Phase 1 · Volume 05 Specialist review: none

AOS-LEGAL-024 — Map EU CRA, privacy, update, and vulnerability obligations

Type / priority / status: Review · P0 · Planned Owner / workstream: Product Compliance Counsel · Product Compliance Schedule: 2026-08-17 → 2026-10-04 · 18 estimated days · M1 Parent: AOS-LEGAL-000 Dependencies: none Related tasks: none

Outcome. Map EU CRA, privacy, update, and vulnerability obligations.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-LEGAL-010#controls, AOS-LEGAL-004#cra. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Map EU CRA, privacy, update, and vulnerability obligations; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-LEGAL-010#review;AOS-LEGAL-004#eu-path; sources: SRC-097; claims: none; experiments: none Phase / volume: Phase 1 · Volume 05 Specialist review: none

AOS-LEGAL-025 — Build firmware and binary redistribution rights matrix

Type / priority / status: Task · P0 · Planned Owner / workstream: Open Source and Commercial Counsel · Artifact Rights Schedule: 2026-08-17 → 2026-10-11 · 20 estimated days · M1 Parent: AOS-LEGAL-000 Dependencies: none Related tasks: none

Outcome. Build firmware and binary redistribution rights matrix.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-LEGAL-001#artifact-rights, AOS-HW-016#rights. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Build firmware and binary redistribution rights matrix; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-LEGAL-001#device-and-protocol-work;AOS-HW-016#contract; sources: none; claims: none; experiments: none Phase / volume: Phase 1 · Volume 05 Specialist review: none

AOS-ODM

AOS-ODM-000 — Custom Device and ODM Readiness epic

Type / priority / status: Epic · P1 · Backlog Owner / workstream: Product Hardware Lead · Program Schedule: 2027-07-12 → 2030-07-07 · 3 estimated days · Continuous Parent: none Dependencies: none Related tasks: none

Outcome. Preserve manufacturing interfaces and prepare a later custom/ODM device route.

Scope. Produce and integrate: project charter; milestone map; owned backlog; status/evidence dashboard. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Preserve vendor replaceability, manufacturing/test interfaces, documentation rights, provisioning security, and certification responsibility.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Project has one accountable lead, an approved scope, milestone links, and no orphaned P0/P1 work
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: project charter; milestone map; owned backlog; status/evidence dashboard Verification: monthly project review and gate reconciliation Evidence: project update; dependency report; risk and budget delta Traceability: specs: AOS-HW-008#design-now; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-ODM-010 — Define manufacturing, provisioning, calibration, and test service contracts

Type / priority / status: Experiment · P1 · Backlog Owner / workstream: Product Hardware Architect · Manufacturing Architecture Schedule: 2027-07-12 → 2027-10-17 · 18 estimated days · M9 Parent: AOS-ODM-000 Dependencies: AOS-PLAT-020;AOS-SEC-022;AOS-PLAT-060;AOS-LEGAL-004 Related tasks: none

Outcome. Ensure board packages and platform services expose factory-test, identity, key injection, calibration, diagnostics, traceability, repair and decommission operations from the start.

Scope. Produce and integrate: manufacturing/test/provisioning IDLs; role/capability model; station simulator; audit/traceability; data ownership/retention. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Preserve vendor replaceability, manufacturing/test interfaces, documentation rights, provisioning security, and certification responsibility.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Factory authority is distinct from user/device authority, secrets are never exposed to generic stations, and operations are portable across vendors
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: manufacturing/test/provisioning IDLs; role/capability model; station simulator; audit/traceability; data ownership/retention Verification: EXP-080 mock factory flow for blank board through provision/calibrate/test/repair/decommission Evidence: interface review; mock flow/audit records; EXP-080 record Traceability: specs: AOS-HW-008#design-now;AOS-ARCH-006#manufacturing-interfaces; sources: none; claims: CLM-020; experiments: EXP-080 Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-ODM-011 — Freeze product-hardware architecture envelope

Type / priority / status: Task · P1 · Backlog Owner / workstream: Product Hardware Architect · Product Requirements Schedule: 2027-09-06 → 2027-12-26 · 15 estimated days · M9 Parent: AOS-ODM-000 Dependencies: AOS-LEGAL-010 Related tasks: none

Outcome. Define target quality, dimensions, display, camera, compute/memory/storage, radios, sensors, battery/runtime, thermal, security, repair, markets, lifecycle and cost ranges without selecting a vendor.

Scope. Produce and integrate: hardware requirements document; must/target/optional ranges; variant/market assumptions; interface and evidence requirements; exclusions. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Preserve vendor replaceability, manufacturing/test interfaces, documentation rights, provisioning security, and certification responsibility.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Requirements are measurable and prioritize user quality, portability/documentation and lifecycle rather than copying one phone’s parts list
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: hardware requirements document; must/target/optional ranges; variant/market assumptions; interface and evidence requirements; exclusions Verification: product/camera/cellular/power/security/regulatory/supply review and sensitivity scenarios Evidence: approved envelope; unresolved trade-offs; claim/certification impacts Traceability: specs: AOS-HW-010#decision-weights;AOS-PROD-006#tier-three;AOS-HW-008#architecture-envelope;AOS-PLAN-006#quality-device-route-decision; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-ODM-012 — Build preliminary product BOM and cost model

Type / priority / status: Task · P1 · Backlog Owner / workstream: Hardware Program/Finance Lead · Cost and Supply Schedule: 2027-11-29 → 2028-03-05 · 12 estimated days · M9 Parent: AOS-ODM-000 Dependencies: AOS-CELL-002 Related tasks: AOS-ODM-011;AOS-CAM-070

Outcome. Estimate modules/components, NRE, tooling, certification, assembly/test, yield, logistics, warranty, support and volume sensitivity for candidate architectures.

Scope. Produce and integrate: preliminary BOM; NRE/tooling/certification model; volume/MOQ scenarios; supply/lifecycle risk; target cost gaps. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Preserve vendor replaceability, manufacturing/test interfaces, documentation rights, provisioning security, and certification responsibility.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Model distinguishes component BOM from landed/support cost and exposes sole-source, obsolete, minimum-volume and yield assumptions
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: preliminary BOM; NRE/tooling/certification model; volume/MOQ scenarios; supply/lifecycle risk; target cost gaps Verification: quote sanity checks from multiple distributors/vendors/partners and sensitivity analysis Evidence: cost workbook/CSV; quote references; assumptions and ranges; gap actions Traceability: specs: AOS-HW-008#commercial-readiness;AOS-PLAN-004#cost-model; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-ODM-020 — Select module-versus-custom subsystem strategy

Type / priority / status: Decision · P1 · Backlog Owner / workstream: Product Hardware Architect · System Architecture Schedule: 2027-12-27 → 2028-03-05 · 10 estimated days · M9 Parent: AOS-ODM-000 Dependencies: AOS-ODM-011;AOS-CELL-002 Related tasks: AOS-CAM-070

Outcome. Choose which early developer-device functions use documented modules versus custom silicon/board integration to control quality, openness, cost and schedule.

Scope. Produce and integrate: subsystem make/buy/module/custom matrix; interface/rights/lifecycle requirements; replacement plan; performance/power/cost impacts. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Preserve vendor replaceability, manufacturing/test interfaces, documentation rights, provisioning security, and certification responsibility.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Any proprietary subsystem is replaceable at a declared boundary and its documentation/update/deployment rights are contract requirements
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: subsystem make/buy/module/custom matrix; interface/rights/lifecycle requirements; replacement plan; performance/power/cost impacts Verification: architecture/camera/cellular/security/supply review with at least two feasible configurations Evidence: decision record; interface contracts; cost/risk comparison Traceability: specs: AOS-HW-010#candidate-scorecard;AOS-HW-008#carrier-board-stage;AOS-HW-008#replaceability; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-ODM-021 — Design custom carrier-board reference architecture

Type / priority / status: Task · P1 · Backlog Owner / workstream: Lead Hardware Engineer · Carrier Board Schedule: 2028-03-06 → 2028-08-06 · 30 estimated days · M9 Parent: AOS-ODM-000 Dependencies: AOS-ODM-020;AOS-OPEN-030;AOS-PLAT-041;AOS-CAM-060;AOS-CELL-030 Related tasks: none

Outcome. Create a module-based developer-device architecture connecting compute, memory/storage, display/touch, camera, audio, cellular, Wi-Fi/Bluetooth, sensors, battery/power, debug and security.

Scope. Produce and integrate: block diagrams; interface/power/reset/clock/debug architecture; preliminary schematics; board-package plan; risk/bring-up/test plan. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Preserve vendor replaceability, manufacturing/test interfaces, documentation rights, provisioning security, and certification responsibility.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Every subsystem has documented electrical/logical contract, debug/recovery, power state, replacement path and assigned owner
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: block diagrams; interface/power/reset/clock/debug architecture; preliminary schematics; board-package plan; risk/bring-up/test plan Verification: independent schematic/architecture review, interface budgets and module-vendor feedback Evidence: design review; interface/power budgets; risk register; revision plan Traceability: specs: AOS-HW-008#carrier-board-stage;AOS-ARCH-006#board-package; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-ODM-022 — Define display, enclosure, battery, charging, thermal, and repair architecture

Type / priority / status: Task · P1 · Backlog Owner / workstream: Mechanical/Power Lead · Mechanical and Power Schedule: 2028-04-03 → 2028-08-20 · 24 estimated days · M9 Parent: AOS-ODM-000 Dependencies: AOS-ODM-011;AOS-PLAT-041;AOS-LEGAL-010 Related tasks: AOS-ODM-021

Outcome. Translate product quality into safe mechanical/electrical/thermal design with serviceability, user protection, regulatory and supply constraints.

Scope. Produce and integrate: display/touch shortlist; battery/charger architecture; thermal model; enclosure/service strategy; safety/certification requirements; test plan. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Preserve vendor replaceability, manufacturing/test interfaces, documentation rights, provisioning security, and certification responsibility.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Design has safe charge/thermal limits, measurable serviceability, known hazardous-energy controls and no unqualified battery/enclosure certification assumption
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: display/touch shortlist; battery/charger architecture; thermal model; enclosure/service strategy; safety/certification requirements; test plan Verification: supplier data, thermal/power simulation or prototype, safety/regulatory consultation and repair workflow review Evidence: mechanical/power dossier; thermal model; supplier/rights responses; risk updates Traceability: specs: AOS-HW-008#mechanical-and-power;AOS-LEGAL-004#development-stages; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-ODM-023 — Define production camera module and calibration architecture

Type / priority / status: Task · P1 · Backlog Owner / workstream: Camera Hardware Lead · Camera Hardware Schedule: 2028-10-02 → 2029-02-04 · 20 estimated days · M10 Parent: AOS-ODM-000 Dependencies: AOS-CAM-080;AOS-ODM-021;AOS-ODM-010 Related tasks: none

Outcome. Select sensor/lens/OIS/ISP/module options, physical interfaces, calibration stations/data ownership, tuning/support and replacement strategy.

Scope. Produce and integrate: camera module shortlist; optical/mechanical/interface design; calibration/test flow; tuning/rights/lifecycle plan; fallback module. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Preserve vendor replaceability, manufacturing/test interfaces, documentation rights, provisioning security, and certification responsibility.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Selected path meets measured quality and grants calibration/tuning/update/deployment/repair rights or has explicit replacement trigger
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: camera module shortlist; optical/mechanical/interface design; calibration/test flow; tuning/rights/lifecycle plan; fallback module Verification: vendor/module evaluation, quality harness, calibration mock and manufacturing/repair review Evidence: camera hardware decision; quality/rights/cost data; calibration station spec Traceability: specs: AOS-HW-006#controlled-proprietary-option;AOS-HW-008#camera-manufacturing; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-ODM-024 — Define production cellular/RF module and antenna architecture

Type / priority / status: Task · P1 · Backlog Owner / workstream: RF/Cellular Hardware Lead · RF and Cellular Schedule: 2028-10-02 → 2029-02-18 · 22 estimated days · M10 Parent: AOS-ODM-000 Dependencies: AOS-CELL-080;AOS-ODM-021;AOS-LEGAL-013 Related tasks: none

Outcome. Select module, bands/variants, SIM/eSIM, antennas/coexistence, firmware/support, certification inheritance and test interfaces.

Scope. Produce and integrate: module/antenna/variant architecture; certification matrix; RF test/connector plan; firmware/support agreement needs; fallback. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Preserve vendor replaceability, manufacturing/test interfaces, documentation rights, provisioning security, and certification responsibility.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Final-device certification responsibilities and antenna/enclosure/module constraints are explicit
  • voice/eSIM support matches product decision
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: module/antenna/variant architecture; certification matrix; RF test/connector plan; firmware/support agreement needs; fallback Verification: module vendor and accredited-lab review, preliminary RF/coexistence/thermal/power analysis Evidence: RF architecture review; certification impact; partner responses; cost/risk model Traceability: specs: AOS-HW-007#module-selection;AOS-LEGAL-004#cellular-path; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-ODM-025 — Design secure provisioning and device identity lifecycle

Type / priority / status: Task · P0 · Backlog Owner / workstream: Hardware Security Lead · Provisioning Schedule: 2028-05-15 → 2028-09-17 · 24 estimated days · M10 Parent: AOS-ODM-000 Dependencies: AOS-ODM-010;AOS-SEC-022;AOS-SEC-030;AOS-SEC-031 Related tasks: AOS-ODM-010

Outcome. Provision boot/update/device/attestation/service identities, certificates and revocation through least-authority audited factory stations and field recovery.

Scope. Produce and integrate: key ceremony; provisioning service/station roles; HSM/secure element options; audit/traceability; revocation/rework/decommission; contract requirements. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Preserve vendor replaceability, manufacturing/test interfaces, documentation rights, provisioning security, and certification responsibility.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • No universal device key exists in ordinary tooling, station compromise is containable/revocable, and rework/decommission preserve user security
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: key ceremony; provisioning service/station roles; HSM/secure element options; audit/traceability; revocation/rework/decommission; contract requirements Verification: mock factory/stolen station/misprovision/rework/returned device/key compromise and audit reconciliation Evidence: provisioning threat model; ceremony/drill logs; identity inventory; partner requirements Traceability: specs: AOS-ARCH-013#root-of-trust; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-ODM-026 — Design manufacturing and field diagnostic test suite

Type / priority / status: Task · P1 · Backlog Owner / workstream: Manufacturing Test Lead · Manufacturing Test Schedule: 2028-05-29 → 2028-10-15 · 24 estimated days · M10 Parent: AOS-ODM-000 Dependencies: AOS-ODM-010;AOS-PLAT-080;AOS-PLAT-060 Related tasks: AOS-ODM-010;AOS-ODM-021

Outcome. Create deterministic board/subsystem/calibration/end-of-line/burn-in/repair tests with traceability, limits, privacy and release compatibility.

Scope. Produce and integrate: test manifest/protocol; fixtures/station software; limits/calibration; serial traceability; rework/repair flows; data retention/export. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Preserve vendor replaceability, manufacturing/test interfaces, documentation rights, provisioning security, and certification responsibility.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Tests detect declared faults with controlled false results, preserve traceability, and cannot access user data or production keys beyond scope
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: test manifest/protocol; fixtures/station software; limits/calibration; serial traceability; rework/repair flows; data retention/export Verification: simulate good/seeded-bad boards and repeat across station instances/software versions Evidence: coverage/yield simulation; station audit; seeded defect detection; version compatibility report Traceability: specs: AOS-HW-008#manufacturing-test; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-ODM-030 — Complete custom carrier-board feasibility study

Type / priority / status: Experiment · P0 · Backlog Owner / workstream: Product Hardware Lead · Feasibility Schedule: 2028-11-13 → 2029-03-04 · 20 estimated days · M10 Parent: AOS-ODM-000 Dependencies: AOS-ODM-012;AOS-ODM-021;AOS-ODM-022;AOS-ODM-025;AOS-ODM-026 Related tasks: AOS-ODM-023;AOS-ODM-024

Outcome. Determine whether the module-based architecture meets product interfaces, camera, cellular, power, thermal, size, cost, supply, documentation and NRE goals.

Scope. Produce and integrate: integrated architecture; preliminary BOM/NRE/MOQ; supplier/partner feedback; compliance/rights/schedule risks; build/no-build recommendation. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Preserve vendor replaceability, manufacturing/test interfaces, documentation rights, provisioning security, and certification responsibility.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Recommendation quantifies unresolved critical paths and may stop the build
  • positive result has partner/documentation/supply path
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: integrated architecture; preliminary BOM/NRE/MOQ; supplier/partner feedback; compliance/rights/schedule risks; build/no-build recommendation Verification: EXP-081 independent cross-functional design review and at least two vendor/manufacturer feasibility inputs Evidence: feasibility report; updated diagrams/BOM/risk; EXP-081 record Traceability: specs: AOS-HW-008#carrier-board-stage;AOS-PLAN-006#quality-device-route-decision; sources: none; claims: CLM-024; experiments: EXP-081 Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-ODM-040 — Perform DFM, DFT, reliability, and serviceability review

Type / priority / status: Review · P1 · Backlog Owner / workstream: Manufacturing Engineering Lead · Manufacturing Readiness Schedule: 2029-02-19 → 2029-06-10 · 20 estimated days · M10 Parent: AOS-ODM-000 Dependencies: AOS-ODM-026 Related tasks: AOS-ODM-030

Outcome. Adapt selected design for fabrication, assembly, test coverage, yield, component variance, thermal/mechanical reliability, repair and lifecycle.

Scope. Produce and integrate: DFM/DFT review; tolerance/stack/yield assumptions; reliability/repair plan; test points/fixtures; component alternate rules. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Preserve vendor replaceability, manufacturing/test interfaces, documentation rights, provisioning security, and certification responsibility.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Critical nets/subsystems are testable, component substitutions are controlled, and repair/service operations do not defeat security/calibration
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: DFM/DFT review; tolerance/stack/yield assumptions; reliability/repair plan; test points/fixtures; component alternate rules Verification: EMS/ODM and independent hardware review with seeded manufacturing/repair scenarios Evidence: review findings/closure; revised design; yield/reliability risk model Traceability: specs: AOS-HW-008#manufacturing-readiness;AOS-LEGAL-004#development-stages; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-ODM-041 — Prepare EVT developer-device build plan

Type / priority / status: Task · P1 · Backlog Owner / workstream: Product Hardware Lead · EVT Planning Schedule: 2029-05-14 → 2029-08-19 · 15 estimated days · M10 Parent: AOS-ODM-000 Dependencies: AOS-ODM-030;AOS-LEGAL-013 Related tasks: AOS-ODM-040

Outcome. Define objectives, units, revisions, fixtures, firmware/software, bring-up, tests, issue triage, safety, data and disposal for the first custom hardware build.

Scope. Produce and integrate: EVT build matrix; unit allocation; bring-up/test/calibration schedule; acceptance/stop limits; safety/compliance pre-scan; budget. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Preserve vendor replaceability, manufacturing/test interfaces, documentation rights, provisioning security, and certification responsibility.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Build does not begin without frozen revision, recoverable software, safety controls, test coverage, owners and failure budget
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: EVT build matrix; unit allocation; bring-up/test/calibration schedule; acceptance/stop limits; safety/compliance pre-scan; budget Verification: cross-functional build-readiness review and dry-run of issue/traceability workflow Evidence: approved EVT plan; unit/test ownership; spend authorization; open blockers Traceability: specs: AOS-HW-008#evt-dvt-pvt;AOS-HW-009#procurement-controls; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-ODM-050 — Run product-hardware certification pre-scan

Type / priority / status: Review · P1 · Backlog Owner / workstream: Regulatory/Hardware Lead · Certification Schedule: 2029-06-25 → 2029-09-30 · 15 estimated days · M10 Parent: AOS-ODM-000 Dependencies: AOS-LEGAL-013;AOS-ODM-022;AOS-ODM-024 Related tasks: AOS-ODM-041

Outcome. Identify EMC/RF/SAR/safety/thermal/battery/cybersecurity/update and market failures before design freeze and expensive formal testing.

Scope. Produce and integrate: pre-scan samples/config; lab plan/results; failure remediation; variant/change-control impacts; formal test budget/schedule. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Preserve vendor replaceability, manufacturing/test interfaces, documentation rights, provisioning security, and certification responsibility.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Known failures are corrected or gate-blocking before DVT/formal submission and tested hardware/software configuration is traceable
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: pre-scan samples/config; lab plan/results; failure remediation; variant/change-control impacts; formal test budget/schedule Verification: accredited/qualified lab pre-scan and cross-functional result review Evidence: pre-scan reports; design changes; residual risk; certification plan Traceability: specs: AOS-LEGAL-004#development-stages;AOS-LEGAL-004#evidence-package; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-ODM-060 — Prepare and issue ODM/JDM/EMS request for information

Type / priority / status: Contact · P1 · Backlog Owner / workstream: Product Hardware/Commercial Lead · ODM Engagement Schedule: 2029-07-09 → 2029-11-25 · 18 estimated days · M11 Parent: AOS-ODM-000 Dependencies: AOS-ODM-011;AOS-ODM-012;AOS-ODM-030;AOS-LEGAL-010 Related tasks: AOS-LEGAL-014

Outcome. Test market capability for a later quality device using measurable requirements, portable interfaces, IP/documentation/security/certification and support obligations.

Scope. Produce and integrate: RFI package; technical/commercial/legal/security schedules; volume/market assumptions; response template; vendor longlist; confidentiality process. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Preserve vendor replaceability, manufacturing/test interfaces, documentation rights, provisioning security, and certification responsibility.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • RFI requests rights and evidence needed for Agent OS portability/update/support and does not promise volume, certification or feature readiness unsupported by program data
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: RFI package; technical/commercial/legal/security schedules; volume/market assumptions; response template; vendor longlist; confidentiality process Verification: cross-functional/legal review and issue to qualified vendors with controlled Q&A Evidence: issued RFI; recipient/response log; clarification record; no-go list Traceability: specs: AOS-HW-008#odm-rfi;AOS-LEGAL-005#contact-dossier; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-ODM-061 — Evaluate ODM/JDM/EMS responses and capability

Type / priority / status: Review · P1 · Backlog Owner / workstream: Product Hardware Sourcing Committee · ODM Engagement Schedule: 2029-10-29 → 2030-03-17 · 20 estimated days · M11 Parent: AOS-ODM-000 Dependencies: none Related tasks: AOS-ODM-060;AOS-LEGAL-014

Outcome. Score technical architecture, documentation, camera/radio/power quality, software rights, security, certification, manufacturing, supply, NRE/MOQ, support and exit risk.

Scope. Produce and integrate: response normalization; scorecard; technical/reference checks; site/audit plan; shortlist; clarification/red-flag log. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Preserve vendor replaceability, manufacturing/test interfaces, documentation rights, provisioning security, and certification responsibility.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Lowest price cannot override missing documentation, update/control, certification, quality or exit rights, and confidence is stated per answer
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: response normalization; scorecard; technical/reference checks; site/audit plan; shortlist; clarification/red-flag log Verification: independent functional scoring, reference checks and scenario analysis for schedule slip/vendor exit/security issue Evidence: scorecard; shortlist decision; assumptions/risks; due-diligence tasks Traceability: specs: AOS-HW-008#partner-scorecard;AOS-LEGAL-005#contractual-and-technical-asks; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-ODM-070 — Negotiate architecture, IP, tooling, security, quality, and lifecycle terms

Type / priority / status: Task · P1 · Backlog Owner / workstream: Commercial/Technology Counsel · ODM Engagement Schedule: 2030-01-21 → 2030-07-07 · 25 estimated days · Continuous Parent: AOS-ODM-000 Dependencies: AOS-LEGAL-014;AOS-SEC-061 Related tasks: AOS-LEGAL-014;AOS-ODM-061

Outcome. Convert shortlisted feasibility into enforceable ownership, interface, documentation, firmware, update, tooling, quality, certification, supply and termination obligations.

Scope. Produce and integrate: term sheet/contracts/SOW; IP/tooling/data matrix; security/update/SLA; quality/certification/supply responsibilities; escrow/exit where justified. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Preserve vendor replaceability, manufacturing/test interfaces, documentation rights, provisioning security, and certification responsibility.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • No deal makes Agent OS dependent on undocumented unmaintainable interfaces or leaves update keys, tooling, certification and post-termination support ambiguous
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: term sheet/contracts/SOW; IP/tooling/data matrix; security/update/SLA; quality/certification/supply responsibilities; escrow/exit where justified Verification: legal/technical/security/finance red-team and failure/termination scenario review Evidence: approved negotiation positions; residual exceptions; signed agreement or no-deal decision Traceability: specs: AOS-LEGAL-001#contract-principles; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-ODM-080 — Approve product hardware NRE, MOQ, and lifecycle business case

Type / priority / status: Decision · P0 · Backlog Owner / workstream: Program/Finance/Product Leadership · Business Case Schedule: 2030-04-15 → 2030-06-09 · 10 estimated days · Continuous Parent: AOS-ODM-000 Dependencies: AOS-ODM-012;AOS-ODM-050;AOS-ODM-061 Related tasks: AOS-ODM-070

Outcome. Decide whether expected demand, unit economics, support, certification, warranty, supply and strategic value justify product-hardware investment.

Scope. Produce and integrate: NRE/MOQ/cash/volume scenarios; landed/support/warranty costs; risk-adjusted options; funding/partner commitments; go/no-go. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Preserve vendor replaceability, manufacturing/test interfaces, documentation rights, provisioning security, and certification responsibility.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Go decision funds full lifecycle and downside reserves rather than only prototypes, and no-go preserves portable platform/community path
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: NRE/MOQ/cash/volume scenarios; landed/support/warranty costs; risk-adjusted options; funding/partner commitments; go/no-go Verification: independent finance/operations/legal/product review and downside/stress scenarios Evidence: business-case model; decision record; funding conditions; stop thresholds Traceability: specs: AOS-PLAN-004#funding-tranches;AOS-HW-008#commercial-readiness; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-ODM-090 — Issue production-device program gate

Type / priority / status: Decision · P0 · Backlog Owner / workstream: Program Board · Program Gate Schedule: 2030-06-10 → 2030-06-30 · 6 estimated days · Continuous Parent: AOS-ODM-000 Dependencies: AOS-ODM-080;AOS-PROD-110;AOS-CAM-080;AOS-CELL-080 Related tasks: AOS-SEC-100

Outcome. Authorize, defer, partner, or stop a contract-manufactured device based on product demand, quality, architecture, rights, certification, funding and support evidence.

Scope. Produce and integrate: production gate packet; selected route/partner; scope/markets/claims; funding and lifecycle commitments; fallback/termination plan. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Preserve vendor replaceability, manufacturing/test interfaces, documentation rights, provisioning security, and certification responsibility.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Production is approved only with sustainable update/security/support/certification and replaceable portable architecture
  • stopping remains an acceptable result
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: production gate packet; selected route/partner; scope/markets/claims; funding and lifecycle commitments; fallback/termination plan Verification: program-board review of all G0–G10 evidence and independent legal/security/finance inputs Evidence: signed decision; updated roadmap/budget/risk/public claims; contractual next steps Traceability: specs: AOS-PLAN-006#technical-gates;AOS-HW-008#odm-rfi; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-ODM-100 — Freeze future custom-device interface and provisioning requirements

Type / priority / status: Task · P1 · Planned Owner / workstream: Product Hardware Lead · Future Device Contract Schedule: 2027-12-27 → 2028-03-19 · 30 estimated days · M9 Parent: AOS-ODM-000 Dependencies: none Related tasks: none

Outcome. Freeze future custom-device interface and provisioning requirements.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-HW-008#design-now, AOS-HW-013#future-device. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Freeze future custom-device interface and provisioning requirements; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-HW-008#design-now;AOS-HW-013#quality-ceiling; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-ODM-101 — Prepare the future ODM/JDM RFI data-room schema

Type / priority / status: Task · P2 · Planned Owner / workstream: ODM Program Lead · ODM Preparation Schedule: 2028-05-15 → 2028-08-06 · 30 estimated days · M11 Parent: AOS-ODM-000 Dependencies: none Related tasks: none

Outcome. Prepare the future ODM/JDM RFI data-room schema.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-LEGAL-007#future-device, AOS-HW-008#partner-selection. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Prepare the future ODM/JDM RFI data-room schema; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-LEGAL-007#device;AOS-HW-008#partner-scorecard; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 05 Specialist review: none

AOS-OPEN

AOS-OPEN-000 — Documented and Open Hardware epic

Type / priority / status: Epic · P1 · Backlog Owner / workstream: Open Hardware Lead · Program Schedule: 2026-07-20 → 2029-07-22 · 3 estimated days · Continuous Parent: none Dependencies: none Related tasks: none

Outcome. Prove native portability on documented boards and phone-form-factor hardware.

Scope. Produce and integrate: project charter; milestone map; owned backlog; status/evidence dashboard. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record exact board/device revision and recovery path; hardware-specific behavior terminates in board packages and service backends.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Project has one accountable lead, an approved scope, milestone links, and no orphaned P0/P1 work
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: project charter; milestone map; owned backlog; status/evidence dashboard Verification: monthly project review and gate reconciliation Evidence: project update; dependency report; risk and budget delta Traceability: specs: AOS-HW-001#portfolio-policy; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-OPEN-001 — Implement hardware evidence and asset-control system

Type / priority / status: Task · P0 · Backlog Owner / workstream: Hardware Program Lead · Hardware Operations Schedule: 2026-07-13 → 2026-08-02 · 8 estimated days · M0 Parent: AOS-OPEN-000 Dependencies: none Related tasks: AOS-DOCS-004;AOS-LEGAL-004

Outcome. Track exact devices/boards/modules, revisions, firmware, rights, recovery, measurements, experiments, failures, and owners.

Scope. Produce and integrate: asset register; target dossier template; serial aliases; firmware/source/rights fields; evidence storage map. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record exact board/device revision and recovery path; hardware-specific behavior terminates in board packages and service backends.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • No modified hardware lacks exact revision, owner, recovery path, approved artifact status and experiment linkage
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: asset register; target dossier template; serial aliases; firmware/source/rights fields; evidence storage map Verification: register representative board, phone, camera, modem and instrument and perform audit Evidence: asset inventory; missing-field report; access-control review Traceability: specs: AOS-HW-001#target-dossier;AOS-TPL-EVIDENCE#identity; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-OPEN-002 — Build safe automated bring-up laboratory baseline

Type / priority / status: Purchase · P0 · Backlog Owner / workstream: Hardware Lab Engineer · Laboratory Schedule: 2026-07-20 → 2026-08-30 · 12 estimated days · M1 Parent: AOS-OPEN-000 Dependencies: none Related tasks: AOS-OPEN-001;AOS-DOCS-009

Outcome. Provide controlled power, UART, USB, relay, logic, thermal, network and evidence capture for repeatable destructive hardware work.

Scope. Produce and integrate: bench layout; ESD/fire/power controls; programmable power cycle; UART/USB capture; instrument inventory/calibration; scripts. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record exact board/device revision and recovery path; hardware-specific behavior terminates in board packages and service backends.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Power and device identity are logged, destructive operations have interlocks/recovery, and instruments have known calibration/status
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: bench layout; ESD/fire/power controls; programmable power cycle; UART/USB capture; instrument inventory/calibration; scripts Verification: repeat automated boot/failure capture and emergency shutdown on a sacrificial target Evidence: lab commissioning checklist; safety review; sample evidence bundle Traceability: specs: AOS-HW-009#laboratory-equipment;AOS-RES-004#evidence-integrity; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-OPEN-003 — Procure first hardware tranche with revision controls

Type / priority / status: Purchase · P0 · Backlog Owner / workstream: Hardware Program Lead · Procurement Schedule: 2026-07-20 → 2026-09-13 · 5 estimated days · M1 Parent: AOS-OPEN-000 Dependencies: none Related tasks: AOS-OPEN-001;AOS-DOCS-009;AOS-LEGAL-006

Outcome. Acquire duplicate documented boards, camera benches, open phones, Pixel units only after SKU review, storage, and debug/power equipment tied to tasks.

Scope. Produce and integrate: approved purchase orders; revision/SKU verification; return/warranty plan; spares; intake/stock backups. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record exact board/device revision and recovery path; hardware-specific behavior terminates in board packages and service backends.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Each purchase has a task/experiment, duplicate or fallback where destructive, and no Pixel SKU is bought as unlockable without verification
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: approved purchase orders; revision/SKU verification; return/warranty plan; spares; intake/stock backups Verification: receipt/intake against task, revision, serial, firmware, condition and recovery checklist Evidence: procurement ledger; intake photos/hashes; variance report Traceability: specs: AOS-HW-009#first-order;AOS-HW-009#procurement-controls; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-OPEN-010 — Create QEMU hardware profiles and CI target matrix

Type / priority / status: Task · P0 · Backlog Owner / workstream: Simulation Engineer · Emulation Schedule: 2026-09-21 → 2026-11-29 · 15 estimated days · M2 Parent: AOS-OPEN-000 Dependencies: AOS-CORE-010;AOS-CORE-011 Related tasks: AOS-PLAT-070

Outcome. Model CPU/memory/interrupt/storage/network/display/input/device-fault variants so kernel/platform/product tests do not rely on one emulated configuration.

Scope. Produce and integrate: minimal/standard/stress profiles; architecture matrix; fault profiles; CI schedule; support metadata. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record exact board/device revision and recovery path; hardware-specific behavior terminates in board packages and service backends.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • A passing result identifies architecture/profile and no critical test is run only on the most permissive configuration
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: minimal/standard/stress profiles; architecture matrix; fault profiles; CI schedule; support metadata Verification: run kernel/platform/product conformance across profiles and seeded resource/device failures Evidence: matrix dashboard; timing/resource metrics; failure coverage Traceability: specs: AOS-HW-001#qemu-track;AOS-ARCH-015#emulation; sources: none; claims: none; experiments: none Phase / volume: Phase 5 · Volume 03 Specialist review: none

AOS-OPEN-020 — Bring up Agent OS on BeaglePlay/AM625

Type / priority / status: Experiment · P0 · Backlog Owner / workstream: AM62x Bring-up Engineer · AM62x Schedule: 2026-10-19 → 2027-03-07 · 30 estimated days · M3 Parent: AOS-OPEN-000 Dependencies: AOS-OPEN-002;AOS-OPEN-003;AOS-CORE-012 Related tasks: AOS-PLAT-020

Outcome. Reach repeatable native early boot, console, memory, interrupts/timer, multicore policy, storage/USB/network seeds and recovery on documented AArch64 hardware.

Scope. Produce and integrate: board package; loader/boot path; UART; memory/IRQ/timer; recovery; exact-revision dossier; CI/lab scripts. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record exact board/device revision and recovery path; hardware-specific behavior terminates in board packages and service backends.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Two specimens boot repeatably from documented steps, recover from bad image, and architecture-neutral kernel sources remain unchanged
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: board package; loader/boot path; UART; memory/IRQ/timer; recovery; exact-revision dossier; CI/lab scripts Verification: EXP-014 on two specimens from power-off and after failed images Evidence: UART/boot logs; board manifest; recovery recording; EXP-014 record Traceability: specs: AOS-HW-004#beagleplay-track;AOS-HW-004#porting-sequence; sources: SRC-033;SRC-035; claims: CLM-011; experiments: EXP-014 Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-OPEN-021 — Enable BeaglePlay storage, USB, and network services

Type / priority / status: Task · P0 · Backlog Owner / workstream: AM62x Platform Engineer · AM62x Schedule: 2027-01-25 → 2027-05-02 · 25 estimated days · M3 Parent: AOS-OPEN-000 Dependencies: none Related tasks: AOS-OPEN-020;AOS-PLAT-031;AOS-PLAT-033;AOS-PLAT-034

Outcome. Run native block/storage, USB and Ethernet/network services through the portable driver and service contracts.

Scope. Produce and integrate: board drivers/backends; persistent system image; Ethernet/IP; USB debug/HID/storage; fault/restart tests. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record exact board/device revision and recovery path; hardware-specific behavior terminates in board packages and service backends.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Portable clients require no BeaglePlay types and driver faults cannot corrupt unrelated services or storage
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: board drivers/backends; persistent system image; Ethernet/IP; USB debug/HID/storage; fault/restart tests Verification: cold boot, I/O stress, cable/device loss, driver crash, update/recovery and cross-target conformance Evidence: service conformance matrix; throughput/error logs; restart/recovery evidence Traceability: specs: AOS-HW-004#beagleplay-track;AOS-ARCH-006#driver-domains; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-OPEN-022 — Deliver first frame and input on documented board

Type / priority / status: Task · P0 · Backlog Owner / workstream: Display/Input Bring-up Engineer · AM62x Schedule: 2027-02-08 → 2027-05-16 · 25 estimated days · M3 Parent: AOS-OPEN-000 Dependencies: none Related tasks: AOS-OPEN-020;AOS-PLAT-037;AOS-PLAT-035;AOS-PROD-050

Outcome. Drive display output and touch/USB input through portable display, buffer, compositor and input services.

Scope. Produce and integrate: display backend; mode/timing; framebuffer/buffer path; input backend; shell first frame; capture evidence. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record exact board/device revision and recovery path; hardware-specific behavior terminates in board packages and service backends.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • First frame is produced by native services, input reaches semantic shell, and the path recovers from display/driver restart
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: display backend; mode/timing; framebuffer/buffer path; input backend; shell first frame; capture evidence Verification: boot-to-frame, mode/error/restart, input latency/focus, repeated cold boots and two displays where practical Evidence: first-frame image/video; frame timing; input trace; M3 gate packet Traceability: specs: AOS-HW-004#display-path;AOS-ARCH-008#display-contract; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-OPEN-023 — Characterize documented-board power and thermal behavior

Type / priority / status: Task · P1 · Backlog Owner / workstream: Power Engineer · Power Schedule: 2027-02-22 → 2027-05-16 · 18 estimated days · M4 Parent: AOS-OPEN-000 Dependencies: AOS-OPEN-002 Related tasks: AOS-OPEN-020;AOS-PLAT-041

Outcome. Measure boot, idle, load, peripheral, thermal, suspend-candidate and wake behavior and implement initial power backends.

Scope. Produce and integrate: power/thermal backend; rail/system measurements; thermal zones; performance states; wake matrix; baseline report. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record exact board/device revision and recovery path; hardware-specific behavior terminates in board packages and service backends.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Measurements are repeatable with uncertainty stated and unsafe/unknown states are surfaced rather than hidden
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: power/thermal backend; rail/system measurements; thermal zones; performance states; wake matrix; baseline report Verification: controlled workloads, repeated ambient conditions, peripheral on/off, failed suspend participant and thermal trip tests Evidence: power traces; thermal images; calibration/environment record; recommendations Traceability: specs: AOS-ARCH-014#measurement;AOS-HW-004#power-and-thermal; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-OPEN-030 — Port Agent OS to a second documented SoC family

Type / priority / status: Experiment · P0 · Backlog Owner / workstream: Second-SoC Bring-up Lead · Portability Schedule: 2027-03-08 → 2027-09-05 · 40 estimated days · M5 Parent: AOS-OPEN-000 Dependencies: AOS-OPEN-020 Related tasks: AOS-PLAT-080

Outcome. Prove portable kernel/service/product contracts on an unrelated SoC using public or contractually usable documentation.

Scope. Produce and integrate: target dossier; architecture/board package; boot/recovery; storage/network/display/input; conformance/leakage report. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record exact board/device revision and recovery path; hardware-specific behavior terminates in board packages and service backends.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Portable services and product compile/run without source forks and all differences are board/backend declarations
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: target dossier; architecture/board package; boot/recovery; storage/network/display/input; conformance/leakage report Verification: EXP-015 and source/config comparison with QEMU/AM625 Evidence: port diff; conformance matrix; leakage fixes; EXP-015 record Traceability: specs: AOS-HW-004#second-soc-track;AOS-ARCH-001#portability-test; sources: none; claims: CLM-002;CLM-023; experiments: EXP-015 Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-OPEN-031 — Evaluate and bring up BeagleY-AI/AM67A vision target

Type / priority / status: Spike · P1 · Backlog Owner / workstream: Vision Board Engineer · Vision Boards Schedule: 2027-02-08 → 2027-07-11 · 30 estimated days · M5 Parent: AOS-OPEN-000 Dependencies: AOS-OPEN-003;AOS-PLAT-020;AOS-CAM-001 Related tasks: AOS-OPEN-020

Outcome. Use an open-design camera/vision-capable board to validate richer I/O, accelerator, camera and power contracts.

Scope. Produce and integrate: dossier; boot/recovery; camera/display/accelerator resource map; board package; feasibility report. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record exact board/device revision and recovery path; hardware-specific behavior terminates in board packages and service backends.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Target earns a maintained role only if camera/accelerator access adds unique evidence with sustainable documentation
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: dossier; boot/recovery; camera/display/accelerator resource map; board package; feasibility report Verification: repeat boot, public-source/document audit, camera-path experiment and cross-target service tests Evidence: board evidence bundle; first capture/frame; gap/rights report Traceability: specs: AOS-HW-004#camera-capable-boards;AOS-HW-006#documented-camera-bench; sources: SRC-034;SRC-036; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-OPEN-032 — Evaluate and bring up NXP i.MX 8M Plus target

Type / priority / status: Spike · P2 · Backlog Owner / workstream: NXP Bring-up Engineer · Vision Boards Schedule: 2027-04-05 → 2027-09-19 · 30 estimated days · M5 Parent: AOS-OPEN-000 Dependencies: AOS-OPEN-003;AOS-OPEN-020;AOS-CAM-001 Related tasks: none

Outcome. Test a second product-oriented camera SoC ecosystem, documentation/support path and portable camera/display/power backends.

Scope. Produce and integrate: board/vendor dossier; boot/recovery; ISP/camera/doc/rights map; board package prototype; cost/benefit comparison. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record exact board/device revision and recovery path; hardware-specific behavior terminates in board packages and service backends.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Continue only if it supplies documentation, camera, power or productization evidence not duplicated by AM62x path
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: board/vendor dossier; boot/recovery; ISP/camera/doc/rights map; board package prototype; cost/benefit comparison Verification: official-source review, vendor contact, native boot/camera feasibility and scorecard update Evidence: dossier; vendor response; experiment logs; decision record Traceability: specs: AOS-HW-004#camera-capable-boards;AOS-HW-010#candidate-scorecard; sources: SRC-037; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-OPEN-040 — Build Raspberry Pi PiSP camera reference bench

Type / priority / status: Purchase · P1 · Backlog Owner / workstream: Camera Lab Engineer · Camera Bench Schedule: 2026-10-05 → 2026-12-13 · 12 estimated days · M3 Parent: AOS-OPEN-000 Dependencies: AOS-OPEN-003 Related tasks: AOS-CAM-001;AOS-CAM-002

Outcome. Create an inexpensive repeatable RAW/tuning/computational-photography bench independent of phone bring-up and AOS-native ISP availability.

Scope. Produce and integrate: Pi board/camera modules; controlled capture image; scene/lighting fixtures; metadata/export pipeline; stock/reference dataset. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record exact board/device revision and recovery path; hardware-specific behavior terminates in board packages and service backends.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Bench produces repeatable RAW/metadata and processed reference captures with controlled configuration and no claim of native Agent OS support
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: Pi board/camera modules; controlled capture image; scene/lighting fixtures; metadata/export pipeline; stock/reference dataset Verification: repeat RAW/processed captures across fixed scenes/exposure/temperature and hash/calibration checks Evidence: bench dossier; sample dataset; repeatability metrics; asset records Traceability: specs: AOS-HW-006#reference-benches;AOS-HW-009#camera-lab; sources: SRC-038;SRC-039; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-OPEN-050 — Reach native early boot on PinePhone Pro

Type / priority / status: Experiment · P1 · Backlog Owner / workstream: Open Phone Bring-up Lead · PinePhone Pro Schedule: 2027-01-25 → 2027-07-11 · 35 estimated days · M6 Parent: AOS-OPEN-000 Dependencies: AOS-OPEN-002;AOS-OPEN-003;AOS-CORE-012;AOS-PLAT-020;AOS-LEGAL-006 Related tasks: none

Outcome. Boot Agent OS to structured console on phone-form hardware with exact revision, reversible flashing, power safety and documented recovery.

Scope. Produce and integrate: target dossier; boot/recovery; UART/USB logs; board package; memory/IRQ/timer/CPU baseline; safety notes. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record exact board/device revision and recovery path; hardware-specific behavior terminates in board packages and service backends.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Two devices recover and boot repeatably without relying on Linux at runtime, and phone charging safety limitations are documented
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: target dossier; boot/recovery; UART/USB logs; board package; memory/IRQ/timer/CPU baseline; safety notes Verification: EXP-020 on two devices, failed image recovery, charger/battery boundaries and cold boots Evidence: boot/recovery recordings; manifests; power traces; EXP-020 record Traceability: specs: AOS-HW-003#pinephone-pro-role;AOS-HW-003#bring-up-sequence; sources: SRC-029;SRC-030; claims: CLM-010; experiments: EXP-020 Phase / volume: Phase 5 · Volume 03 Specialist review: none

AOS-OPEN-051 — Implement PinePhone Pro board and peripheral services

Type / priority / status: Task · P1 · Backlog Owner / workstream: Open Phone Platform Lead · PinePhone Pro Schedule: 2027-05-17 → 2027-12-26 · 45 estimated days · M6 Parent: AOS-OPEN-000 Dependencies: AOS-PLAT-021;AOS-PLAT-024 Related tasks: AOS-OPEN-050

Outcome. Bring up storage, USB, display/touch, audio, network, sensors, power and modem transport in isolated native backends.

Scope. Produce and integrate: board package; subsystem drivers/services; lifecycle/power integration; target conformance; support limitations. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record exact board/device revision and recovery path; hardware-specific behavior terminates in board packages and service backends.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Each subsystem is independently stateful/restartable, portable clients remain unchanged, and unsupported functions are explicit
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: board package; subsystem drivers/services; lifecycle/power integration; target conformance; support limitations Verification: subsystem-by-subsystem fault/restart/suspend/recovery and cross-target tests Evidence: target matrix; logs/traces; unresolved subsystem dossier; power/safety review Traceability: specs: AOS-HW-003#bring-up-sequence;AOS-ARCH-006#board-package; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-OPEN-052 — Validate open-phone display, touch, and audio experience

Type / priority / status: Experiment · P0 · Backlog Owner / workstream: Open Phone UX Engineer · PinePhone Pro Schedule: 2027-08-09 → 2027-10-31 · 18 estimated days · M6 Parent: AOS-OPEN-000 Dependencies: AOS-PLAT-036;AOS-PLAT-037;AOS-PROD-050 Related tasks: AOS-OPEN-051

Outcome. Run the entity shell with measured frame/input/audio behavior and recoverable driver failures on PinePhone Pro.

Scope. Produce and integrate: display/touch/audio backends; shell profile; latency/frame/audio metrics; restart/rebind flows. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record exact board/device revision and recovery path; hardware-specific behavior terminates in board packages and service backends.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Core UI is usable at declared performance, input/audio paths are privacy-correct, and driver restart does not require device reboot
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: display/touch/audio backends; shell profile; latency/frame/audio metrics; restart/rebind flows Verification: EXP-022 common workflows, rotation/mode, touch/audio routing, driver crash and accessibility Evidence: video; traces/metrics; conformance; EXP-022 record Traceability: specs: AOS-HW-003#display-input-audio;AOS-PROD-006#tier-two; sources: none; claims: none; experiments: EXP-022 Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-OPEN-053 — Enable open-phone Wi-Fi and Bluetooth baseline

Type / priority / status: Task · P1 · Backlog Owner / workstream: Wireless Engineer · PinePhone Pro Schedule: 2027-07-26 → 2027-12-12 · 30 estimated days · M6 Parent: AOS-OPEN-000 Dependencies: AOS-PLAT-041 Related tasks: AOS-OPEN-051;AOS-PLAT-033

Outcome. Provide native connectivity or a clearly bounded documented module/backend route with secure pairing, lifecycle, power and update behavior.

Scope. Produce and integrate: radio dossier; native/module backend; Wi-Fi association/IP; Bluetooth discovery/pairing baseline; firmware/update record. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record exact board/device revision and recovery path; hardware-specific behavior terminates in board packages and service backends.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Radio firmware/protocol rights are known, credentials are protected, and connectivity cannot imply unsupported profiles/features
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: radio dossier; native/module backend; Wi-Fi association/IP; Bluetooth discovery/pairing baseline; firmware/update record Verification: malformed/hostile inputs, reconnect, suspend, key storage, power, firmware failure and coexistence tests Evidence: wireless matrix; security review; power traces; firmware provenance Traceability: specs: AOS-HW-003#connectivity;AOS-ARCH-007#network-service; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-OPEN-054 — Enable open-phone sensors and GNSS baseline

Type / priority / status: Task · P2 · Backlog Owner / workstream: Sensor/GNSS Engineer · PinePhone Pro Schedule: 2027-08-09 → 2027-11-14 · 20 estimated days · M8 Parent: AOS-OPEN-000 Dependencies: AOS-PLAT-013 Related tasks: AOS-OPEN-051

Outcome. Expose motion, orientation, proximity, ambient, location and time observations through permissioned portable services with calibration and privacy.

Scope. Produce and integrate: sensor/GNSS backends; calibration; permissions; timestamps/accuracy; power modes; fake/replay data. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record exact board/device revision and recovery path; hardware-specific behavior terminates in board packages and service backends.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Consumers receive accuracy/freshness/provenance and location/sensor access follows explicit foreground/background policy
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: sensor/GNSS backends; calibration; permissions; timestamps/accuracy; power modes; fake/replay data Verification: known-motion/location comparisons, denied/background access, suspend/resume and calibration persistence Evidence: accuracy/power report; privacy tests; sensor conformance Traceability: specs: AOS-ARCH-006#sensor-contract;AOS-ARCH-012#location-privacy; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-OPEN-055 — Measure and improve open-phone idle, suspend, wake, charging, and thermal behavior

Type / priority / status: Experiment · P0 · Backlog Owner / workstream: Mobile Power Engineer · PinePhone Pro Schedule: 2027-08-09 → 2027-12-26 · 28 estimated days · M6 Parent: AOS-OPEN-000 Dependencies: AOS-PLAT-041;AOS-OPEN-002 Related tasks: AOS-OPEN-051

Outcome. Establish safe phone power operation and quantify whether hardware can support a connected-device preview.

Scope. Produce and integrate: battery/charger backend; wake-source matrix; suspend states; idle/load/thermal profiles; safety limits; remediation backlog. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record exact board/device revision and recovery path; hardware-specific behavior terminates in board packages and service backends.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Unsafe charging/thermal behavior is blocked, wake causes are attributable, and preview claim includes measured idle/runtime limitations
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: battery/charger backend; wake-source matrix; suspend states; idle/load/thermal profiles; safety limits; remediation backlog Verification: EXP-023 repeated cycles, network/modem/display states, charger variants, low battery, wake storms and thermal limits Evidence: power traces; thermal report; battery cycle data; EXP-023 record Traceability: specs: AOS-HW-003#power-path;AOS-ARCH-014#measurement; sources: none; claims: none; experiments: EXP-023 Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-OPEN-056 — Validate open-phone update and recovery

Type / priority / status: Task · P0 · Backlog Owner / workstream: Open Phone Release Engineer · PinePhone Pro Schedule: 2027-10-04 → 2027-12-26 · 16 estimated days · M8 Parent: AOS-OPEN-000 Dependencies: AOS-OPEN-050;AOS-PLAT-052;AOS-SEC-041 Related tasks: AOS-PLAT-051

Outcome. Prove failed updates, corrupt state, lost user-space service, and bad board package can return to a trusted bootable state.

Scope. Produce and integrate: target update layout; signed recovery path; rollback/repair tooling; user-facing limitations; drill scripts. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record exact board/device revision and recovery path; hardware-specific behavior terminates in board packages and service backends.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • A published supported build cannot permanently brick from a single failed update under declared hardware assumptions
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: target update layout; signed recovery path; rollback/repair tooling; user-facing limitations; drill scripts Verification: interrupt every update phase, corrupt partitions/manifests and recover two devices from external instructions Evidence: recovery drill; update traces; boot-state inventory; support decision Traceability: specs: AOS-ARCH-013#recovery-environment;AOS-HW-003#support-definition; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-OPEN-057 — Integrate open-phone modem hardware with native cellular service

Type / priority / status: Task · P1 · Backlog Owner / workstream: Cellular/Open Phone Engineer · PinePhone Pro Schedule: 2027-08-09 → 2027-12-12 · 25 estimated days · M6 Parent: AOS-OPEN-000 Dependencies: AOS-PLAT-040 Related tasks: AOS-OPEN-051;AOS-CELL-020

Outcome. Connect the physically separate modem transport, control, power/reset and SIM paths without importing Linux runtime APIs.

Scope. Produce and integrate: modem hardware backend; power/reset; USB/serial transport; SIM routing; diagnostics; cellular-service binding. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record exact board/device revision and recovery path; hardware-specific behavior terminates in board packages and service backends.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Modem is treated as an untrusted peripheral, Linux D-Bus/network/plugin ABIs are absent, and failures do not destabilize core services
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: modem hardware backend; power/reset; USB/serial transport; SIM routing; diagnostics; cellular-service binding Verification: registration/data/SMS tasks, modem crash/replug/reset, suspend and capability isolation Evidence: modem traces; power/lifecycle tests; dependency scan; support matrix Traceability: specs: AOS-HW-003#modem-role;AOS-HW-007#native-cellular-stack; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-OPEN-060 — Design reproducible community hardware kit

Type / priority / status: Task · P1 · Backlog Owner / workstream: Community Hardware Lead · Community Hardware Schedule: 2028-07-10 → 2028-12-24 · 20 estimated days · M10 Parent: AOS-OPEN-000 Dependencies: AOS-OPEN-030;AOS-PLAT-090;AOS-COMM-050 Related tasks: none

Outcome. Select a documented board, peripherals, camera/display/input/power setup and recovery method that external contributors can obtain and reproduce.

Scope. Produce and integrate: kit BOM/revisions; assembly/flash/recovery guide; test image; conformance checklist; support/lifecycle/alternatives. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record exact board/device revision and recovery path; hardware-specific behavior terminates in board packages and service backends.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Kit has at least two supply sources or successor plan, exact revisions, non-destructive recovery, and tests that identify unsupported substitutions
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: kit BOM/revisions; assembly/flash/recovery guide; test image; conformance checklist; support/lifecycle/alternatives Verification: internal clean-room-style reproduction before external pilot Evidence: kit build records; availability/pricing check; issue list; maintainer commitment Traceability: specs: AOS-GOV-002#hardware-maintainers;AOS-HW-008#community-reference-kit; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-OPEN-070 — Complete current Fairphone feasibility dossier

Type / priority / status: Experiment · P2 · Backlog Owner / workstream: Partner Hardware Researcher · Semi-Open Hardware Schedule: 2026-10-05 → 2027-01-24 · 10 estimated days · M5 Parent: AOS-OPEN-000 Dependencies: AOS-LEGAL-006;AOS-OPEN-001;AOS-OPEN-003 Related tasks: none

Outcome. Determine whether a current Fairphone offers a useful quality/documentation/boot/supply partnership route without making Android a native dependency.

Scope. Produce and integrate: exact-SKU dossier; source/docs/firmware/boot/camera/power/radio/rights/supply analysis; vendor outreach; scorecard. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record exact board/device revision and recovery path; hardware-specific behavior terminates in board packages and service backends.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Recommendation states unique evidence, native blockers, rights, cost, partner ask and stop condition rather than equating source release with openness
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: exact-SKU dossier; source/docs/firmware/boot/camera/power/radio/rights/supply analysis; vendor outreach; scorecard Verification: EXP-024 and counsel/architecture/hardware review Evidence: dossier; vendor response; score changes; EXP-024 record Traceability: specs: AOS-HW-005#fairphone-track;AOS-HW-005#dossier-requirements; sources: SRC-026;SRC-027; claims: CLM-022; experiments: EXP-024 Phase / volume: Phase 1 · Volume 03 Specialist review: none

AOS-OPEN-071 — Complete Sony Open Devices feasibility dossier

Type / priority / status: Experiment · P2 · Backlog Owner / workstream: Partner Hardware Researcher · Semi-Open Hardware Schedule: 2026-10-05 → 2027-01-24 · 10 estimated days · M5 Parent: AOS-OPEN-000 Dependencies: AOS-LEGAL-006;AOS-OPEN-001 Related tasks: none

Outcome. Determine whether a current supported Xperia program provides a useful quality/reference/partner route for native Agent OS work.

Scope. Produce and integrate: supported-device dossier; AOSP binary/source/boot/camera/power/radio/rights/lifecycle analysis; outreach; scorecard. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record exact board/device revision and recovery path; hardware-specific behavior terminates in board packages and service backends.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Recommendation distinguishes AOSP support from native hardware documentation and identifies any contract needed for Agent OS
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: supported-device dossier; AOSP binary/source/boot/camera/power/radio/rights/lifecycle analysis; outreach; scorecard Verification: EXP-025 and review against public program terms/current device support Evidence: dossier; vendor response; score changes; EXP-025 record Traceability: specs: AOS-HW-005#sony-track;AOS-HW-005#dossier-requirements; sources: SRC-028; claims: CLM-022; experiments: EXP-025 Phase / volume: Phase 1 · Volume 03 Specialist review: none

AOS-OPEN-072 — Evaluate Librem 5 as modular-radio/manufacturing prior art

Type / priority / status: Spike · P3 · Backlog Owner / workstream: Open Hardware Researcher · Open Phone Research Schedule: 2026-11-02 → 2027-01-10 · 6 estimated days · M5 Parent: AOS-OPEN-000 Dependencies: AOS-OPEN-001;AOS-LEGAL-006 Related tasks: none

Outcome. Assess whether its hardware documentation, replaceable modem/Wi-Fi, kill switches and supply/manufacturing experience justify acquisition or collaboration.

Scope. Produce and integrate: public-source dossier; modularity/power/performance/cost analysis; contact decision; scorecard update. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record exact board/device revision and recovery path; hardware-specific behavior terminates in board packages and service backends.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Purchase occurs only if expected modular/certification/manufacturing evidence exceeds cost and duplicates
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: public-source dossier; modularity/power/performance/cost analysis; contact decision; scorecard update Verification: source/vendor review and comparison to PinePhone/custom carrier goals Evidence: dossier; buy/no-buy decision; related architecture findings Traceability: specs: AOS-HW-003#librem-role;AOS-HW-010#candidate-scorecard; sources: none; claims: none; experiments: none Phase / volume: Phase 1 · Volume 03 Specialist review: none

AOS-OPEN-080 — Select maintained hardware portfolio after M6/M7

Type / priority / status: Decision · P0 · Backlog Owner / workstream: Architecture Council / Program Lead · Portfolio Schedule: 2028-01-24 → 2028-02-13 · 6 estimated days · M9 Parent: AOS-OPEN-000 Dependencies: AOS-OPEN-030;AOS-OPEN-055;AOS-OPEN-070;AOS-OPEN-071 Related tasks: AOS-P9-070

Outcome. Re-score QEMU, documented boards, open phones, Pixel, semi-open candidates and custom path from measured evidence and owner capacity.

Scope. Produce and integrate: updated scorecard; maintained/experimental/retired assignments; budgets/owners; route hypotheses; public support language. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Record exact board/device revision and recovery path; hardware-specific behavior terminates in board packages and service backends.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • No target remains maintained without unique value, owner, specimens, recovery, test scope and lifecycle budget
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: updated scorecard; maintained/experimental/retired assignments; budgets/owners; route hypotheses; public support language Verification: cross-functional gate review with total cost and capacity model Evidence: signed portfolio decision; retired-target migration plan; risk/budget updates Traceability: specs: AOS-HW-010#evidence-updates;AOS-PLAN-006#technical-gates; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-OPEN-090 — Produce the BeagleY-AI and AM67A target dossier

Type / priority / status: Task · P1 · Planned Owner / workstream: Open Hardware Lead · Target Dossier Schedule: 2026-08-10 → 2026-09-20 · 15 estimated days · M1 Parent: AOS-OPEN-000 Dependencies: none Related tasks: none

Outcome. Produce the BeagleY-AI and AM67A target dossier.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-HW-011#candidate-table, AOS-HW-004#target-dossier. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Produce the BeagleY-AI and AM67A target dossier; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-HW-011#candidates;AOS-HW-004#documentation-audit; sources: SRC-087;SRC-088; claims: none; experiments: none Phase / volume: Phase 1 · Volume 03 Specialist review: none

AOS-OPEN-091 — Produce the NXP i.MX 8M Plus target and camera dossier

Type / priority / status: Task · P1 · Planned Owner / workstream: Open Hardware Lead · Target Dossier Schedule: 2026-08-10 → 2026-09-27 · 18 estimated days · M1 Parent: AOS-OPEN-000 Dependencies: none Related tasks: none

Outcome. Produce the NXP i.MX 8M Plus target and camera dossier.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-HW-011#candidate-table, AOS-HW-012#documented-isp. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Produce the NXP i.MX 8M Plus target and camera dossier; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-HW-011#candidates;AOS-HW-012#tracks; sources: SRC-089;SRC-090;SRC-091; claims: none; experiments: none Phase / volume: Phase 1 · Volume 03 Specialist review: none

AOS-OPEN-092 — Produce the RK3588 performance-target dossier

Type / priority / status: Task · P1 · Planned Owner / workstream: Open Hardware Lead · Target Dossier Schedule: 2026-08-17 → 2026-10-04 · 18 estimated days · M1 Parent: AOS-OPEN-000 Dependencies: none Related tasks: none

Outcome. Produce the RK3588 performance-target dossier.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-HW-011#candidate-table, AOS-HW-013#performance. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Produce the RK3588 performance-target dossier; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-HW-011#candidates;AOS-HW-013#categories; sources: SRC-092;SRC-093; claims: none; experiments: none Phase / volume: Phase 1 · Volume 03 Specialist review: none

AOS-OPEN-093 — Produce the VIM3/A311D reference dossier

Type / priority / status: Task · P1 · Planned Owner / workstream: Open Hardware Lead · Target Dossier Schedule: 2026-08-17 → 2026-09-27 · 15 estimated days · M1 Parent: AOS-OPEN-000 Dependencies: none Related tasks: none

Outcome. Produce the VIM3/A311D reference dossier.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-HW-011#candidate-table, AOS-RES-007#systems. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Produce the VIM3/A311D reference dossier; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-HW-011#candidates;AOS-RES-007#dimensions; sources: none; claims: none; experiments: none Phase / volume: Phase 1 · Volume 03 Specialist review: none

AOS-OPEN-094 — Refresh the PinePhone Pro native phone-form dossier

Type / priority / status: Review · P1 · Planned Owner / workstream: Open Phone Lead · Open Phone Schedule: 2026-08-17 → 2026-09-27 · 15 estimated days · M1 Parent: AOS-OPEN-000 Dependencies: none Related tasks: none

Outcome. Refresh the PinePhone Pro native phone-form dossier.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-HW-003#pinephone-pro-role, AOS-HW-011#candidate-table. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Refresh the PinePhone Pro native phone-form dossier; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-HW-003#pinephone-pro-role;AOS-HW-011#candidates; sources: SRC-085;SRC-086; claims: none; experiments: none Phase / volume: Phase 1 · Volume 03 Specialist review: none

AOS-OPEN-095 — Compare Fairphone and Sony as semi-open quality bridges

Type / priority / status: Review · P1 · Planned Owner / workstream: Quality Hardware Lead · Quality Bridge Schedule: 2026-08-24 → 2026-10-11 · 18 estimated days · M1 Parent: AOS-OPEN-000 Dependencies: none Related tasks: none

Outcome. Compare Fairphone and Sony as semi-open quality bridges.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-HW-005#dossier-requirements, AOS-HW-011#candidate-table. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Compare Fairphone and Sony as semi-open quality bridges; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-HW-005#dossier-requirements;AOS-HW-011#candidates; sources: SRC-083;SRC-084; claims: none; experiments: none Phase / volume: Phase 1 · Volume 03 Specialist review: none

AOS-OPEN-096 — Select two unrelated documented SoC families for native ports

Type / priority / status: Decision · P0 · Planned Owner / workstream: Architecture and Hardware Leads · Target Selection Schedule: 2026-09-21 → 2026-10-11 · 8 estimated days · M1 Parent: AOS-OPEN-000 Dependencies: none Related tasks: AOS-OPEN-090;AOS-OPEN-091;AOS-OPEN-092;AOS-OPEN-093

Outcome. Select two unrelated documented SoC families for native ports.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-HW-011#selection, AOS-ARCH-016#portability-proof. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Select two unrelated documented SoC families for native ports; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-HW-011#selection;AOS-ARCH-016#conformance; sources: none; claims: none; experiments: none Phase / volume: Phase 1 · Volume 03 Specialist review: none

AOS-P9

AOS-P9-000 — Pixel 9 Quality-Hardware Research epic

Type / priority / status: Epic · P1 · Backlog Owner / workstream: Pixel Track Lead · Program Schedule: 2026-07-27 → 2028-02-06 · 3 estimated days · Continuous Parent: none Dependencies: none Related tasks: none

Outcome. Use Pixel 9 minimally as a quality oracle and bounded native feasibility target.

Scope. Produce and integrate: project charter; milestone map; owned backlog; status/evidence dashboard. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep every Android/Linux artifact inside the Pixel adapter, stock-oracle, trace, or recovery boundary; do not alter portable Agent OS contracts to match a vendor ABI.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Project has one accountable lead, an approved scope, milestone links, and no orphaned P0/P1 work
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: project charter; milestone map; owned backlog; status/evidence dashboard Verification: monthly project review and gate reconciliation Evidence: project update; dependency report; risk and budget delta Traceability: specs: AOS-HW-002#track-purpose; sources: none; claims: none; experiments: none Phase / volume: Phase 1 · Volume 03 Specialist review: none

AOS-P9-001 — Complete Pixel 9 target and legal dossier

Type / priority / status: Task · P0 · Backlog Owner / workstream: Pixel Track Lead · Pixel Dossier Schedule: 2026-07-27 → 2026-09-20 · 15 estimated days · M1 Parent: AOS-P9-000 Dependencies: none Related tasks: AOS-OPEN-001;AOS-DOCS-004;AOS-LEGAL-005

Outcome. Record exact SKU, SoC/subsystems, boot/recovery, public sources, factory artifacts, terms, firmware, debug, camera, power, radio, security and unknowns before native work.

Scope. Produce and integrate: target dossier; subsystem/source/rights map; exact-SKU matrix; experiment/stop plan; artifact controls. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep every Android/Linux artifact inside the Pixel adapter, stock-oracle, trace, or recovery boundary; do not alter portable Agent OS contracts to match a vendor ABI.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • No native Pixel implementation task begins with an unspecified SKU, source class, recovery path, artifact right or stop condition
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: target dossier; subsystem/source/rights map; exact-SKU matrix; experiment/stop plan; artifact controls Verification: architecture/hardware/security/legal review against official/current sources and acquired unit Evidence: dossier; approved/blocked method list; unresolved-source matrix Traceability: specs: AOS-HW-002#target-dossier;AOS-LEGAL-002#pixel-application; sources: SRC-019;SRC-020;SRC-021; claims: none; experiments: none Phase / volume: Phase 1 · Volume 03 Specialist review: none

AOS-P9-010 — Verify Pixel 9 acquisition, unlock, relock, and stock restore

Type / priority / status: Experiment · P0 · Backlog Owner / workstream: Pixel Lab Engineer · Pixel Lab Schedule: 2026-08-10 → 2026-10-04 · 7 estimated days · M1 Parent: AOS-P9-000 Dependencies: none Related tasks: AOS-P9-001;AOS-OPEN-003;AOS-LEGAL-006

Outcome. Acquire appropriate non-carrier-restricted development units and prove a reversible documented unlock/recovery path before destructive research.

Scope. Produce and integrate: SKU/seller records; stock backups; unlock/relock/restore procedure; data-wipe/user-warning record; spare/stock oracle allocation. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep every Android/Linux artifact inside the Pixel adapter, stock-oracle, trace, or recovery boundary; do not alter portable Agent OS contracts to match a vendor ABI.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Exact acquired SKU is demonstrably unlockable/restorable under approved terms and no irreplaceable user data/credentials are used
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: SKU/seller records; stock backups; unlock/relock/restore procedure; data-wipe/user-warning record; spare/stock oracle allocation Verification: EXP-030 on at least two development units with factory restore and one preserved stock oracle Evidence: unlock/restore logs; purchase/firmware hashes; EXP-030 record Traceability: specs: AOS-HW-002#device-acquisition;AOS-LEGAL-001#device-and-protocol-work; sources: SRC-019;SRC-020; claims: CLM-005; experiments: EXP-030 Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-P9-011 — Automate Pixel stock recovery and artifact inventory

Type / priority / status: Task · P0 · Backlog Owner / workstream: Pixel Lab Engineer · Pixel Lab Schedule: 2026-08-24 → 2026-10-18 · 10 estimated days · M1 Parent: AOS-P9-000 Dependencies: none Related tasks: AOS-P9-010;AOS-P9-001

Outcome. Create safe repeatable stock-image restoration, build/firmware identification, partition inventory, boot-state capture and device reset procedures.

Scope. Produce and integrate: recovery scripts/runbook; artifact/hash/license inventory; boot-state capture; destructive-operation interlocks; audit log. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep every Android/Linux artifact inside the Pixel adapter, stock-oracle, trace, or recovery boundary; do not alter portable Agent OS contracts to match a vendor ABI.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Every experiment can return the unit to a known stock state and no unapproved artifact is redistributed or committed
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: recovery scripts/runbook; artifact/hash/license inventory; boot-state capture; destructive-operation interlocks; audit log Verification: recover from intentionally bad noncritical image/state and reproduce on a second unit Evidence: recovery drill; artifact manifest; safety review; time-to-recover metrics Traceability: specs: AOS-HW-002#recovery-first;AOS-LEGAL-002#artifact-controls; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-P9-015 — Enforce Pixel Android/Linux dependency containment

Type / priority / status: Experiment · P0 · Backlog Owner / workstream: Architecture/Build Engineer · Containment Schedule: 2026-08-24 → 2028-02-06 · 10 estimated days · M7 Parent: AOS-P9-000 Dependencies: AOS-DOCS-007 Related tasks: AOS-P9-001;AOS-PLAT-001

Outcome. Continuously prove that Pixel-only stock, sidecar, trace, firmware and bring-up aids do not enter native portable code, IDL, schemas or product state.

Scope. Produce and integrate: forbidden dependency/type rules; source/binary graph scanner; adapter inventory; retirement ledger; CI gate. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep every Android/Linux artifact inside the Pixel adapter, stock-oracle, trace, or recovery boundary; do not alter portable Agent OS contracts to match a vendor ABI.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Seeded leakage fails CI, every temporary dependency has owner/expiry/alternative, and portable packages build without Pixel artifacts
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: forbidden dependency/type rules; source/binary graph scanner; adapter inventory; retirement ledger; CI gate Verification: EXP-031 with seeded Android/Linux/Binder/POSIX/vendor types and actual Pixel components Evidence: dependency reports; adapter/retirement dashboard; EXP-031 records Traceability: specs: AOS-ARCH-011#pixel-legacy-boundary;AOS-ADR-0004#decision; sources: none; claims: CLM-004; experiments: EXP-031 Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-P9-020 — Build Pixel 9 stock camera/display/power quality oracle

Type / priority / status: Experiment · P1 · Backlog Owner / workstream: Pixel Quality Engineer · Quality Oracle Schedule: 2026-09-21 → 2027-01-10 · 18 estimated days · M5 Parent: AOS-P9-000 Dependencies: AOS-OPEN-002 Related tasks: AOS-P9-010;AOS-CAM-001;AOS-LEGAL-008

Outcome. Capture repeatable stock baselines and test procedures for image/video, display/frame/input, battery/thermal/suspend and common workflows.

Scope. Produce and integrate: stock test image/config; camera RAW/processed/video corpus where accessible; display/power traces; workflow baselines; metadata/provenance. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep every Android/Linux artifact inside the Pixel adapter, stock-oracle, trace, or recovery boundary; do not alter portable Agent OS contracts to match a vendor ABI.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Baseline identifies stock build/settings/unit/conditions, can be repeated, and is used only as comparison—not evidence of native feasibility
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: stock test image/config; camera RAW/processed/video corpus where accessible; display/power traces; workflow baselines; metadata/provenance Verification: EXP-035 repeated across two units, software versions, controlled scenes/workloads and battery states Evidence: oracle dataset; repeatability/variance report; EXP-035 record Traceability: specs: AOS-HW-002#quality-oracle;AOS-HW-006#quality-definition; sources: SRC-021; claims: none; experiments: EXP-035 Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-P9-021 — Implement approved Pixel trace and observation tooling

Type / priority / status: Task · P1 · Backlog Owner / workstream: Pixel Evidence Engineer · Trace and Observation Schedule: 2026-10-05 → 2027-01-24 · 18 estimated days · M3 Parent: AOS-P9-000 Dependencies: AOS-LEGAL-007 Related tasks: AOS-PLAT-081;AOS-P9-011

Outcome. Collect sanitized black-box and stock-system observations needed for native contract tests without copying protected implementation or personal data.

Scope. Produce and integrate: observation scripts; portable trace adapters; sanitizer; source/provenance/retention manifest; black-box test fixtures. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep every Android/Linux artifact inside the Pixel adapter, stock-oracle, trace, or recovery boundary; do not alter portable Agent OS contracts to match a vendor ABI.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Only approved functional observations leave quarantine, traces contain no Android/Linux ABI or protected/personal payload, and version is explicit
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: observation scripts; portable trace adapters; sanitizer; source/provenance/retention manifest; black-box test fixtures Verification: legal/source review, sensitive/proprietary scan, deterministic replay and version-change test Evidence: approved trace corpus; sanitation report; observation protocol; hashes Traceability: specs: AOS-LEGAL-002#workflow; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-P9-022 — Define temporary Pixel sidecar/proxy contracts and retirement plan

Type / priority / status: Task · P2 · Backlog Owner / workstream: Pixel Adapter Architect · Sidecar Schedule: 2026-11-30 → 2027-02-21 · 15 estimated days · M4 Parent: AOS-P9-000 Dependencies: none Related tasks: AOS-P9-015;AOS-P9-021;AOS-PLAT-039;AOS-PLAT-040

Outcome. Allow selected stock-OS device capabilities to feed experiments through explicit portable proxy services while preserving native replacement boundaries.

Scope. Produce and integrate: proxy threat model; portable message schemas; authentication/encryption; mock/native backends; dependency and retirement tasks; visible labeling. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep every Android/Linux artifact inside the Pixel adapter, stock-oracle, trace, or recovery boundary; do not alter portable Agent OS contracts to match a vendor ABI.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Proxy cannot grant broader device/Android authority, product code cannot distinguish it except declared capability quality, and it has a removal/limit gate
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: proxy threat model; portable message schemas; authentication/encryption; mock/native backends; dependency and retirement tasks; visible labeling Verification: disconnect/compromise/version mismatch/replay/data minimization and native-backend swap tests Evidence: adapter conformance; threat review; dependency graph; user-facing labels Traceability: specs: AOS-HW-002#sidecar-and-proxy;AOS-ARCH-011#compatibility-cells; sources: none; claims: none; experiments: none Phase / volume: Phase 2 · Volume 03 Specialist review: none

AOS-P9-030 — Reach lawful reproducible Agent OS early diagnostics on Pixel 9

Type / priority / status: Experiment · P0 · Backlog Owner / workstream: Pixel Boot Engineer · Native Bring-up Schedule: 2027-01-25 → 2027-06-13 · 30 estimated days · M7 Parent: AOS-P9-000 Dependencies: AOS-P9-010;AOS-P9-011;AOS-LEGAL-007;AOS-CORE-012 Related tasks: none

Outcome. Determine whether the Pixel boot chain can load Agent OS far enough to produce independent early diagnostics without undocumented portable dependencies.

Scope. Produce and integrate: boot-chain map; loader/image path; early console/trace channel; CPU/memory seed; recovery-safe automation; provenance dossier. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep every Android/Linux artifact inside the Pixel adapter, stock-oracle, trace, or recovery boundary; do not alter portable Agent OS contracts to match a vendor ABI.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Positive result is reproducible and lawfully documentable
  • negative result triggers stop/limit rather than hidden use of Android/Linux runtime
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: boot-chain map; loader/image path; early console/trace channel; CPU/memory seed; recovery-safe automation; provenance dossier Verification: EXP-032 repeated from stock/recovery states on two units, malformed image and loss-of-diagnostic tests Evidence: boot logs/traces; artifact/source manifest; time/cost log; EXP-032 record Traceability: specs: AOS-HW-002#phase-one-boot;AOS-PLAN-006#pixel-stop-criteria; sources: none; claims: CLM-006; experiments: EXP-032 Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-P9-031 — Map Pixel boot, memory, interrupt, timer, IOMMU, and storage architecture

Type / priority / status: Spike · P1 · Backlog Owner / workstream: Pixel Platform Architect · Native Bring-up Schedule: 2027-04-19 → 2027-09-05 · 30 estimated days · M7 Parent: AOS-P9-000 Dependencies: AOS-CORE-037;AOS-PLAT-020 Related tasks: AOS-P9-030

Outcome. Produce an approved functional specification and native board-package plan for essential SoC/board primitives after early diagnostics.

Scope. Produce and integrate: functional specs; board resource manifest; memory/IOMMU/storage maps; test plan; unknown/proprietary dependency and cost report. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep every Android/Linux artifact inside the Pixel adapter, stock-oracle, trace, or recovery boundary; do not alter portable Agent OS contracts to match a vendor ABI.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Continue implementation only for subsystems with sufficient lawful specification and safe recovery
  • unknowns remain explicit
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: functional specs; board resource manifest; memory/IOMMU/storage maps; test plan; unknown/proprietary dependency and cost report Verification: clean-room/source review, controlled probes, consistency with boot traces and independent reviewer Evidence: approved specifications; experiment logs; residual-risk/cost matrix Traceability: specs: AOS-HW-002#phase-two-platform;AOS-LEGAL-002#workflow; sources: none; claims: none; experiments: none Phase / volume: Phase 5 · Volume 03 Specialist review: none

AOS-P9-040 — Evaluate native Pixel storage, USB, display, and touch paths

Type / priority / status: Experiment · P0 · Backlog Owner / workstream: Pixel I/O Lead · Native Bring-up Schedule: 2027-05-31 → 2027-11-28 · 45 estimated days · M7 Parent: AOS-P9-000 Dependencies: AOS-PLAT-031 Related tasks: AOS-P9-031;AOS-PLAT-034;AOS-PLAT-037;AOS-PLAT-035

Outcome. Prove or bound the route to persistent storage, USB debug/recovery, first frame and touch without leaking vendor interfaces into portable services.

Scope. Produce and integrate: native/functional-spec backends or bounded blockers; first-frame/storage/USB/touch evidence; interface leakage and recovery report. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep every Android/Linux artifact inside the Pixel adapter, stock-oracle, trace, or recovery boundary; do not alter portable Agent OS contracts to match a vendor ABI.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • A positive path uses native portable service contracts and a negative path names exact unavailable dependency, legal constraint, cost and fallback
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: native/functional-spec backends or bounded blockers; first-frame/storage/USB/touch evidence; interface leakage and recovery report Verification: EXP-033 cold boots, I/O/display/touch/reset/driver-fault and bad-image recovery across two units Evidence: first frame/logs; storage/USB tests; interface diff; EXP-033 record Traceability: specs: AOS-HW-002#phase-three-essential-io;AOS-ARCH-006#board-package; sources: none; claims: CLM-006; experiments: EXP-033 Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-P9-041 — Evaluate native Pixel audio and basic device-service paths

Type / priority / status: Spike · P2 · Backlog Owner / workstream: Pixel Device Services Engineer · Native Bring-up Schedule: 2027-06-28 → 2027-11-28 · 30 estimated days · M7 Parent: AOS-P9-000 Dependencies: none Related tasks: AOS-P9-031;AOS-PLAT-036;AOS-PLAT-041

Outcome. Bound speaker/microphone, buttons/haptics, sensors and basic power-state integrations without asserting modem/camera readiness.

Scope. Produce and integrate: subsystem specs/backends or blockers; audio/privacy/power tests; board-package updates; cost/rights report. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep every Android/Linux artifact inside the Pixel adapter, stock-oracle, trace, or recovery boundary; do not alter portable Agent OS contracts to match a vendor ABI.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Each subsystem has separate evidence and no combined “phone works” claim is made from partial device I/O
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: subsystem specs/backends or blockers; audio/privacy/power tests; board-package updates; cost/rights report Verification: controlled output/input/button/sensor/power transitions, failure and privacy tests where feasible Evidence: subsystem matrix; traces; source/rights review; residual risk Traceability: specs: AOS-HW-002#phase-three-essential-io;AOS-ARCH-006#device-lifecycle; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-P9-050 — Evaluate Pixel GPU, display acceleration, power, and thermal feasibility

Type / priority / status: Experiment · P0 · Backlog Owner / workstream: Pixel GPU/Power Lead · Native Feasibility Schedule: 2027-07-26 → 2028-01-09 · 40 estimated days · M7 Parent: AOS-P9-000 Dependencies: AOS-PLAT-041;AOS-LEGAL-007 Related tasks: AOS-P9-040;AOS-PLAT-038

Outcome. Determine whether a bounded lawful native GPU/display acceleration and safe power/thermal route exists at acceptable effort.

Scope. Produce and integrate: GPU/display/power functional dossiers; minimal native experiments where allowed; command/firmware/power dependencies; performance/safety/cost forecast. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep every Android/Linux artifact inside the Pixel adapter, stock-oracle, trace, or recovery boundary; do not alter portable Agent OS contracts to match a vendor ABI.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Panfrost/Mesa knowledge is treated only as prior art
  • continue requires SoC display, firmware, IOMMU, power and security route—not GPU brand similarity
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: GPU/display/power functional dossiers; minimal native experiments where allowed; command/firmware/power dependencies; performance/safety/cost forecast Verification: EXP-034 first accelerated workload or bounded blocker, power/thermal transitions and interface/provenance review Evidence: protocol/source dossier; traces; power/thermal metrics; EXP-034 record Traceability: specs: AOS-HW-002#gpu-and-display;AOS-HW-002#power-and-thermal; sources: SRC-041;SRC-042; claims: CLM-007; experiments: EXP-034 Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-P9-051 — Evaluate native Pixel camera feasibility and quality gap

Type / priority / status: Spike · P1 · Backlog Owner / workstream: Pixel Camera Lead · Native Feasibility Schedule: 2027-08-09 → 2028-01-23 · 35 estimated days · M7 Parent: AOS-P9-000 Dependencies: AOS-P9-020;AOS-CAM-010;AOS-LEGAL-007 Related tasks: AOS-P9-031;AOS-CAM-041

Outcome. Map sensors, CSI, ISP, lens/OIS, metadata, calibration, firmware, tuning, power and legal rights to determine a native or controlled-adapter route.

Scope. Produce and integrate: camera subsystem/source/rights/calibration/tuning map; native capture spike if lawful; quality/resource gap; partner/stop recommendation. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep every Android/Linux artifact inside the Pixel adapter, stock-oracle, trace, or recovery boundary; do not alter portable Agent OS contracts to match a vendor ABI.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • No published paper, Linux driver or stock quality is treated as transferable production stack
  • every missing element is itemized
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: camera subsystem/source/rights/calibration/tuning map; native capture spike if lawful; quality/resource gap; partner/stop recommendation Verification: compare accessible native evidence to stock oracle and portable camera API; legal/security/camera review Evidence: camera feasibility dossier; sample captures if any; rights/cost gap; decision input Traceability: specs: AOS-HW-002#camera-feasibility;AOS-HW-006#controlled-proprietary-option; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-P9-052 — Evaluate Pixel modem, radio, secure element, and verified-boot boundaries

Type / priority / status: Spike · P2 · Backlog Owner / workstream: Pixel Security/Radio Lead · Native Feasibility Schedule: 2027-08-23 → 2028-01-23 · 30 estimated days · M7 Parent: AOS-P9-000 Dependencies: AOS-CELL-001;AOS-SEC-030;AOS-LEGAL-007;AOS-LEGAL-010 Related tasks: AOS-P9-031

Outcome. Identify lawful native control, firmware, provisioning, key, attestation, cellular and certification dependencies without attempting unsafe or unsupported claims.

Scope. Produce and integrate: boundary/source/rights map; secure boot/key/attestation possibilities; modem/IMS/eSIM/certification blockers; safe experiment plan; recommendation. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep every Android/Linux artifact inside the Pixel adapter, stock-oracle, trace, or recovery boundary; do not alter portable Agent OS contracts to match a vendor ABI.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Result does not claim Titan/Android verified boot, carrier voice, eSIM or emergency support “as-is” and states root-of-trust ownership
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: boundary/source/rights map; secure boot/key/attestation possibilities; modem/IMS/eSIM/certification blockers; safe experiment plan; recommendation Verification: official/public-source and approved black-box review with security/cellular/legal specialists Evidence: boundary dossier; prohibited/unknown list; partner requirements; risk update Traceability: specs: AOS-HW-002#radio-and-security;AOS-ARCH-013#root-of-trust; sources: none; claims: none; experiments: none Phase / volume: Phase 5 · Volume 03 Specialist review: none

AOS-P9-060 — Audit Pixel track source, license, security, and publication readiness

Type / priority / status: Review · P0 · Backlog Owner / workstream: Legal/Security/Architecture Review Team · Gate Review Schedule: 2027-12-13 → 2028-02-06 · 12 estimated days · M7 Parent: AOS-P9-000 Dependencies: AOS-P9-021;AOS-P9-030;AOS-P9-040 Related tasks: AOS-P9-015;AOS-P9-050;AOS-P9-051;AOS-P9-052

Outcome. Review every Pixel artifact, specification, trace, adapter, code contribution, dependency and public claim before gate decision or release.

Scope. Produce and integrate: artifact/provenance/license audit; clean-room attestations; dependency scan; public redaction; security/claim review; remediation list. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep every Android/Linux artifact inside the Pixel adapter, stock-oracle, trace, or recovery boundary; do not alter portable Agent OS contracts to match a vendor ABI.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • No unknown/red artifact, protected data, unapproved firmware, undocumented Android/Linux dependency or overstated claim enters public release
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: artifact/provenance/license audit; clean-room attestations; dependency scan; public redaction; security/claim review; remediation list Verification: independent sample/rebuild/scan and counsel sign-off on releasable scope Evidence: audit report; quarantined/remediated list; release boundary; approval record Traceability: specs: AOS-LEGAL-002#artifact-controls;AOS-LEGAL-003#release-gate;AOS-ARCH-011#pixel-legacy-boundary; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-P9-070 — Issue Pixel 9 continue, limit, or stop gate decision

Type / priority / status: Decision · P0 · Backlog Owner / workstream: Program Lead / Architecture Council · Gate Review Schedule: 2028-01-24 → 2028-02-13 · 6 estimated days · M7 Parent: AOS-P9-000 Dependencies: AOS-P9-050;AOS-P9-051;AOS-P9-052;AOS-OPEN-030 Related tasks: AOS-P9-060

Outcome. Decide whether native Pixel work continues, remains a quality/sidecar target, or stops based on evidence, legal rights, effort, opportunity cost and portable architecture impact.

Scope. Produce and integrate: G7 packet; subsystem outcomes; total-cost forecast; selected role; adapter retirement/maintenance; public wording; budget decision. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep every Android/Linux artifact inside the Pixel adapter, stock-oracle, trace, or recovery boundary; do not alter portable Agent OS contracts to match a vendor ABI.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Decision is allowed to stop
  • continuation requires a bounded route for essential I/O, safe power and unique value exceeding opportunity cost
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: G7 packet; subsystem outcomes; total-cost forecast; selected role; adapter retirement/maintenance; public wording; budget decision Verification: cross-functional review with comparison to documented/open/custom alternatives Evidence: signed gate decision; scorecard/risk/task updates; stop/continue rationale Traceability: specs: AOS-PLAN-006#pixel-stop-criteria;AOS-HW-002#decision-gate; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-P9-080 — Retire or constrain temporary Pixel adapters after gate

Type / priority / status: Task · P1 · Backlog Owner / workstream: Pixel Adapter Architect · Retirement Schedule: 2028-02-07 → 2028-06-25 · 20 estimated days · M9 Parent: AOS-P9-000 Dependencies: AOS-P9-015 Related tasks: AOS-P9-070

Outcome. Remove, freeze, or explicitly maintain each stock/sidecar/trace dependency according to G7 and native replacement evidence.

Scope. Produce and integrate: adapter disposition list; native replacements; frozen compatibility versions; user labels; deletion/quarantine of unnecessary artifacts; support tests. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Keep every Android/Linux artifact inside the Pixel adapter, stock-oracle, trace, or recovery boundary; do not alter portable Agent OS contracts to match a vendor ABI.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • No temporary adapter survives without an approved maintained purpose, owner, version/security policy and visible product distinction
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: adapter disposition list; native replacements; frozen compatibility versions; user labels; deletion/quarantine of unnecessary artifacts; support tests Verification: portable build/test without retired adapters and declared maintenance tests for retained ones Evidence: dependency delta; retirement report; support matrix; artifact disposition Traceability: specs: AOS-ARCH-011#retirement-requirement;AOS-ADR-0004#consequences; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: none

AOS-P9-090 — Establish Pixel 9 stock baseline, SKU, unlock, and recovery evidence

Type / priority / status: Experiment · P0 · Planned Owner / workstream: Pixel Track Lead · Acquisition and Recovery Schedule: 2026-08-03 → 2026-09-13 · 15 estimated days · M1 Parent: AOS-P9-000 Dependencies: none Related tasks: none

Outcome. Establish Pixel 9 stock baseline, SKU, unlock, and recovery evidence.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-HW-014#entry-gates, AOS-HW-014#experiments. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Establish Pixel 9 stock baseline, SKU, unlock, and recovery evidence; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-HW-014#role;AOS-HW-014#experiments; sources: SRC-020;SRC-081; claims: CLM-005; experiments: EXP-030 Phase / volume: Phase 1 · Volume 03 Specialist review: legal;hardware

AOS-P9-091 — Produce Pixel 9 boot-chain and early-diagnostics dossier

Type / priority / status: Experiment · P0 · Planned Owner / workstream: Pixel Boot Engineer · Boot Feasibility Schedule: 2027-02-22 → 2027-05-16 · 30 estimated days · M7 Parent: AOS-P9-000 Dependencies: none Related tasks: none

Outcome. Produce Pixel 9 boot-chain and early-diagnostics dossier.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-HW-014#experiments, AOS-ARCH-017#pixel-gates. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Produce Pixel 9 boot-chain and early-diagnostics dossier; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-HW-014#experiments;AOS-ARCH-017#pixel; sources: none; claims: CLM-006; experiments: EXP-032 Phase / volume: Phase 7 · Volume 03 Specialist review: reverse-engineering-legal;kernel

AOS-P9-092 — Test Pixel 9 USB, storage, display, and touch feasibility

Type / priority / status: Experiment · P0 · Planned Owner / workstream: Pixel Platform Engineer · Essential Hardware Schedule: 2027-05-17 → 2027-09-05 · 40 estimated days · M7 Parent: AOS-P9-000 Dependencies: none Related tasks: none

Outcome. Test Pixel 9 USB, storage, display, and touch feasibility.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-HW-014#experiments, AOS-HW-014#stop. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Test Pixel 9 USB, storage, display, and touch feasibility; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-HW-014#experiments;AOS-HW-014#stop; sources: none; claims: CLM-006; experiments: EXP-033 Phase / volume: Phase 7 · Volume 03 Specialist review: hardware

AOS-P9-093 — Test Pixel 9 GPU, IOMMU, firmware, and power feasibility

Type / priority / status: Experiment · P0 · Planned Owner / workstream: GPU and Power Engineers · GPU and Power Schedule: 2027-07-12 → 2027-11-14 · 45 estimated days · M7 Parent: AOS-P9-000 Dependencies: none Related tasks: none

Outcome. Test Pixel 9 GPU, IOMMU, firmware, and power feasibility.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-HW-014#gpu, AOS-HW-014#power. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Test Pixel 9 GPU, IOMMU, firmware, and power feasibility; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-HW-014#experiments;AOS-HW-014#experiments; sources: none; claims: CLM-007; experiments: EXP-034 Phase / volume: Phase 7 · Volume 03 Specialist review: gpu;legal

AOS-P9-094 — Test Pixel 9 camera control and quality replacement feasibility

Type / priority / status: Experiment · P0 · Planned Owner / workstream: Camera and Pixel Leads · Camera Feasibility Schedule: 2027-09-06 → 2028-01-09 · 45 estimated days · M7 Parent: AOS-P9-000 Dependencies: none Related tasks: none

Outcome. Test Pixel 9 camera control and quality replacement feasibility.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-HW-014#camera, AOS-HW-012#pixel-oracle. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Test Pixel 9 camera control and quality replacement feasibility; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-HW-014#experiments;AOS-HW-012#tracks; sources: none; claims: CLM-013; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: camera;legal

AOS-P9-095 — Test Pixel 9 modem isolation and native service boundary feasibility

Type / priority / status: Experiment · P1 · Planned Owner / workstream: Cellular and Pixel Leads · Cellular Feasibility Schedule: 2027-10-18 → 2028-02-20 · 45 estimated days · M7 Parent: AOS-P9-000 Dependencies: none Related tasks: none

Outcome. Test Pixel 9 modem isolation and native service boundary feasibility.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-HW-014#modem, AOS-HW-007#separate-capability-gates. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Test Pixel 9 modem isolation and native service boundary feasibility; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-HW-014#experiments;AOS-HW-007#separate-capability-gates; sources: none; claims: CLM-008;CLM-009; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: cellular;legal

AOS-P9-096 — Issue the Pixel 9 continue, limit, partner, or stop decision

Type / priority / status: Decision · P0 · Planned Owner / workstream: Architecture Council · Track Gate Schedule: 2028-01-10 → 2028-02-06 · 10 estimated days · M7 Parent: AOS-P9-000 Dependencies: none Related tasks: AOS-P9-091;AOS-P9-092;AOS-P9-093;AOS-P9-094;AOS-P9-095

Outcome. Issue the Pixel 9 continue, limit, partner, or stop decision.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-HW-014#decision, AOS-PLAN-012#convergence-gates. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Issue the Pixel 9 continue, limit, partner, or stop decision; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-HW-014#stop;AOS-PLAN-012#convergence; sources: none; claims: none; experiments: none Phase / volume: Phase 7 · Volume 03 Specialist review: architecture;legal;hardware

AOS-PLAT

AOS-PLAT-000 — Portable Platform epic

Type / priority / status: Epic · P1 · Backlog Owner / workstream: Platform Lead · Program Schedule: 2026-07-27 → 2029-01-07 · 3 estimated days · Continuous Parent: none Dependencies: none Related tasks: none

Outcome. Deliver IDL, board packages, user-space drivers, services, SDK, and conformance.

Scope. Produce and integrate: project charter; milestone map; owned backlog; status/evidence dashboard. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Project has one accountable lead, an approved scope, milestone links, and no orphaned P0/P1 work
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: project charter; milestone map; owned backlog; status/evidence dashboard Verification: monthly project review and gate reconciliation Evidence: project update; dependency report; risk and budget delta Traceability: specs: AOS-ARCH-001#portability-boundaries; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-PLAT-001 — Catalog native platform contracts

Type / priority / status: Task · P0 · Backlog Owner / workstream: Platform Architect · Architecture Schedule: 2026-07-27 → 2026-08-30 · 10 estimated days · M1 Parent: AOS-PLAT-000 Dependencies: none Related tasks: AOS-CORE-001;AOS-DOCS-012

Outcome. Define the minimal typed service families needed by kernel, system services, product runtime, hardware backends, diagnostics, update, and testing.

Scope. Produce and integrate: service catalog; ownership/dependency graph; authority/data/lifecycle fields; target variance model. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Every service has an owner, capability boundary, failure/lifecycle model, versioning plan, and at least one emulated backend
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: service catalog; ownership/dependency graph; authority/data/lifecycle fields; target variance model Verification: architecture/security/product/hardware review and Linux/Android type scan Evidence: approved catalog; dependency graph; rejected leakage list Traceability: specs: AOS-ARCH-001#native-contract;AOS-ARCH-007#service-catalog; sources: none; claims: none; experiments: none Phase / volume: Phase 2 · Volume 02 Specialist review: none

AOS-PLAT-002 — Specify Agent OS IDL syntax and semantic model

Type / priority / status: Task · P0 · Backlog Owner / workstream: IDL Architect · IDL Schedule: 2026-09-07 → 2026-10-18 · 12 estimated days · M2 Parent: AOS-PLAT-000 Dependencies: AOS-PLAT-001 Related tasks: AOS-CORE-031

Outcome. Define types, methods, events, errors, handles, ownership, optionality, evolution, resource limits, and documentation needed for native service interfaces.

Scope. Produce and integrate: IDL grammar; semantic rules; wire ownership model; examples; invalid corpus. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • IDL can express capability-bearing asynchronous services without POSIX/vendor types and rejects ambiguous ownership/evolution
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: IDL grammar; semantic rules; wire ownership model; examples; invalid corpus Verification: parser/typechecker prototype and review against storage/display/camera/cellular/action interfaces Evidence: language spec; conformance examples; review findings Traceability: specs: AOS-ARCH-005#idl-semantics;AOS-ARCH-005#service-contract-rules; sources: none; claims: none; experiments: none Phase / volume: Phase 2 · Volume 02 Specialist review: none

AOS-PLAT-003 — Implement IDL compiler and Rust bindings v0

Type / priority / status: Task · P0 · Backlog Owner / workstream: IDL Tooling Engineer · IDL Schedule: 2026-10-05 → 2026-12-13 · 20 estimated days · M2 Parent: AOS-PLAT-000 Dependencies: none Related tasks: AOS-PLAT-002;AOS-CORE-031

Outcome. Generate deterministic client/server bindings, codecs, validation, capability transfer and test fixtures from Agent OS IDL.

Scope. Produce and integrate: parser/typechecker; code generator; Rust runtime; golden files; fuzz hooks; docs. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Generated endpoints validate bounds/handles before dispatch, preserve unknown compatible fields, and produce deterministic source
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: parser/typechecker; code generator; Rust runtime; golden files; fuzz hooks; docs Verification: round-trip/golden/invalid/fuzz tests and two independently implemented endpoints Evidence: binding conformance report; generated diff stability; fuzz results Traceability: specs: AOS-ARCH-005#bindings;AOS-ARCH-005#wire-format; sources: none; claims: none; experiments: none Phase / volume: Phase 2 · Volume 02 Specialist review: none

AOS-PLAT-004 — Define API-level and schema evolution tooling

Type / priority / status: Task · P1 · Backlog Owner / workstream: API Governance Engineer · API Governance Schedule: 2026-10-19 → 2026-12-06 · 10 estimated days · M2 Parent: AOS-PLAT-000 Dependencies: AOS-PLAT-002;AOS-DOCS-007 Related tasks: none

Outcome. Track interface levels, compatibility ranges, deprecation, migration, unknown fields, feature discovery, and target support.

Scope. Produce and integrate: API manifest format; compatibility checker; change classifier; deprecation/migration templates; CI rule. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • A breaking wire/semantic change fails CI unless it declares a new level and migration/rollback impact
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: API manifest format; compatibility checker; change classifier; deprecation/migration templates; CI rule Verification: seed breaking/compatible changes and multi-level client/server matrices Evidence: compatibility report; fixture outcomes; policy review Traceability: specs: AOS-ARCH-005#versioning-policy;AOS-GOV-001#api-levels; sources: none; claims: none; experiments: none Phase / volume: Phase 2 · Volume 02 Specialist review: none

AOS-PLAT-010 — Implement user-space service manager

Type / priority / status: Task · P0 · Backlog Owner / workstream: Platform Runtime Engineer · Runtime Schedule: 2026-11-02 → 2027-01-10 · 20 estimated days · M2 Parent: AOS-PLAT-000 Dependencies: AOS-CORE-018 Related tasks: AOS-CORE-031;AOS-CORE-034;AOS-PLAT-003

Outcome. Start, stop, restart, monitor, route capabilities to, and update isolated services from a declarative manifest.

Scope. Produce and integrate: service manifest; launcher; capability router; health/restart policy; dependency graph; tests. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • No service receives undeclared authority, failures remain isolated, and crash loops are bounded with diagnosable state
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: service manifest; launcher; capability router; health/restart policy; dependency graph; tests Verification: start order, denied route, crash loop, dependency failure, update and resource-exhaustion scenarios Evidence: service lifecycle traces; capability route audit; restart report Traceability: specs: AOS-ARCH-007#service-manager;AOS-ARCH-007#service-lifecycle; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-PLAT-011 — Implement structured logging and diagnostics service

Type / priority / status: Task · P0 · Backlog Owner / workstream: Observability Engineer · Observability Schedule: 2026-11-16 → 2027-01-03 · 12 estimated days · M2 Parent: AOS-PLAT-000 Dependencies: AOS-CORE-038 Related tasks: AOS-PLAT-010

Outcome. Collect bounded structured logs, metrics, traces, crash references, target identity, and privacy classes through explicit capabilities.

Scope. Produce and integrate: log/metric/trace IDL; collectors; ring buffers; query/export; redaction/rate limits. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Diagnostics are bounded by producer and class, cannot grant authority, and preserve build/target/provenance required for experiments
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: log/metric/trace IDL; collectors; ring buffers; query/export; redaction/rate limits Verification: overload, malicious logger, secure-field taint, crash/reboot persistence and export tests Evidence: overhead/retention report; redaction test; sample evidence bundle Traceability: specs: AOS-ARCH-015#observability;AOS-ARCH-012#diagnostic-data; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-PLAT-012 — Demonstrate a native API application slice without POSIX

Type / priority / status: Experiment · P0 · Backlog Owner / workstream: Platform Lead · Vertical Slice Schedule: 2026-12-14 → 2027-01-24 · 12 estimated days · M2 Parent: AOS-PLAT-000 Dependencies: AOS-PLAT-003 Related tasks: AOS-PLAT-010;AOS-PLAT-011;AOS-CORE-032

Outcome. Run a small user-space shell, storage object, timer, logging, and message workflow using only Agent OS syscalls/IDL/capabilities.

Scope. Produce and integrate: native demo components; forbidden-dependency lint; conformance scenario; developer walkthrough. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • The slice builds and runs with no POSIX, Binder, Android HAL, Linux ABI, libc, or target-vendor type above declared adapters
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: native demo components; forbidden-dependency lint; conformance scenario; developer walkthrough Verification: EXP-011 source/binary dependency scan and end-to-end failure tests Evidence: demo trace; scan report; EXP-011 record Traceability: specs: AOS-ARCH-001#native-contract;AOS-ARCH-011#compatibility-policy; sources: none; claims: CLM-003;CLM-004; experiments: EXP-011 Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-PLAT-013 — Implement time, entropy, and identity foundation services

Type / priority / status: Task · P1 · Backlog Owner / workstream: Platform Security Engineer · Foundation Services Schedule: 2026-12-28 → 2027-02-28 · 15 estimated days · M3 Parent: AOS-PLAT-000 Dependencies: AOS-CORE-021 Related tasks: AOS-PLAT-010;AOS-SEC-021

Outcome. Expose wall-time synchronization, monotonic mapping, entropy, device/user/service identity references, and trust quality through separate services.

Scope. Produce and integrate: time service; entropy broker; identity directory; quality/status APIs; test backends. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Consumers can distinguish monotonic/wall/uncertain time and never receive silent weak entropy or ambient identity authority
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: time service; entropy broker; identity directory; quality/status APIs; test backends Verification: clock jumps, no-network, entropy failure, identity rotation/revocation and authorization tests Evidence: foundation conformance; failure matrix; entropy review Traceability: specs: AOS-ARCH-007#foundation-services;AOS-ARCH-012#identity-and-entropy; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-PLAT-014 — Specify package, component, and integration manifest

Type / priority / status: Task · P1 · Backlog Owner / workstream: Package System Architect · Packages Schedule: 2026-12-14 → 2027-02-07 · 12 estimated days · M3 Parent: AOS-PLAT-000 Dependencies: AOS-PLAT-004 Related tasks: AOS-PLAT-010;AOS-LEGAL-012

Outcome. Describe executable components, dependencies, capabilities, data domains, resources, updates, migrations, SBOM, signatures and target compatibility.

Scope. Produce and integrate: manifest schema; signature/provenance fields; resource/capability declarations; migration/rollback hooks; examples. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Package install cannot imply undeclared authority and all executable/artifact dependencies are versioned and attributable
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: manifest schema; signature/provenance fields; resource/capability declarations; migration/rollback hooks; examples Verification: validate first-party service, product integration, driver and malicious/invalid packages Evidence: schema conformance; security/legal review; invalid fixture results Traceability: specs: AOS-ARCH-007#package-model;AOS-PROD-003#integration-package; sources: none; claims: none; experiments: none Phase / volume: Phase 2 · Volume 02 Specialist review: none

AOS-PLAT-015 — Implement initial system image and bootstrap service graph

Type / priority / status: Task · P0 · Backlog Owner / workstream: Release/Platform Engineer · Boot Image Schedule: 2027-01-25 → 2027-04-04 · 18 estimated days · M3 Parent: AOS-PLAT-000 Dependencies: AOS-PLAT-010 Related tasks: AOS-PLAT-013;AOS-PLAT-014;AOS-SEC-030

Outcome. Assemble kernel, initial process, service manager, essential services, target board package, trust material, and recovery metadata reproducibly.

Scope. Produce and integrate: image assembly tool; signed manifest; service graph; target overlays; reproducibility metadata; emulator images. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • A target image names every component, capability route, version and trust input, and fails closed on integrity/dependency mismatch
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: image assembly tool; signed manifest; service graph; target overlays; reproducibility metadata; emulator images Verification: clean assembly, tamper/missing component, recovery fallback and version compatibility tests Evidence: image manifest/SBOM; boot traces; failure results Traceability: specs: AOS-ARCH-013#initial-system-image;AOS-ARCH-015#release-evidence; sources: none; claims: none; experiments: none Phase / volume: Phase 5 · Volume 02 Specialist review: none

AOS-PLAT-020 — Specify board package and hardware resource contract

Type / priority / status: Task · P0 · Backlog Owner / workstream: Hardware Platform Architect · Board Packages Schedule: 2026-11-16 → 2027-01-17 · 15 estimated days · M3 Parent: AOS-PLAT-000 Dependencies: AOS-PLAT-001;AOS-CORE-012 Related tasks: AOS-CORE-037

Outcome. Normalize firmware/board facts into versioned CPU, memory, MMIO, IRQ, clock, reset, power, pin, bus, DMA and device descriptors.

Scope. Produce and integrate: board manifest schema; resource capabilities; discovery/overlay rules; QEMU/AM625 examples; validation. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Kernel and product code do not parse target-native device descriptions, and resources can be delegated only through explicit capabilities
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: board manifest schema; resource capabilities; discovery/overlay rules; QEMU/AM625 examples; validation Verification: represent two unrelated targets and reject conflicting/overlapping resources Evidence: schema review; target diff; invalid manifest tests Traceability: specs: AOS-ARCH-006#board-package;AOS-HW-004#porting-sequence; sources: none; claims: none; experiments: none Phase / volume: Phase 2 · Volume 02 Specialist review: none

AOS-PLAT-021 — Implement hardware resource broker

Type / priority / status: Task · P0 · Backlog Owner / workstream: Driver Framework Engineer · Driver Framework Schedule: 2026-12-28 → 2027-03-07 · 18 estimated days · M3 Parent: AOS-PLAT-000 Dependencies: none Related tasks: AOS-PLAT-020;AOS-PLAT-010;AOS-CORE-037

Outcome. Grant scoped MMIO, interrupt, DMA, clock/reset/power and bus resources to isolated driver domains from board packages.

Scope. Produce and integrate: resource broker service; capability types; conflict checks; lifecycle/revocation; audit records. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • A driver receives only declared resources, conflicting grants fail, and driver death revokes DMA/interrupt access before reuse
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: resource broker service; capability types; conflict checks; lifecycle/revocation; audit records Verification: overlap/forgery/driver-death/reset/DMA teardown tests on QEMU and first board Evidence: resource route audit; isolation tests; leak report Traceability: specs: AOS-ARCH-006#resource-broker;AOS-ARCH-004#resource-capabilities; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-PLAT-022 — Implement bus discovery and device binding framework

Type / priority / status: Task · P1 · Backlog Owner / workstream: Driver Framework Engineer · Driver Framework Schedule: 2027-01-25 → 2027-04-04 · 18 estimated days · M3 Parent: AOS-PLAT-000 Dependencies: AOS-PLAT-020 Related tasks: AOS-PLAT-021

Outcome. Discover/bind platform, PCI, USB and simple serial-bus devices without embedding one OS device model in native contracts.

Scope. Produce and integrate: device descriptors; match/bind rules; bus managers; hotplug events; driver manifest integration. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Binding is deterministic/auditable, target identifiers stay in board/driver packages, and no driver gains undeclared sibling resources
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: device descriptors; match/bind rules; bus managers; hotplug events; driver manifest integration Verification: multiple/missing/ambiguous driver, hotplug, device reset and malicious descriptor tests Evidence: binding traces; conformance matrix; failure report Traceability: specs: AOS-ARCH-006#device-discovery;AOS-ARCH-006#driver-binding; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-PLAT-023 — Implement interrupt and DMA broker integration

Type / priority / status: Task · P0 · Backlog Owner / workstream: Driver Framework Engineer · Driver Framework Schedule: 2027-02-08 → 2027-04-11 · 16 estimated days · M3 Parent: AOS-PLAT-000 Dependencies: AOS-CORE-033 Related tasks: AOS-PLAT-021;AOS-CORE-037

Outcome. Connect user-space driver event loops to kernel interrupt/DMA primitives with safe buffer ownership and backpressure.

Scope. Produce and integrate: interrupt endpoint; DMA buffer/queue APIs; cache sync; cancellation/reset; performance counters. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Buffer ownership transitions are explicit, stale DMA is impossible after revoke under supported IOMMU, and overload is bounded
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: interrupt endpoint; DMA buffer/queue APIs; cache sync; cancellation/reset; performance counters Verification: device-emulator workloads, driver crash/restart, queue overflow, stale buffer and teardown tests Evidence: DMA/interrupt traces; performance baseline; isolation result Traceability: specs: AOS-ARCH-006#dma-and-iommu;AOS-ARCH-006#interrupt-contract; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-PLAT-024 — Specify device lifecycle, reset, suspend, and hotplug state machine

Type / priority / status: Task · P0 · Backlog Owner / workstream: Platform Architect · Driver Framework Schedule: 2027-02-08 → 2027-03-28 · 10 estimated days · M3 Parent: AOS-PLAT-000 Dependencies: none Related tasks: AOS-PLAT-022;AOS-PLAT-023

Outcome. Give all hardware services consistent discovery, initialization, readiness, degradation, reset, suspend, resume, removal, and failure semantics.

Scope. Produce and integrate: state machine; IDL base types; timeout/error rules; dependency ordering; conformance tests. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Every hardware backend reports state/failure consistently and no suspended/removed device retains active buffers or waits indefinitely
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: state machine; IDL base types; timeout/error rules; dependency ordering; conformance tests Verification: model-check lifecycle sequences and run reset/suspend/removal fault injection Evidence: state model; transition coverage; unresolved device classes Traceability: specs: AOS-ARCH-006#device-lifecycle;AOS-ARCH-014#suspend-resume; sources: none; claims: none; experiments: none Phase / volume: Phase 2 · Volume 02 Specialist review: none

AOS-PLAT-030 — Demonstrate driver-domain crash and restart recovery

Type / priority / status: Experiment · P0 · Backlog Owner / workstream: Driver Framework Engineer · Reliability Schedule: 2027-03-08 → 2027-04-18 · 10 estimated days · M3 Parent: AOS-PLAT-000 Dependencies: AOS-PLAT-021;AOS-PLAT-010 Related tasks: AOS-PLAT-024

Outcome. Restart an isolated device driver and rebind clients without restarting kernel or corrupting canonical state.

Scope. Produce and integrate: fault injection; restart/rebind manager; client error/retry policy; state reconciliation demo. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Kernel and unrelated services remain live, device authority is revoked/recreated, and clients receive bounded errors or successful rebind
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: fault injection; restart/rebind manager; client error/retry policy; state reconciliation demo Verification: EXP-006 for crash during idle, I/O, DMA and suspend transitions Evidence: restart traces; client consistency report; EXP-006 record Traceability: specs: AOS-ARCH-006#driver-domains;AOS-ARCH-007#service-lifecycle; sources: SRC-009;SRC-012; claims: none; experiments: EXP-006 Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-PLAT-031 — Implement block-storage service and backend contract

Type / priority / status: Task · P0 · Backlog Owner / workstream: Storage Engineer · Storage Schedule: 2027-03-08 → 2027-05-16 · 18 estimated days · M3 Parent: AOS-PLAT-000 Dependencies: none Related tasks: AOS-PLAT-023;AOS-PLAT-024

Outcome. Expose asynchronous block devices, queues, flush/discard, integrity/error, hot removal, encryption hooks and diagnostics through native services.

Scope. Produce and integrate: block IDL; RAM/virtio backend; partition service; queue/backpressure; fault injector. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Clients can reason about completion/durability/error and cannot access blocks outside granted ranges
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: block IDL; RAM/virtio backend; partition service; queue/backpressure; fault injector Verification: ordering/flush/power-loss simulation, malformed request, removal and throughput tests Evidence: storage conformance; durability experiments; performance baseline Traceability: specs: AOS-ARCH-007#storage-services;AOS-ARCH-006#storage-contract; sources: none; claims: none; experiments: none Phase / volume: Phase 2 · Volume 02 Specialist review: none

AOS-PLAT-032 — Implement durable object/filesystem service v0

Type / priority / status: Task · P0 · Backlog Owner / workstream: Storage Engineer · Storage Schedule: 2027-04-05 → 2027-07-25 · 30 estimated days · M4 Parent: AOS-PLAT-000 Dependencies: AOS-PLAT-013 Related tasks: AOS-PLAT-031

Outcome. Provide transactional namespaces, objects/files, metadata, quotas, snapshots, integrity checks and recovery for system/product storage.

Scope. Produce and integrate: storage engine; namespace/capability API; journal/snapshots; fsck/recovery; quota/encryption integration. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Committed transactions survive declared failures, corrupt data is detected, recovery is bounded, and namespaces cannot escape grants
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: storage engine; namespace/capability API; journal/snapshots; fsck/recovery; quota/encryption integration Verification: crash/power-cut model, corruption, rollback, quota, concurrent transactions and migration tests Evidence: durability report; recovery corpus; performance/storage overhead Traceability: specs: AOS-ARCH-009#storage-engine;AOS-ARCH-007#storage-services; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-PLAT-033 — Implement native network service v0

Type / priority / status: Task · P1 · Backlog Owner / workstream: Network Engineer · Networking Schedule: 2027-04-05 → 2027-08-08 · 30 estimated days · M4 Parent: AOS-PLAT-000 Dependencies: AOS-PLAT-010;AOS-PLAT-013 Related tasks: AOS-PLAT-023

Outcome. Provide interface/link/IP/transport/DNS/connectivity contracts with per-component network capabilities, accounting, and test backends.

Scope. Produce and integrate: network IDL; virtio/Ethernet backend; IP/UDP/TCP baseline; DNS; policy/accounting; packet test lab. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Components receive scoped endpoints rather than ambient sockets, network loss/rebind is explicit, and parser exposure is fuzzed
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: network IDL; virtio/Ethernet backend; IP/UDP/TCP baseline; DNS; policy/accounting; packet test lab Verification: interoperability, malformed/hostile traffic, capability isolation, link loss, suspend and throughput/latency tests Evidence: network conformance; packet traces; security review; performance baseline Traceability: specs: AOS-ARCH-007#network-service;AOS-ARCH-012#network-policy; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-PLAT-034 — Implement USB host/device service baseline

Type / priority / status: Task · P1 · Backlog Owner / workstream: USB Engineer · USB Schedule: 2027-04-05 → 2027-07-11 · 24 estimated days · M4 Parent: AOS-PLAT-000 Dependencies: AOS-PLAT-022;AOS-PLAT-024 Related tasks: AOS-PLAT-023

Outcome. Enumerate USB, isolate class/function drivers, transfer buffers safely, handle hotplug/reset, and support debug/recovery needs.

Scope. Produce and integrate: USB controller backend; core service; descriptor parser; HID/storage/debug class paths; fuzz corpus. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Untrusted devices cannot escape assigned domains, descriptor lengths are bounded, and removal completes all transfers with defined errors
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: USB controller backend; core service; descriptor parser; HID/storage/debug class paths; fuzz corpus Verification: malformed descriptors, hotplug storms, reset, driver crash, DMA ownership and real devices on documented board Evidence: USB conformance; fuzz findings; device matrix Traceability: specs: AOS-ARCH-006#usb-contract;AOS-HW-004#usb-first; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-PLAT-035 — Implement input service and semantic event contract

Type / priority / status: Task · P1 · Backlog Owner / workstream: Input/Accessibility Engineer · Input Schedule: 2027-04-19 → 2027-06-27 · 16 estimated days · M4 Parent: AOS-PLAT-000 Dependencies: AOS-PLAT-013;AOS-PLAT-024 Related tasks: AOS-PLAT-034

Outcome. Normalize touch, pointer, keyboard, switch, stylus and sensors into secure timestamped input streams and semantic focus actions.

Scope. Produce and integrate: input IDL; HID/virtio backends; seat/focus routing; secure-input mode; replay fixtures. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Input is delivered only to authorized focus paths, secure mode excludes journals/observers, and replay is explicit/diagnostic-only
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: input IDL; HID/virtio backends; seat/focus routing; secure-input mode; replay fixtures Verification: multi-device, hotplug, timestamp/order, focus isolation, secure-field and accessibility tests Evidence: input conformance; secure-field taint results; latency metrics Traceability: specs: AOS-ARCH-008#input-service;AOS-PROD-005#input-modalities; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-PLAT-036 — Implement audio service and graph contract

Type / priority / status: Task · P1 · Backlog Owner / workstream: Audio Engineer · Audio Schedule: 2027-05-03 → 2027-08-08 · 24 estimated days · M4 Parent: AOS-PLAT-000 Dependencies: AOS-PLAT-023;AOS-PLAT-024;AOS-PLAT-013 Related tasks: none

Outcome. Route capture/playback streams, devices, volume/policy, timing, privacy indicators, low-latency paths and telephony endpoints through native services.

Scope. Produce and integrate: audio IDL; graph/mixer; USB/virtual backend; clock/latency model; capture privacy; loopback tests. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Capture requires explicit authority/indicator, timing is measurable, and backend changes do not alter product audio semantics
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: audio IDL; graph/mixer; USB/virtual backend; clock/latency model; capture privacy; loopback tests Verification: latency/drift/glitch, route changes, device removal, permission, suspend and crash tests Evidence: audio metrics; route matrix; privacy review; conformance logs Traceability: specs: AOS-ARCH-007#audio-service;AOS-HW-007#audio-routing; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-PLAT-037 — Implement display, buffer, and compositor backend contract

Type / priority / status: Task · P0 · Backlog Owner / workstream: Graphics Platform Engineer · Graphics Schedule: 2027-03-22 → 2027-07-11 · 28 estimated days · M3 Parent: AOS-PLAT-000 Dependencies: none Related tasks: AOS-PLAT-023;AOS-PLAT-024;AOS-CORE-037

Outcome. Provide displays, modes, surfaces, buffer collections, synchronization, presentation timing, capture policy and fallback through native services.

Scope. Produce and integrate: display/buffer IDL; software/virtio backend; compositor integration; synchronization/timing; capture permissions. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Client buffers cannot be reused before release, presentation outcomes are timestamped, and secure surfaces cannot be captured without grant
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: display/buffer IDL; software/virtio backend; compositor integration; synchronization/timing; capture permissions Verification: first-frame, mode change, buffer lifetime, missed deadline, driver restart, secure surface and load tests Evidence: first-frame artifact; frame timing; buffer lifecycle trace; conformance Traceability: specs: AOS-ARCH-008#display-contract;AOS-ARCH-008#scene-and-semantics; sources: none; claims: none; experiments: none Phase / volume: Phase 2 · Volume 02 Specialist review: none

AOS-PLAT-038 — Specify GPU acceleration and command-submission contract

Type / priority / status: Spike · P2 · Backlog Owner / workstream: GPU Architect · Graphics Schedule: 2027-05-17 → 2027-08-22 · 18 estimated days · M5 Parent: AOS-PLAT-000 Dependencies: AOS-CORE-037 Related tasks: AOS-PLAT-037

Outcome. Separate portable graphics APIs, GPU memory/context/queue services, compiler/runtime backends, and device-specific command streams.

Scope. Produce and integrate: GPU service contract; memory/context/isolation model; software reference; backend requirements; fault/reset policy. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • No vendor command stream enters product/compositor API and GPU reset/fault/memory isolation are explicit before hardware implementation
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: GPU service contract; memory/context/isolation model; software reference; backend requirements; fault/reset policy Verification: architecture/security review and two candidate backend mapping exercises Evidence: contract draft; gap analysis; threat/performance model Traceability: specs: AOS-ARCH-006#gpu-contract;AOS-ARCH-008#gpu-acceleration; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-PLAT-039 — Specify portable camera service contract

Type / priority / status: Task · P1 · Backlog Owner / workstream: Camera Architect · Camera Platform Schedule: 2027-02-22 → 2027-05-02 · 15 estimated days · M4 Parent: AOS-PLAT-000 Dependencies: AOS-PLAT-002 Related tasks: AOS-PLAT-024;AOS-PLAT-035

Outcome. Represent sensors, streams, controls, metadata, frames, calibration, 3A, processing stages, privacy, timing and power independent of one ISP.

Scope. Produce and integrate: camera IDL; stream/control/result model; buffer/timestamp ownership; privacy/lifecycle; conformance fixtures. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Capture metadata can reproduce exposure/lens/timing context and ISP/vendor-specific controls remain extensible but bounded
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: camera IDL; stream/control/result model; buffer/timestamp ownership; privacy/lifecycle; conformance fixtures Verification: map virtual, documented-board and hypothetical proprietary pipeline without API forks Evidence: mapping report; schema tests; security/camera review Traceability: specs: AOS-ARCH-006#camera-contract;AOS-HW-006#portable-camera-stack; sources: none; claims: none; experiments: none Phase / volume: Phase 2 · Volume 02 Specialist review: none

AOS-PLAT-040 — Specify portable cellular and telephony service contracts

Type / priority / status: Task · P1 · Backlog Owner / workstream: Cellular Architect · Cellular Platform Schedule: 2027-04-05 → 2027-06-27 · 18 estimated days · M5 Parent: AOS-PLAT-000 Dependencies: AOS-PLAT-002;AOS-PLAT-024 Related tasks: AOS-PLAT-033;AOS-PLAT-036

Outcome. Separate modem transport, registration, packet data, SMS, SIM/eSIM, GNSS, voice, IMS, emergency and policy into native capability services.

Scope. Produce and integrate: cellular/telephony IDL set; state machines; error/provisioning/security/power fields; fake backends. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Data support cannot imply voice/IMS, emergency state is explicit, and SIM/eSIM secrets stay behind scoped services
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: cellular/telephony IDL set; state machines; error/provisioning/security/power fields; fake backends Verification: map MBIM/QMI/module/data/SMS and unresolved IMS paths without claiming unsupported functions Evidence: contract review; state-model tests; gap register Traceability: specs: AOS-ARCH-006#cellular-contract;AOS-HW-007#separate-capability-gates; sources: none; claims: none; experiments: none Phase / volume: Phase 2 · Volume 02 Specialist review: none

AOS-PLAT-041 — Implement power, thermal, battery, charging, and suspend service contracts

Type / priority / status: Task · P0 · Backlog Owner / workstream: Power Platform Engineer · Power Schedule: 2027-03-22 → 2027-07-11 · 24 estimated days · M4 Parent: AOS-PLAT-000 Dependencies: AOS-PLAT-013;AOS-CORE-022 Related tasks: AOS-PLAT-024

Outcome. Coordinate device power states, wake sources, thermal zones, performance hints, battery/charger safety, energy budgets and suspend transactions.

Scope. Produce and integrate: power/thermal IDL; dependency graph; suspend coordinator; battery/charger model; telemetry; fake backend. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Unsafe or unknown battery/thermal states fail safe, suspend has bounded rollback, and consumers receive no direct board regulator access
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: power/thermal IDL; dependency graph; suspend coordinator; battery/charger model; telemetry; fake backend Verification: failed suspend participant, wake storm, thermal trip, charger removal, low battery and budget-enforcement tests Evidence: state traces; power/thermal safety review; energy accounting report Traceability: specs: AOS-ARCH-014#power-service;AOS-ARCH-014#suspend-resume;AOS-HW-003#power-path; sources: none; claims: none; experiments: none Phase / volume: Phase 2 · Volume 02 Specialist review: none

AOS-PLAT-050 — Implement package installation, verification, and component registry

Type / priority / status: Task · P1 · Backlog Owner / workstream: Package System Engineer · Packages Schedule: 2027-05-17 → 2027-08-29 · 24 estimated days · M4 Parent: AOS-PLAT-000 Dependencies: AOS-PLAT-014;AOS-SEC-060 Related tasks: AOS-PLAT-032

Outcome. Install signed packages transactionally, verify provenance/API/capabilities/resources, register components/integrations, and support rollback/uninstall.

Scope. Produce and integrate: package format; verifier; registry; transactional installer; rollback/uninstall; policy UI API. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • No executable package runs before integrity, compatibility and capability review
  • failed install leaves prior state bootable
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: package format; verifier; registry; transactional installer; rollback/uninstall; policy UI API Verification: tampered/signature/API/dependency/migration/power-loss/uninstall tests Evidence: package conformance; attack/failure results; provenance/SBOM sample Traceability: specs: AOS-ARCH-007#package-model;AOS-PROD-003#integration-package;AOS-LEGAL-003#release-gate; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-PLAT-051 — Implement transactional system update pipeline

Type / priority / status: Task · P0 · Backlog Owner / workstream: Update Engineer · Update Schedule: 2027-06-14 → 2027-10-17 · 30 estimated days · M8 Parent: AOS-PLAT-000 Dependencies: AOS-PLAT-015;AOS-SEC-030 Related tasks: AOS-PLAT-050;AOS-SEC-032

Outcome. Assemble, stage, verify, activate, monitor, roll back, and report kernel/platform/product updates across supported targets.

Scope. Produce and integrate: update manifest; downloader/stager; slot/snapshot activation; health check; rollback; status/receipt. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • An interrupted or unhealthy update preserves/reaches a bootable trusted state and anti-rollback policy is explicit
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: update manifest; downloader/stager; slot/snapshot activation; health check; rollback; status/receipt Verification: tamper, interruption at every phase, bad kernel/service/schema, rollback attack and recovery tests on QEMU/board Evidence: update fault matrix; signed manifests; rollback/recovery traces Traceability: specs: AOS-ARCH-013#update-model;AOS-ARCH-013#rollback; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-PLAT-052 — Implement recovery environment and service tools

Type / priority / status: Task · P0 · Backlog Owner / workstream: Recovery Engineer · Recovery Schedule: 2027-06-14 → 2027-10-03 · 24 estimated days · M8 Parent: AOS-PLAT-000 Dependencies: AOS-PLAT-015;AOS-PLAT-031 Related tasks: AOS-SEC-041

Outcome. Provide independent verified diagnostics, storage inspection, update repair, backup restore, key/revocation flow and target reflash without normal system services.

Scope. Produce and integrate: recovery image; console/UI; target transport; storage/update/backup tools; audit/export; destructive confirmations. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Recovery has an independent trust path, clearly distinguishes destructive actions, and does not expose protected data without authentication policy
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: recovery image; console/UI; target transport; storage/update/backup tools; audit/export; destructive confirmations Verification: unbootable system, corrupt metadata, failed update, lost credential and malicious recovery media scenarios Evidence: recovery drill reports; signed image manifest; threat review Traceability: specs: AOS-ARCH-013#recovery-environment;AOS-PROD-004#failure-and-rollback; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-PLAT-060 — Build unified observability and evidence export pipeline

Type / priority / status: Task · P1 · Backlog Owner / workstream: Observability Engineer · Observability Schedule: 2027-03-08 → 2027-06-13 · 20 estimated days · M4 Parent: AOS-PLAT-000 Dependencies: AOS-PLAT-011;AOS-PLAT-013 Related tasks: AOS-PLAT-041

Outcome. Join logs, traces, metrics, power, frame, storage, network, crash and experiment metadata into reproducible bounded evidence bundles.

Scope. Produce and integrate: trace schema; correlation IDs; capture profiles; export/redaction; analysis notebooks/scripts; dashboard. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • A gate experiment can identify exact build/target/time/configuration and correlate events without collecting unapproved content
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: trace schema; correlation IDs; capture profiles; export/redaction; analysis notebooks/scripts; dashboard Verification: cross-layer incident reproduction, clock-correlation, rate/size limits, redaction and offline export Evidence: sample integrated evidence bundle; overhead analysis; privacy approval Traceability: specs: AOS-ARCH-015#observability;AOS-RES-004#evidence-integrity; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-PLAT-070 — Implement emulator hardware-service backends and fault injection

Type / priority / status: Task · P0 · Backlog Owner / workstream: Simulation Engineer · Simulation Schedule: 2026-12-14 → 2027-04-18 · 25 estimated days · M4 Parent: AOS-PLAT-000 Dependencies: AOS-PLAT-003 Related tasks: AOS-PLAT-020;AOS-PLAT-024

Outcome. Provide deterministic display/input/storage/network/audio/camera/cellular/power fakes that exercise portable services before hardware availability.

Scope. Produce and integrate: fake device framework; scripted state/fault language; golden traces; CI scenarios; visual/control harness. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Every portable hardware service has a CI backend capable of success, denial, timeout, reset, removal and malformed-data cases
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: fake device framework; scripted state/fault language; golden traces; CI scenarios; visual/control harness Verification: service conformance and seeded disconnect/crash/corruption/latency/power cases Evidence: scenario catalog; deterministic replay results; coverage matrix Traceability: specs: AOS-ARCH-015#emulation;AOS-HW-001#qemu-track; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-PLAT-080 — Build cross-target platform conformance suite

Type / priority / status: Experiment · P0 · Backlog Owner / workstream: Platform QA Lead · Conformance Schedule: 2027-04-05 → 2027-10-31 · 25 estimated days · M5 Parent: AOS-PLAT-000 Dependencies: AOS-OPEN-020 Related tasks: AOS-PLAT-070;AOS-PLAT-030

Outcome. Prove that QEMU and native targets implement the same capability, lifecycle, error, update, recovery, power and service semantics.

Scope. Produce and integrate: conformance protocol; target adapters; result schema; CI/lab runner; waiver policy; dashboard. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Differences are declared optional capabilities or tracked defects—never silent target forks in portable clients
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: conformance protocol; target adapters; result schema; CI/lab runner; waiver policy; dashboard Verification: EXP-021 on QEMU, first board and second SoC as they become available Evidence: cross-target matrix; adapter leakage findings; EXP-021 records Traceability: specs: AOS-ARCH-001#portability-test;AOS-ARCH-015#conformance; sources: none; claims: CLM-002;CLM-023; experiments: EXP-021 Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-PLAT-081 — Implement hardware trace capture and deterministic replay

Type / priority / status: Task · P1 · Backlog Owner / workstream: Simulation/Evidence Engineer · Simulation Schedule: 2027-03-22 → 2027-07-11 · 20 estimated days · M5 Parent: AOS-PLAT-000 Dependencies: AOS-LEGAL-005 Related tasks: AOS-PLAT-060;AOS-PLAT-070

Outcome. Record public-safe service-level traces from stock/reference/native systems and replay them against Agent OS backends without importing their OS ABI.

Scope. Produce and integrate: trace format; sanitizers; recorder adapters; replay engine; golden trace corpus; provenance manifest. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Trace schema contains only approved portable observations, preserves timing/state needed for tests, and is versioned/provenanced
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: trace format; sanitizers; recorder adapters; replay engine; golden trace corpus; provenance manifest Verification: record/replay lifecycle scenarios and verify no protected/personal/Android/Linux type crosses format Evidence: trace corpus; sanitation/legal review; replay determinism report Traceability: specs: AOS-ARCH-015#trace-replay;AOS-LEGAL-002#artifact-controls; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-PLAT-090 — Publish developer SDK, debugger, and service test kit

Type / priority / status: Task · P1 · Backlog Owner / workstream: Developer Experience Lead · Developer Experience Schedule: 2027-05-17 → 2027-10-31 · 30 estimated days · M8 Parent: AOS-PLAT-000 Dependencies: AOS-PLAT-003;AOS-PLAT-014;AOS-PLAT-070;AOS-CORE-038 Related tasks: none

Outcome. Let contributors build native components, generate bindings, run emulator tests, inspect capabilities/traces, package, and validate without full source tree expertise.

Scope. Produce and integrate: SDK/sysroot; IDL tools; emulator; debugger protocol/client; package tool; examples; conformance runner; docs. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use Agent OS IDL and capabilities as the native contract; target, POSIX, Android, Linux, and vendor types must terminate in adapters.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • A new contributor can build/test/debug/package a least-authority service using only documented public tools and no private target artifacts
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: SDK/sysroot; IDL tools; emulator; debugger protocol/client; package tool; examples; conformance runner; docs Verification: fresh external-style onboarding on Linux hosts and reproducible sample component release Evidence: onboarding timings; issue log; SDK manifest; sample artifacts Traceability: specs: AOS-ARCH-015#developer-experience;AOS-GOV-002#community-infrastructure; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 02 Specialist review: none

AOS-PLAT-100 — Specify portable device-service quality profiles

Type / priority / status: Task · P1 · Planned Owner / workstream: Platform Architect · Device Contracts Schedule: 2026-09-07 → 2026-10-18 · 15 estimated days · M2 Parent: AOS-PLAT-000 Dependencies: none Related tasks: none

Outcome. Specify portable device-service quality profiles.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-ARCH-020#contract-set, AOS-ARCH-020#quality. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Specify portable device-service quality profiles; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-ARCH-020#contract-set;AOS-ARCH-020#quality; sources: none; claims: none; experiments: none Phase / volume: Phase 2 · Volume 02 Specialist review: none

AOS-PLAT-101 — Implement the legacy-contamination interface linter

Type / priority / status: Task · P1 · Planned Owner / workstream: Platform Tooling Engineer · Compatibility Boundaries Schedule: 2026-11-09 → 2027-01-03 · 20 estimated days · M2 Parent: AOS-PLAT-000 Dependencies: none Related tasks: none

Outcome. Implement the legacy-contamination interface linter.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-ARCH-018#audit, AOS-ARCH-016#acceptance. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Implement the legacy-contamination interface linter; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-ARCH-018#audit;AOS-ARCH-016#acceptance; sources: none; claims: none; experiments: none Phase / volume: Phase 4 · Volume 10 Specialist review: none

AOS-PLAT-102 — Build deterministic service trace replay harnesses

Type / priority / status: Task · P1 · Planned Owner / workstream: Platform Test Engineer · Trace Replay Schedule: 2027-01-11 → 2027-03-21 · 25 estimated days · M3 Parent: AOS-PLAT-000 Dependencies: none Related tasks: none

Outcome. Build deterministic service trace replay harnesses.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-ARCH-020#mocking, AOS-VAL-002#artifact. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Build deterministic service trace replay harnesses; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-ARCH-020#mocking;AOS-VAL-002#artifact; sources: none; claims: none; experiments: none Phase / volume: Phase 5 · Volume 10 Specialist review: none

AOS-PLAT-103 — Generate backend conformance tests from Agent OS IDL

Type / priority / status: Task · P1 · Planned Owner / workstream: IDL and Test Engineer · Conformance Schedule: 2027-04-19 → 2027-07-11 · 30 estimated days · M4 Parent: AOS-PLAT-000 Dependencies: none Related tasks: none

Outcome. Generate backend conformance tests from Agent OS IDL.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-VAL-001#portable, AOS-ARCH-005#type-system. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Generate backend conformance tests from Agent OS IDL; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-VAL-001#portable;AOS-ARCH-005#type-system; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 10 Specialist review: none

AOS-PLAT-104 — Prove two backend implementations expose identical product semantics

Type / priority / status: Experiment · P0 · Planned Owner / workstream: Platform Lead · Portability Proof Schedule: 2027-09-06 → 2027-12-26 · 40 estimated days · M6 Parent: AOS-PLAT-000 Dependencies: none Related tasks: none

Outcome. Prove two backend implementations expose identical product semantics.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-ARCH-016#portability-proof, AOS-VAL-001#portable. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Prove two backend implementations expose identical product semantics; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-ARCH-016#conformance;AOS-VAL-001#portable; sources: none; claims: CLM-002;CLM-023; experiments: EXP-021 Phase / volume: Phase 7 · Volume 03 Specialist review: platform;hardware

AOS-PROD

AOS-PROD-000 — Product Runtime epic

Type / priority / status: Epic · P1 · Backlog Owner / workstream: Product Lead · Program Schedule: 2026-08-10 → 2029-07-08 · 3 estimated days · Continuous Parent: none Dependencies: none Related tasks: none

Outcome. Build entities, actions, history, agents, shell, accessibility, backup, and stock experiences.

Scope. Produce and integrate: project charter; milestone map; owned backlog; status/evidence dashboard. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use portable entity, action, event, view, and provider contracts; no device-specific type may enter product state or UI semantics.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Project has one accountable lead, an approved scope, milestone links, and no orphaned P0/P1 work
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: project charter; milestone map; owned backlog; status/evidence dashboard Verification: monthly project review and gate reconciliation Evidence: project update; dependency report; risk and budget delta Traceability: specs: AOS-PROD-001#product-contract; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 09 Specialist review: none

AOS-PROD-001 — Define entity and relationship schema v0

Type / priority / status: Task · P0 · Backlog Owner / workstream: Product Data Architect · Entity Model Schedule: 2026-08-10 → 2026-10-04 · 15 estimated days · M2 Parent: AOS-PROD-000 Dependencies: AOS-DOCS-012 Related tasks: AOS-PLAT-002

Outcome. Specify stable identity, types, relationships, fields, provenance, trust, lifecycle, merge, deletion, and extension rules for first-party entities.

Scope. Produce and integrate: entity/relationship schemas; type registry; identity/provenance rules; sample graph; invalid fixtures. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use portable entity, action, event, view, and provider contracts; no device-specific type may enter product state or UI semantics.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Identity and provenance survive provider removal/migration, and extensions cannot overwrite canonical fields silently
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: entity/relationship schemas; type registry; identity/provenance rules; sample graph; invalid fixtures Verification: schema review using person, document, activity, device, place, task, media and provider examples Evidence: schema conformance; ambiguity/extension review; sample bundle Traceability: specs: AOS-ARCH-009#entity-model;AOS-PROD-001#entity-surfaces; sources: none; claims: none; experiments: none Phase / volume: Phase 2 · Volume 09 Specialist review: none

AOS-PROD-002 — Implement provenance and entity-resolution model

Type / priority / status: Task · P0 · Backlog Owner / workstream: Product Data Engineer · Entity Model Schedule: 2026-09-07 → 2026-11-01 · 15 estimated days · M3 Parent: AOS-PROD-000 Dependencies: none Related tasks: AOS-PROD-001;AOS-PLAT-013

Outcome. Track source assertions, confidence, conflicts, aliases, merges, splits, user overrides, and audit history without erasing origin.

Scope. Produce and integrate: provenance records; resolution engine; merge/split UI contract; conflict policy; tests. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use portable entity, action, event, view, and provider contracts; no device-specific type may enter product state or UI semantics.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • A user can inspect and undo merge decisions, and no low-trust assertion silently replaces higher-authority data
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: provenance records; resolution engine; merge/split UI contract; conflict policy; tests Verification: duplicate/conflicting contacts, imported documents, provider deletion and malicious assertion scenarios Evidence: resolution test report; user-decision audit; performance baseline Traceability: specs: AOS-ARCH-009#provenance;AOS-PROD-001#entity-surfaces; sources: none; claims: none; experiments: none Phase / volume: Phase 2 · Volume 09 Specialist review: none

AOS-PROD-003 — Implement entity graph store and query service

Type / priority / status: Task · P0 · Backlog Owner / workstream: Product Data Engineer · Entity Store Schedule: 2026-11-16 → 2027-03-07 · 28 estimated days · M4 Parent: AOS-PROD-000 Dependencies: AOS-PROD-001 Related tasks: AOS-PLAT-032;AOS-CORE-034

Outcome. Persist, index, query, authorize, migrate, snapshot, and export entity/relationship data through scoped projections.

Scope. Produce and integrate: graph/query IDL; storage layout; indexes; projection capabilities; migrations; backup/export hooks. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use portable entity, action, event, view, and provider contracts; no device-specific type may enter product state or UI semantics.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Queries expose only granted fields/relationships, indexes can be rebuilt, and schema migration is transactional/recoverable
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: graph/query IDL; storage layout; indexes; projection capabilities; migrations; backup/export hooks Verification: authorization, schema migration, corruption/recovery, query bounds and performance tests Evidence: entity conformance; migration corpus; query/size metrics Traceability: specs: AOS-ARCH-009#storage-engine;AOS-ARCH-009#entity-model; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 09 Specialist review: none

AOS-PROD-010 — Define portable action schema and effect taxonomy

Type / priority / status: Task · P0 · Backlog Owner / workstream: Action Platform Architect · Actions Schedule: 2026-09-07 → 2026-11-01 · 15 estimated days · M2 Parent: AOS-PROD-000 Dependencies: none Related tasks: AOS-PROD-001;AOS-PLAT-002;AOS-CORE-032

Outcome. Specify typed inputs/outputs, effect classes, confirmation, idempotency, capabilities, estimates, reversibility, compensation, audit and provider behavior.

Scope. Produce and integrate: action schema; effect taxonomy; state machine; sample actions; invalid fixtures; safety review. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use portable entity, action, event, view, and provider contracts; no device-specific type may enter product state or UI semantics.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Every action declares effects/data destinations/required grants and external effects cannot be represented as silent local mutations
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: action schema; effect taxonomy; state machine; sample actions; invalid fixtures; safety review Verification: model ten local/external/system actions and adversarial/missing-provider cases Evidence: schema conformance; security/product review; coverage table Traceability: specs: AOS-PROD-003#action-schema;AOS-ARCH-010#action-lifecycle; sources: none; claims: none; experiments: none Phase / volume: Phase 2 · Volume 09 Specialist review: none

AOS-PROD-011 — Implement integration and provider registry

Type / priority / status: Task · P1 · Backlog Owner / workstream: Integration Platform Engineer · Integrations Schedule: 2027-02-08 → 2027-05-02 · 20 estimated days · M4 Parent: AOS-PROD-000 Dependencies: AOS-PROD-010;AOS-PLAT-014 Related tasks: AOS-PLAT-050

Outcome. Register signed entity/action/view/widget providers, their compatibility, capabilities, endpoints, data policies, quality evidence, revocation and lifecycle.

Scope. Produce and integrate: registry service; manifest validation; publisher/trust records; update/revoke/uninstall; query UI API. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use portable entity, action, event, view, and provider contracts; no device-specific type may enter product state or UI semantics.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Registry metadata cannot grant undeclared authority, revoked code cannot launch, and portable entities survive uninstall
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: registry service; manifest validation; publisher/trust records; update/revoke/uninstall; query UI API Verification: valid/malicious/expired/revoked providers, package update, API mismatch and uninstall-preservation tests Evidence: registry conformance; attack/failure results; sample integration catalog Traceability: specs: AOS-PROD-003#integration-package;AOS-PROD-003#conformance; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 09 Specialist review: none

AOS-PROD-012 — Implement action executor, receipts, and compensation

Type / priority / status: Task · P0 · Backlog Owner / workstream: Action Runtime Engineer · Actions Schedule: 2026-12-28 → 2027-04-04 · 24 estimated days · M4 Parent: AOS-PROD-000 Dependencies: AOS-PROD-010 Related tasks: AOS-PLAT-010;AOS-PROD-020

Outcome. Execute approved actions through providers with policy checks, idempotency, progress, cancellation, result validation, receipts and inverse/compensating actions.

Scope. Produce and integrate: executor service; receipt format; idempotency store; compensation coordinator; fake/external provider tests. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use portable entity, action, event, view, and provider contracts; no device-specific type may enter product state or UI semantics.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • No effect occurs before policy/confirmation, retries cannot duplicate declared idempotent effects, and every outcome is auditable
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: executor service; receipt format; idempotency store; compensation coordinator; fake/external provider tests Verification: duplicate, timeout, crash, cancellation, partial external effect, malicious result and compensation tests Evidence: action traces; receipt corpus; failure/compensation matrix Traceability: specs: AOS-ARCH-010#action-lifecycle;AOS-PROD-002#replay-and-undo; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 09 Specialist review: none

AOS-PROD-013 — Implement provider selection and routing policy

Type / priority / status: Task · P1 · Backlog Owner / workstream: Product Platform Engineer · Actions Schedule: 2027-03-22 → 2027-05-23 · 14 estimated days · M4 Parent: AOS-PROD-000 Dependencies: none Related tasks: AOS-PROD-011;AOS-PROD-012

Outcome. Select providers by user defaults, context, privacy, cost, locality, quality, trust, availability and capability fit while exposing sensitive choices.

Scope. Produce and integrate: routing policy service; preference model; explanation API; fallback rules; test providers. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use portable entity, action, event, view, and provider contracts; no device-specific type may enter product state or UI semantics.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Sensitive provider/account changes are never silent and a user can inspect/override the selected route before effect
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: routing policy service; preference model; explanation API; fallback rules; test providers Verification: account/recipient/destination/cost/privacy ambiguity, outage and malicious-ranking tests Evidence: routing test matrix; explanation examples; product/security review Traceability: specs: AOS-PROD-003#provider-selection;AOS-ARCH-010#policy-engine; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 09 Specialist review: none

AOS-PROD-020 — Implement append-only semantic event log

Type / priority / status: Task · P0 · Backlog Owner / workstream: History/Storage Engineer · History Schedule: 2026-11-16 → 2027-02-21 · 24 estimated days · M4 Parent: AOS-PROD-000 Dependencies: AOS-PROD-001 Related tasks: AOS-PLAT-032;AOS-SEC-022

Outcome. Persist versioned semantic events with causal links, provenance, sensitivity, retention, integrity, payload encryption and bounded indexing.

Scope. Produce and integrate: event schema; append API; causal/integrity metadata; encrypted payloads; retention/tombstone rules; tests. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use portable entity, action, event, view, and provider contracts; no device-specific type may enter product state or UI semantics.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Committed events are immutable under the model, protected payloads require scoped keys, and retention/deletion semantics are explicit
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: event schema; append API; causal/integrity metadata; encrypted payloads; retention/tombstone rules; tests Verification: tamper, ordering, crash, schema evolution, deletion/redaction and quota tests Evidence: event-log conformance; recovery/tamper report; storage overhead Traceability: specs: AOS-ARCH-009#event-log;AOS-PROD-002#event-envelope; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 09 Specialist review: none

AOS-PROD-021 — Implement materialized views, snapshots, and deterministic replay

Type / priority / status: Task · P0 · Backlog Owner / workstream: History/Storage Engineer · History Schedule: 2027-01-11 → 2027-04-04 · 22 estimated days · M4 Parent: AOS-PROD-000 Dependencies: none Related tasks: AOS-PROD-020;AOS-PROD-003

Outcome. Derive current entity/activity state from trusted events and snapshots without repeating external effects.

Scope. Produce and integrate: projection framework; snapshot format; replay engine; versioned reducers; corruption/rebuild tools. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use portable entity, action, event, view, and provider contracts; no device-specific type may enter product state or UI semantics.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Identical trusted inputs yield identical state, external actions are represented by receipts not re-executed, and projections can be rebuilt
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: projection framework; snapshot format; replay engine; versioned reducers; corruption/rebuild tools Verification: full rebuild, snapshot+tail, reducer upgrade, corrupt event and external-effect non-replay tests Evidence: replay determinism report; rebuild metrics; failure corpus Traceability: specs: AOS-ARCH-009#materialized-state;AOS-PROD-002#replay-and-undo; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 09 Specialist review: none

AOS-PROD-030 — Assign consistency model to each data family

Type / priority / status: Experiment · P0 · Backlog Owner / workstream: Distributed Data Architect · Data Consistency Schedule: 2027-01-25 → 2027-04-04 · 15 estimated days · M4 Parent: AOS-PROD-000 Dependencies: AOS-PROD-001 Related tasks: AOS-PROD-020;AOS-PROD-021

Outcome. Choose transaction, event log, CRDT, authoritative provider, snapshot, or ephemeral semantics based on failure and collaboration requirements.

Scope. Produce and integrate: data-family matrix; conflict/partition models; merge/transaction rules; simulations; migration constraints. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use portable entity, action, event, view, and provider contracts; no device-specific type may enter product state or UI semantics.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • No data family defaults to CRDT without merge semantics, and irreversible/security state uses transactional/authoritative rules
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: data-family matrix; conflict/partition models; merge/transaction rules; simulations; migration constraints Verification: EXP-061 with concurrent offline edits, permissions, payments/actions, deletion and provider-authoritative data Evidence: model selection report; simulation traces; EXP-061 record Traceability: specs: AOS-ARCH-009#consistency-models;AOS-ADR-0005#decision; sources: none; claims: CLM-019; experiments: EXP-061 Phase / volume: Phase 2 · Volume 09 Specialist review: none

AOS-PROD-031 — Implement encrypted peer/cloud sync v0

Type / priority / status: Task · P1 · Backlog Owner / workstream: Sync Engineer · Sync Schedule: 2027-04-19 → 2027-08-22 · 30 estimated days · M8 Parent: AOS-PROD-000 Dependencies: AOS-PROD-030 Related tasks: AOS-SEC-022;AOS-PLAT-033

Outcome. Synchronize eligible events/objects across devices or user-controlled relays with identity, causal progress, conflicts, revocation, quotas and offline recovery.

Scope. Produce and integrate: sync protocol; device membership; encrypted chunks; causal checkpoints; conflict handling; relay/reference backend. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use portable entity, action, event, view, and provider contracts; no device-specific type may enter product state or UI semantics.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • A revoked device cannot receive future protected content, corrupt peers cannot silently rewrite history, and offline progress converges per chosen models
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: sync protocol; device membership; encrypted chunks; causal checkpoints; conflict handling; relay/reference backend Verification: partition/reorder/duplicate/corrupt/revoked-device/quota/key-rotation and metadata-privacy tests Evidence: sync conformance; threat review; bandwidth/storage metrics; conflict corpus Traceability: specs: AOS-ARCH-009#sync-model;AOS-PROD-004#backup-bundle; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 09 Specialist review: none

AOS-PROD-040 — Prove semantic journal excludes secure/raw sensitive input

Type / priority / status: Experiment · P0 · Backlog Owner / workstream: Privacy/Security Engineer · History Privacy Schedule: 2027-02-22 → 2027-04-18 · 12 estimated days · M4 Parent: AOS-PROD-000 Dependencies: AOS-PROD-020 Related tasks: AOS-PLAT-035;AOS-SEC-051

Outcome. Verify that passwords, one-time codes, biometric material, private-key operations, protected views and diagnostic raw input do not enter durable/synced history by default.

Scope. Produce and integrate: taint labels; secure-input integration; storage/sync inspectors; diagnostic consent/TTL; attack fixtures. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use portable entity, action, event, view, and provider contracts; no device-specific type may enter product state or UI semantics.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • No protected test token appears in event, log, crash, backup or sync payload
  • diagnostic capture is visibly scoped and expires
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: taint labels; secure-input integration; storage/sync inspectors; diagnostic consent/TTL; attack fixtures Verification: EXP-060 using secure fields, clipboard, voice/handwriting, crash logs and malicious providers Evidence: taint report; storage/sync scans; EXP-060 record; privacy approval Traceability: specs: AOS-PROD-002#capture-boundary;AOS-ARCH-012#sensitive-data; sources: none; claims: CLM-016; experiments: EXP-060 Phase / volume: Phase 6 · Volume 09 Specialist review: none

AOS-PROD-041 — Implement history timeline, search, export, deletion, and explanations

Type / priority / status: Task · P1 · Backlog Owner / workstream: History Product Engineer · History UX Schedule: 2027-04-05 → 2027-06-27 · 20 estimated days · M4 Parent: AOS-PROD-000 Dependencies: AOS-PROD-020;AOS-PROD-021 Related tasks: AOS-PROD-040

Outcome. Let users inspect events by entity/activity/provider/capability/device/time, understand provenance, and apply honest retention/deletion/export actions.

Scope. Produce and integrate: timeline/search API and UI; provenance/explanation view; export bundle; deletion modes; retention controls. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use portable entity, action, event, view, and provider contracts; no device-specific type may enter product state or UI semantics.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • UI never implies remote erasure without provider evidence and every visible event exposes source and retention class
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: timeline/search API and UI; provenance/explanation view; export bundle; deletion modes; retention controls Verification: accessibility, protected payload, remote-vs-local deletion, large history and provider removal tests Evidence: UX test report; export sample; deletion audit; performance metrics Traceability: specs: AOS-PROD-002#timeline-and-search;AOS-PROD-002#privacy-controls; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 09 Specialist review: none

AOS-PROD-050 — Implement entity-first shell skeleton

Type / priority / status: Task · P0 · Backlog Owner / workstream: Shell Lead · Shell Schedule: 2027-02-08 → 2027-06-13 · 30 estimated days · M4 Parent: AOS-PROD-000 Dependencies: none Related tasks: AOS-PLAT-037;AOS-PLAT-035;AOS-PROD-003;AOS-PROD-012;AOS-PROD-021

Outcome. Render entity identity/state/activity/actions/views and workspace navigation through portable scene, input, accessibility, storage, and provider contracts.

Scope. Produce and integrate: home/workspace/entity surfaces; semantic focus tree; action/receipt UI; software renderer path; themes/layout primitives. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use portable entity, action, event, view, and provider contracts; no device-specific type may enter product state or UI semantics.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Same shell source runs on two backends, all actions use portable schemas, and custom views expose complete semantics
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: home/workspace/entity surfaces; semantic focus tree; action/receipt UI; software renderer path; themes/layout primitives Verification: QEMU and first-board workflows, keyboard/switch/screen-reader, provider failure and large graph tests Evidence: demo recording; accessibility tree dumps; frame/input metrics; support matrix Traceability: specs: AOS-PROD-001#entity-surfaces;AOS-ARCH-008#scene-and-semantics; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 09 Specialist review: none

AOS-PROD-051 — Implement IntentBox draft and confirmation flow

Type / priority / status: Task · P1 · Backlog Owner / workstream: Intent/Product Engineer · Intent Schedule: 2027-04-19 → 2027-08-08 · 24 estimated days · M8 Parent: AOS-PROD-000 Dependencies: AOS-PROD-010 Related tasks: AOS-PROD-013;AOS-PROD-050;AOS-PROD-071

Outcome. Parse multimodal user input into editable intent drafts with entities, constraints, providers, grants, estimates, ambiguity and effect preview.

Scope. Produce and integrate: intent draft schema; parser interfaces; entity/constraint editor; confirmation UI; test grammar/providers. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use portable entity, action, event, view, and provider contracts; no device-specific type may enter product state or UI semantics.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Input never directly produces a sensitive external effect and users can see/correct interpretation, provider and destination
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: intent draft schema; parser interfaces; entity/constraint editor; confirmation UI; test grammar/providers Verification: ambiguous recipient/account/amount/destination and inaccessible/offline provider tests Evidence: intent safety dataset; confirmation/error metrics; UX/security review Traceability: specs: AOS-PROD-001#intent-box;AOS-ARCH-010#proposal-and-confirmation; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 09 Specialist review: none

AOS-PROD-052 — Implement widget and view sandbox contracts

Type / priority / status: Task · P1 · Backlog Owner / workstream: UI Runtime Engineer · Widgets Schedule: 2027-05-03 → 2027-08-08 · 24 estimated days · M8 Parent: AOS-PROD-000 Dependencies: AOS-PROD-011;AOS-CORE-034 Related tasks: AOS-PROD-050;AOS-PLAT-041

Outcome. Render declarative or sandboxed provider views with scoped entity projections, action handles, accessibility, energy/network budgets and failure fallback.

Scope. Produce and integrate: view/widget manifest; sandbox runtime; data projection; action bridge; resource enforcement; fallback UI. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use portable entity, action, event, view, and provider contracts; no device-specific type may enter product state or UI semantics.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Visible widgets cannot execute effects directly, access undeclared data, evade budgets, or break shell recovery
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: view/widget manifest; sandbox runtime; data projection; action bridge; resource enforcement; fallback UI Verification: malicious widget, overdraw/CPU/network, provider crash/update, accessibility and action-denial tests Evidence: sandbox test report; energy/resource metrics; conformance catalog Traceability: specs: AOS-PROD-003#widgets;AOS-ARCH-008#sandboxed-views; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 09 Specialist review: none

AOS-PROD-053 — Implement notification, structured clipboard, and share services

Type / priority / status: Task · P1 · Backlog Owner / workstream: Product Platform Engineer · Shell Services Schedule: 2027-05-03 → 2027-07-25 · 20 estimated days · M8 Parent: AOS-PROD-000 Dependencies: AOS-PROD-010;AOS-PROD-020 Related tasks: AOS-PROD-050;AOS-PLAT-035

Outcome. Provide typed, provenance-aware, permissioned notifications, clipboard history, selections and share actions across providers.

Scope. Produce and integrate: notification/clipboard/share schemas; secure expiry; UI surfaces; provider/action routing; migration rules. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use portable entity, action, event, view, and provider contracts; no device-specific type may enter product state or UI semantics.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Sensitive clipboard entries expire and remain scoped, notifications expose publisher/provenance, and share destinations are confirmed
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: notification/clipboard/share schemas; secure expiry; UI surfaces; provider/action routing; migration rules Verification: sensitive clipboard, spoofing, expiry, background access, multi-format coercion and accessibility tests Evidence: privacy/security report; action receipts; UX conformance Traceability: specs: AOS-PROD-005#clipboard-and-selection;AOS-PROD-001#activity-and-stories; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 09 Specialist review: none

AOS-PROD-060 — Run full device migration and restore drill

Type / priority / status: Experiment · P0 · Backlog Owner / workstream: Recovery/Product Engineer · Migration Schedule: 2027-10-04 → 2027-12-12 · 15 estimated days · M8 Parent: AOS-PROD-000 Dependencies: AOS-PROD-031;AOS-PROD-061;AOS-PLAT-052;AOS-SEC-022 Related tasks: none

Outcome. Restore portable state, rehydrate accounts, regenerate device-bound identity, report omissions, and revoke/retain old-device trust deliberately.

Scope. Produce and integrate: source/target inventory; migration protocol; re-enrollment flows; omission report; old-device decision; drill automation. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use portable entity, action, event, view, and provider contracts; no device-specific type may enter product state or UI semantics.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • All portable test data restores, non-exportable keys are absent/regenerated, failures are explicit, and unrelated namespaces recover
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: source/target inventory; migration protocol; re-enrollment flows; omission report; old-device decision; drill automation Verification: EXP-062 clean target, partial provider failure, unknown schema, corrupt bundle and lost source scenarios Evidence: restore logs; key inventory; omission report; EXP-062 record Traceability: specs: AOS-PROD-004#migration-flow;AOS-ADR-0005#decision; sources: none; claims: CLM-015; experiments: EXP-062 Phase / volume: Phase 6 · Volume 09 Specialist review: none

AOS-PROD-061 — Implement encrypted backup bundle and verified restore

Type / priority / status: Task · P0 · Backlog Owner / workstream: Backup Engineer · Backup Schedule: 2027-05-17 → 2027-09-05 · 26 estimated days · M8 Parent: AOS-PROD-000 Dependencies: AOS-PROD-020;AOS-PROD-003;AOS-SEC-022 Related tasks: AOS-PLAT-032

Outcome. Create chunked self-describing encrypted backups with integrity, compatibility, omission, key-wrapping, destination and restore verification.

Scope. Produce and integrate: bundle format; chunk/integrity engine; local/peer/vault destinations; verifier; restore planner; omission report. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use portable entity, action, event, view, and provider contracts; no device-specific type may enter product state or UI semantics.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • “Backup complete” requires verified decrypt/integrity/schema inventory and never contains non-exportable test keys
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: bundle format; chunk/integrity engine; local/peer/vault destinations; verifier; restore planner; omission report Verification: corrupt/truncate/wrong key/unknown schema/dedup/privacy/large data and scheduled drill tests Evidence: backup/restore conformance; sampled decrypt result; omission report; storage metrics Traceability: specs: AOS-PROD-004#backup-bundle;AOS-ARCH-009#backup-classes; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 09 Specialist review: none

AOS-PROD-070 — Implement accessibility semantics and assistive-service baseline

Type / priority / status: Task · P0 · Backlog Owner / workstream: Accessibility Lead · Accessibility Schedule: 2027-03-22 → 2027-07-25 · 25 estimated days · M8 Parent: AOS-PROD-000 Dependencies: none Related tasks: AOS-PROD-050;AOS-PLAT-035

Outcome. Make core shell, settings, history, actions, recovery and stock workflows operable through semantic trees, keyboard, switch, screen reader and magnification.

Scope. Produce and integrate: semantic API/runtime; screen reader baseline; focus/navigation tests; audit tooling; accessible recovery/action flows. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use portable entity, action, event, view, and provider contracts; no device-specific type may enter product state or UI semantics.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Core workflows complete without precise touch/vision and accessibility regressions block release
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: semantic API/runtime; screen reader baseline; focus/navigation tests; audit tooling; accessible recovery/action flows Verification: keyboard-only, switch-only, screen-reader and custom-view conformance with disabled/limited sensory scenarios Evidence: accessibility audit; semantic tree coverage; user test findings Traceability: specs: AOS-ARCH-008#scene-and-semantics;AOS-PROD-005#semantic-tree;AOS-PROD-005#assistive-services; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 09 Specialist review: none

AOS-PROD-071 — Implement localization and multimodal input framework

Type / priority / status: Task · P1 · Backlog Owner / workstream: Internationalization/Input Lead · Localization Schedule: 2027-04-19 → 2027-08-22 · 24 estimated days · M8 Parent: AOS-PROD-000 Dependencies: none Related tasks: AOS-PLAT-035;AOS-PROD-070

Outcome. Support Unicode, bidi, locale-aware presentation, pseudolocalization, keyboards, voice/handwriting adapters and retention of originals by policy.

Scope. Produce and integrate: localization runtime; message format; bidi/layout hooks; IME contract; voice/handwriting adapters; CI locales. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use portable entity, action, event, view, and provider contracts; no device-specific type may enter product state or UI semantics.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Persisted values remain locale-independent, core UI passes RTL/expansion, and uncertain recognition stays editable
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: localization runtime; message format; bidi/layout hooks; IME contract; voice/handwriting adapters; CI locales Verification: RTL, CJK/Indic/Thai, mixed scripts, expansion, plural/case, time zones and original-retention tests Evidence: localization matrix; visual diffs; input/privacy results Traceability: specs: AOS-PROD-005#localization;AOS-PROD-005#input-modalities; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 09 Specialist review: none

AOS-PROD-080 — Benchmark entity-first shell against task baselines

Type / priority / status: Experiment · P1 · Backlog Owner / workstream: Product Research Lead · Product Research Schedule: 2027-06-28 → 2027-09-05 · 15 estimated days · M8 Parent: AOS-PROD-000 Dependencies: AOS-PROD-050;AOS-PROD-041;AOS-LEGAL-008 Related tasks: none

Outcome. Measure workflow time, errors, comprehension, resumption, trust and discoverability for entity-first versus conventional app/launcher approaches.

Scope. Produce and integrate: study protocol; representative workflows; comparator; instrumentation; anonymized results; design decisions. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use portable entity, action, event, view, and provider contracts; no device-specific type may enter product state or UI semantics.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Results quantify benefits and regressions, disclose limitations, and update product priorities rather than merely validating the concept
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: study protocol; representative workflows; comparator; instrumentation; anonymized results; design decisions Verification: EXP-070 with pilot then appropriately sized study and accessibility representation Evidence: study report; raw/processed data under policy; EXP-070 record Traceability: specs: AOS-PROD-001#product-contract;AOS-VSN-003#product-evidence; sources: none; claims: CLM-017; experiments: EXP-070 Phase / volume: Phase 6 · Volume 04 Specialist review: none

AOS-PROD-090 — Evaluate IntentBox interpretation and confirmation safety

Type / priority / status: Experiment · P0 · Backlog Owner / workstream: Product Safety Researcher · Product Research Schedule: 2027-08-23 → 2027-10-31 · 15 estimated days · M8 Parent: AOS-PROD-000 Dependencies: AOS-PROD-051;AOS-LEGAL-008 Related tasks: none

Outcome. Measure whether users detect and correct ambiguous entities, accounts, recipients, amounts, providers, destinations and irreversible effects.

Scope. Produce and integrate: ambiguity/effect test set; study UI; error/confirmation metrics; mitigation recommendations. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use portable entity, action, event, view, and provider contracts; no device-specific type may enter product state or UI semantics.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • High-impact ambiguities have explicit mitigation and no tested sensitive action can bypass review through input modality
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: ambiguity/effect test set; study UI; error/confirmation metrics; mitigation recommendations Verification: EXP-071 including time pressure, accessibility needs and adversarial provider labels Evidence: study report; error taxonomy; EXP-071 record; design changes Traceability: specs: AOS-PROD-001#intent-box;AOS-ARCH-010#proposal-and-confirmation; sources: none; claims: none; experiments: EXP-071 Phase / volume: Phase 6 · Volume 04 Specialist review: none

AOS-PROD-100 — Implement and evaluate agent shadow mode

Type / priority / status: Experiment · P1 · Backlog Owner / workstream: Agent Runtime Lead · Agents Schedule: 2027-07-26 → 2027-11-28 · 28 estimated days · M8 Parent: AOS-PROD-000 Dependencies: AOS-PROD-010;AOS-PROD-020;AOS-LEGAL-008 Related tasks: AOS-PROD-051;AOS-SEC-070

Outcome. Let agents propose ranked action plans and explanations without execution, then measure usefulness, errors, unsupported assumptions and user corrections.

Scope. Produce and integrate: agent sandbox; plan schema; shadow recorder; explanation/provenance; evaluation set; review UI. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use portable entity, action, event, view, and provider contracts; no device-specific type may enter product state or UI semantics.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Shadow mode has no effect authority, every proposal cites inputs/providers/capabilities, and evaluation thresholds gate further autonomy
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: agent sandbox; plan schema; shadow recorder; explanation/provenance; evaluation set; review UI Verification: EXP-073 across local/external/sensitive workflows and withheld adversarial cases Evidence: precision/usefulness/error results; capability-use traces; EXP-073 record Traceability: specs: AOS-ARCH-010#trust-ladder;AOS-ARCH-010#evaluation; sources: none; claims: CLM-018; experiments: EXP-073 Phase / volume: Phase 6 · Volume 09 Specialist review: none

AOS-PROD-101 — Implement agent budgets, approval, receipts, and bounded autonomy

Type / priority / status: Task · P1 · Backlog Owner / workstream: Agent Runtime Lead · Agents Schedule: 2027-11-29 → 2028-04-16 · 30 estimated days · M9 Parent: AOS-PROD-000 Dependencies: AOS-PROD-100;AOS-PROD-012;AOS-CORE-034;AOS-PLAT-041;AOS-SEC-070 Related tasks: none

Outcome. Enforce per-agent data, network, cost, energy, rate, time, scope and effect policies for reversible/confirmed execution.

Scope. Produce and integrate: budget/policy engine integration; user grant UI; action execution bridge; receipts; kill/revoke; audit/explanation. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use portable entity, action, event, view, and provider contracts; no device-specific type may enter product state or UI semantics.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • No agent exceeds grants/budgets, sensitive effects require declared confirmation, and revocation stops future work with visible residual effects
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: budget/policy engine integration; user grant UI; action execution bridge; receipts; kill/revoke; audit/explanation Verification: malicious/looping/costly/data-exfiltrating agent, revocation, offline and provider-compromise tests Evidence: containment report; budget accounting; user-study findings; receipts Traceability: specs: AOS-ARCH-010#defense-in-depth;AOS-ARCH-010#resource-budgets; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 09 Specialist review: none

AOS-PROD-110 — Deliver Tier 0/1 stock experience alpha

Type / priority / status: Task · P1 · Backlog Owner / workstream: Product Lead · Stock Experiences Schedule: 2027-07-12 → 2028-02-06 · 45 estimated days · M8 Parent: AOS-PROD-000 Dependencies: AOS-PROD-050 Related tasks: AOS-PROD-053;AOS-PROD-061;AOS-PROD-070;AOS-PLAT-090

Outcome. Integrate settings, system status, files/editor, contacts, calendar, tasks, notes, photos, browser/provider, search, backup and developer tools into coherent portable experiences.

Scope. Produce and integrate: first-party provider packages; coherent navigation/settings; support/limitations matrix; update/migration data; demo workflows. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. Use portable entity, action, event, view, and provider contracts; no device-specific type may enter product state or UI semantics.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Experiences use shared entity/action/history contracts, survive restart/update/migration, and publish unsupported hardware/service functions honestly
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: first-party provider packages; coherent navigation/settings; support/limitations matrix; update/migration data; demo workflows Verification: daily-use dogfood, accessibility, crash/recovery, provider uninstall/update and cross-target conformance Evidence: alpha release bundle; dogfood findings; workflow coverage; known limitations Traceability: specs: AOS-PROD-006#tier-zero;AOS-PROD-006#tier-one; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 09 Specialist review: none

AOS-PROD-120 — Prototype IntentBox and FlexLight with inspectable action plans

Type / priority / status: Task · P1 · Planned Owner / workstream: Product Interaction Lead · Interaction Runtime Schedule: 2027-05-17 → 2027-08-08 · 30 estimated days · M4 Parent: AOS-PROD-000 Dependencies: none Related tasks: none

Outcome. Prototype IntentBox and FlexLight with inspectable action plans.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-PROD-007#intentbox, AOS-PROD-007#planning. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Prototype IntentBox and FlexLight with inspectable action plans; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-PROD-007#intentbox;AOS-PROD-007#planning; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 09 Specialist review: none

AOS-PROD-121 — Specify action-provider manifests and adapter contracts

Type / priority / status: Task · P1 · Planned Owner / workstream: Product Platform Lead · Provider Interoperability Schedule: 2026-09-21 → 2026-11-15 · 20 estimated days · M2 Parent: AOS-PROD-000 Dependencies: none Related tasks: none

Outcome. Specify action-provider manifests and adapter contracts.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-PROD-011#native-manifest, AOS-PROD-011#adapter-model. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Specify action-provider manifests and adapter contracts; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-PROD-011#native-first;AOS-PROD-011#degradation; sources: none; claims: none; experiments: none Phase / volume: Phase 2 · Volume 09 Specialist review: none

AOS-PROD-122 — Implement semantic transclusion and SideMemo prototype

Type / priority / status: Task · P1 · Planned Owner / workstream: Product Engineer · Context and Linking Schedule: 2027-06-28 → 2027-09-19 · 30 estimated days · M4 Parent: AOS-PROD-000 Dependencies: none Related tasks: none

Outcome. Implement semantic transclusion and SideMemo prototype.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-PROD-010#transclusion, AOS-PROD-010#sidememo. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Implement semantic transclusion and SideMemo prototype; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-PROD-010#transclusion;AOS-PROD-010#sidememo; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 09 Specialist review: none

AOS-PROD-123 — Implement personal data authority and purpose-bound views

Type / priority / status: Task · P0 · Planned Owner / workstream: Privacy Product Engineer · Data Authority Schedule: 2027-06-14 → 2027-09-19 · 35 estimated days · M4 Parent: AOS-PROD-000 Dependencies: none Related tasks: none

Outcome. Implement personal data authority and purpose-bound views.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-PROD-009#authority, AOS-PROD-009#purpose-views. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Implement personal data authority and purpose-bound views; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-PROD-009#ownership;AOS-PROD-009#agent-view; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 09 Specialist review: none

AOS-PROD-124 — Evaluate malleable itemized software against conventional apps

Type / priority / status: Experiment · P1 · Planned Owner / workstream: Product Research Lead · Malleable Software Schedule: 2027-08-09 → 2027-10-31 · 30 estimated days · M8 Parent: AOS-PROD-000 Dependencies: none Related tasks: none

Outcome. Evaluate malleable itemized software against conventional apps.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-PROD-008#model, AOS-PROD-008#evaluation. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Evaluate malleable itemized software against conventional apps; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-PROD-008#item-model;AOS-PROD-008#prior-art; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 09 Specialist review: product;ux

AOS-SEC

AOS-SEC-000 — Security, Update, and Assurance epic

Type / priority / status: Epic · P1 · Backlog Owner / workstream: Security Lead · Program Schedule: 2026-07-13 → 2030-01-20 · 3 estimated days · Continuous Parent: none Dependencies: none Related tasks: none

Outcome. Define, test, and independently review the security and update model.

Scope. Produce and integrate: project charter; milestone map; owned backlog; status/evidence dashboard. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. State the threat scope and residual risk; security claims require tests, evidence, update/recovery implications, and independent review where indicated.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Project has one accountable lead, an approved scope, milestone links, and no orphaned P0/P1 work
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: project charter; milestone map; owned backlog; status/evidence dashboard Verification: monthly project review and gate reconciliation Evidence: project update; dependency report; risk and budget delta Traceability: specs: AOS-ARCH-012#threat-model-scope; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 10 Specialist review: none

AOS-SEC-001 — Publish system threat model v0

Type / priority / status: Task · P0 · Backlog Owner / workstream: Security Lead · Threat Modeling Schedule: 2026-07-13 → 2026-08-16 · 12 estimated days · M0 Parent: AOS-SEC-000 Dependencies: none Related tasks: AOS-DOCS-012;AOS-LEGAL-001

Outcome. Define assets, actors, trust boundaries, physical/network/supply-chain/device/agent threats, assumptions, out-of-scope cases and security objectives.

Scope. Produce and integrate: data-flow/trust diagrams; threat catalog; objectives; residual-risk vocabulary; review cadence. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. State the threat scope and residual risk; security claims require tests, evidence, update/recovery implications, and independent review where indicated.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Every major service/hardware/agent/update boundary has an owner, assets, attacker/failure model and linked controls
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: data-flow/trust diagrams; threat catalog; objectives; residual-risk vocabulary; review cadence Verification: architecture/kernel/platform/product/hardware/legal red-team workshop Evidence: threat-model review; unresolved Critical/High threats; mitigation task links Traceability: specs: AOS-ARCH-012#threat-model-scope;AOS-ARCH-012#assets-and-adversaries; sources: none; claims: none; experiments: none Phase / volume: Phase 2 · Volume 10 Specialist review: none

AOS-SEC-002 — Inventory trusted computing base and privilege domains

Type / priority / status: Task · P0 · Backlog Owner / workstream: Security Architect · Architecture Security Schedule: 2026-07-27 → 2026-09-06 · 10 estimated days · M1 Parent: AOS-SEC-000 Dependencies: none Related tasks: AOS-SEC-001;AOS-PLAT-001;AOS-CORE-001

Outcome. Enumerate kernel, loader, recovery, key, update, identity, driver, firmware, secure hardware and privileged service components and minimize their authority.

Scope. Produce and integrate: TCB inventory; privilege/capability graph; firmware trust list; reduction plan; target-specific exceptions. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. State the threat scope and residual risk; security claims require tests, evidence, update/recovery implications, and independent review where indicated.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Every privileged component has a justified minimal role and firmware/target trust is distinguishable from native Agent OS assurance
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: TCB inventory; privilege/capability graph; firmware trust list; reduction plan; target-specific exceptions Verification: source/package/board manifest analysis and privilege-route review Evidence: TCB size/composition baseline; authority graph; exception tasks Traceability: specs: AOS-ARCH-012#trusted-computing-base;AOS-ARCH-004#least-authority; sources: none; claims: none; experiments: none Phase / volume: Phase 2 · Volume 10 Specialist review: none

AOS-SEC-010 — Conduct capability and IPC security design review

Type / priority / status: Review · P0 · Backlog Owner / workstream: Capability Security Reviewer · Kernel Security Schedule: 2026-11-30 → 2027-01-24 · 12 estimated days · M2 Parent: AOS-SEC-000 Dependencies: AOS-SEC-001 Related tasks: AOS-CORE-032;AOS-CORE-036

Outcome. Find authority amplification, confused-deputy, delegation, revocation, TOCTOU, message-validation, denial-of-service and audit weaknesses before API freeze.

Scope. Produce and integrate: review model; abuse cases; findings; required changes/tests; residual assumptions. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. State the threat scope and residual risk; security claims require tests, evidence, update/recovery implications, and independent review where indicated.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • No unresolved Critical/High authority-amplification or message-ownership finding enters kernel API level 0
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: review model; abuse cases; findings; required changes/tests; residual assumptions Verification: independent review and adversarial model/property tests Evidence: security report; finding closure links; API gate recommendation Traceability: specs: AOS-ARCH-004#security-properties;AOS-ARCH-004#confused-deputy-defense; sources: SRC-017;SRC-018;SRC-001;SRC-002; claims: none; experiments: none Phase / volume: Phase 6 · Volume 10 Specialist review: none

AOS-SEC-011 — Build continuous kernel and service fuzzing program

Type / priority / status: Task · P0 · Backlog Owner / workstream: Security Testing Lead · Fuzzing Schedule: 2026-12-14 → 2028-06-25 · 25 estimated days · Continuous Parent: AOS-SEC-000 Dependencies: AOS-PLAT-003 Related tasks: AOS-CORE-039;AOS-PLAT-014

Outcome. Fuzz syscall, IDL, package, storage, network, USB, camera, cellular, update and backup parsers with minimized reproducible corpora.

Scope. Produce and integrate: fuzz infrastructure; target inventory; corpora; coverage/crash dashboard; triage SLA; regression fixtures. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. State the threat scope and residual risk; security claims require tests, evidence, update/recovery implications, and independent review where indicated.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Every untrusted binary/protocol parser has an owner and active fuzz target or explicit risk acceptance
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: fuzz infrastructure; target inventory; corpora; coverage/crash dashboard; triage SLA; regression fixtures Verification: seeded vulnerabilities and sustained runs with reproducible crash minimization Evidence: coverage trends; findings/fixes; corpus provenance; SLA report Traceability: specs: AOS-ARCH-015#fuzzing;AOS-LEGAL-003#provenance-record; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 10 Specialist review: none

AOS-SEC-012 — Create formal model and assurance roadmap for kernel core

Type / priority / status: Spike · P1 · Backlog Owner / workstream: Formal Methods Lead · Formal Assurance Schedule: 2026-12-28 → 2027-06-13 · 30 estimated days · M5 Parent: AOS-SEC-000 Dependencies: AOS-CORE-001;AOS-CORE-032 Related tasks: AOS-SEC-010

Outcome. Model selected capability, IPC, lifecycle, scheduling/resource and memory invariants and choose feasible proof/refinement targets.

Scope. Produce and integrate: formal model; invariant catalog; code/model relation; tooling evaluation; staged proof plan; external-review proposal. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. State the threat scope and residual risk; security claims require tests, evidence, update/recovery implications, and independent review where indicated.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Assurance claims state exact model/code/version and no “verified kernel” claim is made without completed refinement evidence
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: formal model; invariant catalog; code/model relation; tooling evaluation; staged proof plan; external-review proposal Verification: model-check key properties and compare traces to executable/kernel tests Evidence: model repository; checked properties; gap report; budget/staffing recommendation Traceability: specs: AOS-ARCH-002#assurance-boundary;AOS-ARCH-012#assurance-strategy; sources: SRC-001;SRC-002; claims: none; experiments: none Phase / volume: Phase 2 · Volume 10 Specialist review: none

AOS-SEC-020 — Select and integrate cryptographic primitives and provider API

Type / priority / status: Task · P0 · Backlog Owner / workstream: Cryptography Engineer · Cryptography Schedule: 2026-10-05 → 2026-12-13 · 15 estimated days · M2 Parent: AOS-SEC-000 Dependencies: AOS-SEC-001;AOS-LEGAL-004 Related tasks: none

Outcome. Use reviewed cryptographic libraries/primitives through a narrow provider interface with algorithm agility, key separation, misuse resistance and test vectors.

Scope. Produce and integrate: crypto provider contract; algorithm/profile choices; library/provenance review; key-purpose API; vector/negative tests. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. State the threat scope and residual risk; security claims require tests, evidence, update/recovery implications, and independent review where indicated.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Callers cannot request raw universal keys or unsafe defaults, and algorithm/version/key purpose are recorded for migration
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: crypto provider contract; algorithm/profile choices; library/provenance review; key-purpose API; vector/negative tests Verification: known-answer tests, misuse/nonce/key-purpose cases, dependency/SBOM review and independent crypto review Evidence: crypto design/review; vector results; dependency provenance; migration plan Traceability: specs: AOS-ARCH-012#cryptography;AOS-LEGAL-003#dependency-policy; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 10 Specialist review: none

AOS-SEC-021 — Implement entropy collection and DRBG service

Type / priority / status: Task · P0 · Backlog Owner / workstream: Cryptography Engineer · Cryptography Schedule: 2026-11-30 → 2027-02-21 · 16 estimated days · M3 Parent: AOS-SEC-000 Dependencies: AOS-CORE-010 Related tasks: AOS-PLAT-013;AOS-SEC-020;AOS-OPEN-020

Outcome. Collect, health-test, condition and distribute entropy with explicit startup/failure/target quality and no silent weak fallback.

Scope. Produce and integrate: entropy source interfaces; health tests; DRBG; reseed/fork behavior; quality/status API; target backends. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. State the threat scope and residual risk; security claims require tests, evidence, update/recovery implications, and independent review where indicated.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Security operations block/fail explicitly before sufficient entropy and cloned/emulated instances do not silently share state
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: entropy source interfaces; health tests; DRBG; reseed/fork behavior; quality/status API; target backends Verification: known-answer/statistical health/failure/no-source/duplicate-VM and suspend tests Evidence: entropy design review; health/failure logs; target source inventory Traceability: specs: AOS-ARCH-012#entropy; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 10 Specialist review: none

AOS-SEC-022 — Implement key lifecycle and data-key hierarchy

Type / priority / status: Task · P0 · Backlog Owner / workstream: Key Management Engineer · Key Management Schedule: 2027-01-25 → 2027-05-16 · 24 estimated days · M4 Parent: AOS-SEC-000 Dependencies: AOS-SEC-020;AOS-PROD-001 Related tasks: AOS-SEC-021

Outcome. Generate, wrap, store, rotate, revoke, destroy, recover and migrate keys according to portable/rehydratable/non-exportable data classes.

Scope. Produce and integrate: key service; purpose-scoped handles; hierarchy/wrapping; rotation/revocation; hardware-provider abstraction; recovery metadata; audit. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. State the threat scope and residual risk; security claims require tests, evidence, update/recovery implications, and independent review where indicated.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Raw private keys never enter ordinary clients, non-exportable keys cannot be backed up, and rotation/revocation has bounded recoverable semantics
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: key service; purpose-scoped handles; hierarchy/wrapping; rotation/revocation; hardware-provider abstraction; recovery metadata; audit Verification: lost/corrupt key, rotation, revoked device, backup/restore, process compromise and no-hardware-provider scenarios Evidence: key inventory; lifecycle traces; backup omission test; independent review Traceability: specs: AOS-ARCH-012#key-management;AOS-ADR-0005#decision; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 10 Specialist review: none

AOS-SEC-030 — Implement signed boot manifest and root-of-trust abstraction

Type / priority / status: Task · P0 · Backlog Owner / workstream: Boot Security Engineer · Boot Security Schedule: 2026-12-28 → 2027-04-18 · 24 estimated days · M3 Parent: AOS-SEC-000 Dependencies: AOS-SEC-020;AOS-CORE-012 Related tasks: AOS-PLAT-015

Outcome. Verify kernel/initial image/configuration, bind target/security version, expose boot state, and allow replaceable hardware/software roots of trust.

Scope. Produce and integrate: signed manifest; verifier; key/trust-root abstraction; verified boot-state record; development/production modes; recovery policy. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. State the threat scope and residual risk; security claims require tests, evidence, update/recovery implications, and independent review where indicated.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Untrusted image/configuration does not execute as trusted, boot state is inspectable, and target secure hardware is an adapter—not assumed “as-is”
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: signed manifest; verifier; key/trust-root abstraction; verified boot-state record; development/production modes; recovery policy Verification: tamper, wrong target/version/key, development-state warning, key rotation and recovery tests on QEMU/board Evidence: boot verification traces; key/manifest test corpus; threat review Traceability: specs: AOS-ARCH-013#boot-chain;AOS-ARCH-013#root-of-trust; sources: none; claims: none; experiments: none Phase / volume: Phase 4 · Volume 10 Specialist review: none

AOS-SEC-031 — Specify measured boot and attestation semantics

Type / priority / status: Task · P2 · Backlog Owner / workstream: Security Architect · Attestation Schedule: 2027-04-19 → 2027-07-11 · 14 estimated days · M8 Parent: AOS-SEC-000 Dependencies: AOS-SEC-030;AOS-LEGAL-008 Related tasks: AOS-SEC-022

Outcome. Define what is measured, who can attest, privacy/linkability, freshness, claims, key custody, verifier policy and unsupported hardware behavior.

Scope. Produce and integrate: measurement log format; attestation token/claim model; privacy policy; software reference; hardware-provider requirements. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. State the threat scope and residual risk; security claims require tests, evidence, update/recovery implications, and independent review where indicated.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Attestation cannot become ambient cross-service tracking and claims identify exact measured scope and trust anchor
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: measurement log format; attestation token/claim model; privacy policy; software reference; hardware-provider requirements Verification: replay/linkability/downgrade/unknown-target/verifier-policy tests and privacy review Evidence: attestation design; test tokens; residual privacy/compatibility risks Traceability: specs: AOS-ARCH-013#attestation;AOS-ARCH-012#identity-and-attestation; sources: none; claims: none; experiments: none Phase / volume: Phase 5 · Volume 10 Specialist review: none

AOS-SEC-032 — Implement anti-rollback and security-version policy

Type / priority / status: Task · P0 · Backlog Owner / workstream: Boot/Update Security Engineer · Boot Security Schedule: 2027-04-05 → 2027-06-27 · 16 estimated days · M4 Parent: AOS-SEC-000 Dependencies: AOS-PLAT-004 Related tasks: AOS-SEC-030;AOS-SEC-022

Outcome. Prevent unauthorized downgrade of boot, update, schema, keys and security-critical services while preserving explicit recovery and development paths.

Scope. Produce and integrate: security-version counters/metadata; authorization policy; recovery/dev exceptions; key rotation; test vectors. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. State the threat scope and residual risk; security claims require tests, evidence, update/recovery implications, and independent review where indicated.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Security downgrade is rejected or explicitly user-authorized in a visible non-production state and counter failure remains recoverable
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: security-version counters/metadata; authorization policy; recovery/dev exceptions; key rotation; test vectors Verification: downgrade, counter corruption, interrupted increment, recovery and development-mode tests Evidence: anti-rollback matrix; fault traces; policy review Traceability: specs: AOS-ARCH-013#anti-rollback;AOS-ARCH-013#rollback; sources: none; claims: none; experiments: none Phase / volume: Phase 5 · Volume 10 Specialist review: none

AOS-SEC-040 — Threat-model and red-team update/package pipeline

Type / priority / status: Review · P0 · Backlog Owner / workstream: Update Security Reviewer · Update Security Schedule: 2027-07-26 → 2027-10-17 · 15 estimated days · M8 Parent: AOS-SEC-000 Dependencies: AOS-SEC-032;AOS-LEGAL-012 Related tasks: AOS-PLAT-050;AOS-PLAT-051

Outcome. Find signing, metadata, mirror, replay, freeze, mix-and-match, dependency, rollback, partial-install and recovery attacks.

Scope. Produce and integrate: threat model; attack fixtures; findings; metadata/key/threshold policy; incident/compromise recovery plan. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. State the threat scope and residual risk; security claims require tests, evidence, update/recovery implications, and independent review where indicated.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • No unresolved Critical/High update attack remains before developer preview and signing-key compromise has a recovery plan
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: threat model; attack fixtures; findings; metadata/key/threshold policy; incident/compromise recovery plan Verification: adversarial repository/network/signing-key/partial-state tests and independent review Evidence: red-team report; finding closure; key-compromise drill; release recommendation Traceability: specs: AOS-ARCH-013#update-model;AOS-ARCH-012#supply-chain; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 10 Specialist review: none

AOS-SEC-041 — Threat-model and validate recovery environment

Type / priority / status: Review · P0 · Backlog Owner / workstream: Recovery Security Reviewer · Recovery Security Schedule: 2027-07-12 → 2027-09-19 · 12 estimated days · M8 Parent: AOS-SEC-000 Dependencies: AOS-SEC-030;AOS-SEC-022 Related tasks: AOS-PLAT-052

Outcome. Ensure recovery authentication, data access, destructive operations, trust roots, media, physical access and factory/owner reset preserve declared security.

Scope. Produce and integrate: recovery threat model; authentication/data/destructive policy; attack fixtures; audit/indicator requirements; findings. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. State the threat scope and residual risk; security claims require tests, evidence, update/recovery implications, and independent review where indicated.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Recovery cannot silently bypass device-data policy, destructive actions are unmistakable, and trust state after recovery is explicit
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: recovery threat model; authentication/data/destructive policy; attack fixtures; audit/indicator requirements; findings Verification: stolen device, malicious media, rollback, data extraction, factory reset and failed-key scenarios Evidence: security report; drill traces; finding closure; user-warning review Traceability: specs: AOS-ARCH-013#recovery-environment;AOS-PROD-004#failure-and-rollback; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 10 Specialist review: none

AOS-SEC-050 — Implement data classification and privacy policy engine

Type / priority / status: Task · P0 · Backlog Owner / workstream: Privacy Engineering Lead · Privacy Engineering Schedule: 2026-11-02 → 2027-02-07 · 22 estimated days · M4 Parent: AOS-SEC-000 Dependencies: AOS-SEC-001;AOS-PROD-001;AOS-PROD-010 Related tasks: AOS-LEGAL-008

Outcome. Classify entity/event/action/diagnostic/sensor/location/biometric/credential data and enforce read/use/destination/retention/sync/export policy.

Scope. Produce and integrate: classification vocabulary; labels/taint; policy evaluator; destination/retention rules; UI/explanation API; tests. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. State the threat scope and residual risk; security claims require tests, evidence, update/recovery implications, and independent review where indicated.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Data cannot be silently downgraded or sent to undeclared destinations and policy decisions are inspectable
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: classification vocabulary; labels/taint; policy evaluator; destination/retention rules; UI/explanation API; tests Verification: cross-provider/action/journal/sync/backup/diagnostic flows and malicious relabel/declassification tests Evidence: policy conformance; data-flow audit; denied/explained examples; performance overhead Traceability: specs: AOS-ARCH-012#sensitive-data;AOS-PROD-002#privacy-controls; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 10 Specialist review: none

AOS-SEC-051 — Implement log, trace, crash, and evidence redaction controls

Type / priority / status: Task · P0 · Backlog Owner / workstream: Security Observability Engineer · Privacy Engineering Schedule: 2026-12-14 → 2027-03-07 · 16 estimated days · M4 Parent: AOS-SEC-000 Dependencies: AOS-LEGAL-004 Related tasks: AOS-PLAT-011;AOS-SEC-050

Outcome. Prevent secrets, personal data, protected protocol content and hardware identifiers from leaking through observability or public experiment bundles.

Scope. Produce and integrate: structured field classes; redaction/tokenization; serial aliases; capture profiles; public/private export; scanners/taint tests. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. State the threat scope and residual risk; security claims require tests, evidence, update/recovery implications, and independent review where indicated.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Seeded secrets never appear in normal/public evidence and redaction preserves diagnostic correlation through approved aliases
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: structured field classes; redaction/tokenization; serial aliases; capture profiles; public/private export; scanners/taint tests Verification: seed credentials/tokens/personal/proprietary fields through logs/crashes/traces and inspect raw/exported artifacts Evidence: redaction scan; taint coverage; false-positive/negative review; public bundle sample Traceability: specs: AOS-ARCH-012#diagnostic-data;AOS-RES-004#evidence-integrity; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 10 Specialist review: none

AOS-SEC-060 — Implement package signing, SBOM, provenance, and revocation security

Type / priority / status: Task · P0 · Backlog Owner / workstream: Supply Chain Security Engineer · Supply Chain Schedule: 2026-12-28 → 2027-04-04 · 20 estimated days · M4 Parent: AOS-SEC-000 Dependencies: AOS-SEC-020;AOS-LEGAL-012 Related tasks: AOS-PLAT-014

Outcome. Bind packages/components/firmware/models/data to publishers, builds, dependencies, licenses and revocation while supporting key rotation and compromise recovery.

Scope. Produce and integrate: signature/provenance verification; trust/revocation metadata; SBOM binding; key rotation; transparency/audit option; test repository. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. State the threat scope and residual risk; security claims require tests, evidence, update/recovery implications, and independent review where indicated.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Executable/artifact identity is bound to approved build/provenance and revoked/unknown publishers cannot run without explicit development policy
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: signature/provenance verification; trust/revocation metadata; SBOM binding; key rotation; transparency/audit option; test repository Verification: tamper, dependency substitution, compromised/revoked/expired key, build mismatch and offline-update tests Evidence: supply-chain conformance; signed sample/SBOM; key-compromise drill Traceability: specs: AOS-PROD-003#integration-package;AOS-LEGAL-003#compliance-tooling;AOS-ARCH-012#supply-chain; sources: SRC-058;SRC-059;SRC-060; claims: none; experiments: none Phase / volume: Phase 6 · Volume 10 Specialist review: none

AOS-SEC-061 — Establish secure software and model supply-chain process

Type / priority / status: Task · P1 · Backlog Owner / workstream: Product Security Lead · Supply Chain Schedule: 2027-02-08 → 2027-06-27 · 18 estimated days · M8 Parent: AOS-SEC-000 Dependencies: AOS-DOCS-001 Related tasks: AOS-SEC-060

Outcome. Apply secure development, review, build provenance, dependency/model/data intake, secrets, release and vulnerability controls across repositories.

Scope. Produce and integrate: SSDF-aligned practice map; SLSA roadmap; branch/review/secret/dependency policies; model/data cards; release checklist; training. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. State the threat scope and residual risk; security claims require tests, evidence, update/recovery implications, and independent review where indicated.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Critical repositories/releases have required review/provenance, secrets and vulnerable dependencies are detected, and model/data rights are recorded
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: SSDF-aligned practice map; SLSA roadmap; branch/review/secret/dependency policies; model/data cards; release checklist; training Verification: internal audit and simulated dependency/signing/secret/model provenance incidents Evidence: control audit; training completion; incident exercise; improvement backlog Traceability: specs: AOS-GOV-004#response-process;AOS-LEGAL-003#dependency-policy;AOS-ARCH-015#release-evidence; sources: SRC-058;SRC-059;SRC-060;SRC-061; claims: none; experiments: none Phase / volume: Phase 2 · Volume 10 Specialist review: none

AOS-SEC-070 — Red-team agent capability, data, budget, and effect containment

Type / priority / status: Experiment · P0 · Backlog Owner / workstream: Agent Security Lead · Agent Security Schedule: 2027-06-28 → 2027-10-31 · 20 estimated days · M8 Parent: AOS-SEC-000 Dependencies: AOS-PROD-010;AOS-SEC-050;AOS-CORE-034 Related tasks: AOS-PROD-100

Outcome. Prove malicious or erroneous agents cannot exceed grants, budgets, destinations, confirmation, effect class or receipt/compensation rules.

Scope. Produce and integrate: adversarial agents/prompts/providers; exfiltration/cost/loop/confused-deputy tests; policy findings; kill/revoke drills. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. State the threat scope and residual risk; security claims require tests, evidence, update/recovery implications, and independent review where indicated.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • No test agent exceeds capabilities/budgets or performs sensitive effect without confirmation
  • any escape blocks autonomy release
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: adversarial agents/prompts/providers; exfiltration/cost/loop/confused-deputy tests; policy findings; kill/revoke drills Verification: EXP-074 with hidden cases and compromised provider/agent scenarios Evidence: red-team report; denied/escaped action traces; EXP-074 record; remediation Traceability: specs: AOS-ARCH-010#defense-in-depth;AOS-ARCH-010#resource-budgets; sources: none; claims: CLM-018; experiments: EXP-074 Phase / volume: Phase 6 · Volume 10 Specialist review: none

AOS-SEC-080 — Commission independent kernel/platform security review

Type / priority / status: Review · P0 · Backlog Owner / workstream: Security Lead · Independent Assurance Schedule: 2027-11-01 → 2028-03-19 · 15 estimated days · M8 Parent: AOS-SEC-000 Dependencies: AOS-CORE-040;AOS-SEC-010;AOS-SEC-040;AOS-SEC-041;AOS-PLAT-080 Related tasks: none

Outcome. Obtain an external architecture/code/test review of kernel, capabilities, IPC, memory, update, recovery and selected driver/service boundaries.

Scope. Produce and integrate: review scope/RFP; evidence/code access; external report; remediation/retest plan; public summary. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. State the threat scope and residual risk; security claims require tests, evidence, update/recovery implications, and independent review where indicated.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Developer preview has no unresolved externally identified Critical issue and all High issues have fix or explicit gate-blocking decision
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: review scope/RFP; evidence/code access; external report; remediation/retest plan; public summary Verification: qualified reviewer selection, finding triage/closure and retest Evidence: independent report; closure matrix; residual risk acceptance; public summary Traceability: specs: AOS-ARCH-012#independent-review;AOS-PLAN-006#technical-gates; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 10 Specialist review: none

AOS-SEC-090 — Operate vulnerability disclosure and incident response

Type / priority / status: Task · P0 · Backlog Owner / workstream: Product Security Incident Lead · Security Operations Schedule: 2026-09-07 → 2030-07-07 · 5 estimated days · Continuous Parent: AOS-SEC-000 Dependencies: none Related tasks: AOS-PLAT-051;AOS-SEC-061

Outcome. Provide continuous private intake, triage, embargo coordination, fixes, signed updates, advisories, safe harbor and lessons learned.

Scope. Produce and integrate: security contact/key; triage system; severity/SLA; incident roles; advisory/update workflow; exercises; metrics. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. State the threat scope and residual risk; security claims require tests, evidence, update/recovery implications, and independent review where indicated.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • Reports are acknowledged/owned, supported targets can receive fixes, and incidents preserve evidence while protecting reporters/users
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: security contact/key; triage system; severity/SLA; incident roles; advisory/update workflow; exercises; metrics Verification: quarterly tabletop plus seeded report from intake through patched release Evidence: exercise logs; response metrics; advisories/postmortems as applicable Traceability: specs: AOS-GOV-004#reporting-vulnerabilities;AOS-GOV-004#response-process; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 10 Specialist review: none

AOS-SEC-100 — Maintain system assurance case and claim language

Type / priority / status: Task · P1 · Backlog Owner / workstream: Security Assurance Lead · Assurance Schedule: 2028-01-24 → 2030-07-07 · 15 estimated days · Continuous Parent: AOS-SEC-000 Dependencies: AOS-SEC-012 Related tasks: AOS-SEC-080;AOS-DOCS-013

Outcome. Link security objectives to design controls, implementation, tests, reviews, residual assumptions, supported targets and update lifecycle.

Scope. Produce and integrate: assurance argument/evidence map; target-specific claims; residual risks; release deltas; public wording. The work includes negative and failure-path behavior, documentation, ownership, and downstream interface impact.

Boundary. State the threat scope and residual risk; security claims require tests, evidence, update/recovery implications, and independent review where indicated.

Downstream trust. Consumers may depend on the result only after the stated verification passes and the evidence artifact is linked. Unknowns become claim or experiment records rather than implicit promises.

Acceptance criteria

  • No public security/privacy assurance exceeds implementation, target, threat or update evidence and stale claims are removed promptly
  • Named deliverables are committed or stored under stable IDs with owner and reviewer
  • The stated verification passes on the declared target or the task records a bounded negative result
  • Affected specifications, claims, risks, dependencies, and follow-up tasks are updated

Deliverables: assurance argument/evidence map; target-specific claims; residual risks; release deltas; public wording Verification: release/gate audits trace every security claim to current evidence and supported scope Evidence: assurance case versions; orphaned/weak claim report; approvals Traceability: specs: AOS-ARCH-012#assurance-strategy;AOS-RES-003#claim-states; sources: none; claims: none; experiments: none Phase / volume: Phase 6 · Volume 04 Specialist review: none

AOS-SEC-110 — Implement source-taint and restricted-evidence policy checks

Type / priority / status: Task · P0 · Planned Owner / workstream: Security Tooling Engineer · Source Assurance Schedule: 2026-11-16 → 2027-01-10 · 20 estimated days · M2 Parent: AOS-SEC-000 Dependencies: none Related tasks: none

Outcome. Implement source-taint and restricted-evidence policy checks.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-ARCH-018#taint, AOS-VAL-002#integrity. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Implement source-taint and restricted-evidence policy checks; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-ARCH-018#taint;AOS-VAL-002#integrity; sources: none; claims: none; experiments: none Phase / volume: Phase 4 · Volume 10 Specialist review: none

AOS-SEC-111 — Build the capability and IPC executable assurance models

Type / priority / status: Task · P0 · Planned Owner / workstream: Formal Methods Engineer · Formal Modeling Schedule: 2026-10-19 → 2027-01-10 · 30 estimated days · M2 Parent: AOS-SEC-000 Dependencies: none Related tasks: none

Outcome. Build the capability and IPC executable assurance models.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-ARCH-019#initial-models, AOS-VAL-005#methods. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Build the capability and IPC executable assurance models; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-ARCH-019#initial-models;AOS-VAL-005#methods; sources: none; claims: none; experiments: none Phase / volume: Phase 3 · Volume 02 Specialist review: none

AOS-SEC-112 — Evaluate agent shadow mode and dangerous false-action rates

Type / priority / status: Experiment · P0 · Planned Owner / workstream: Agent Safety Lead · Agent Assurance Schedule: 2027-08-23 → 2027-11-28 · 35 estimated days · M8 Parent: AOS-SEC-000 Dependencies: none Related tasks: none

Outcome. Evaluate agent shadow mode and dangerous false-action rates.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-VAL-005#agents, AOS-ARCH-010#trust-model. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Evaluate agent shadow mode and dangerous false-action rates; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-VAL-005#agents;AOS-ARCH-010#trust-ladder; sources: none; claims: CLM-018; experiments: EXP-073;EXP-074 Phase / volume: Phase 6 · Volume 10 Specialist review: security;product

AOS-SEC-113 — Publish a scoped release assurance case and residual-risk register

Type / priority / status: Review · P0 · Planned Owner / workstream: Security Lead · Assurance Case Schedule: 2027-11-29 → 2028-02-06 · 25 estimated days · M8 Parent: AOS-SEC-000 Dependencies: none Related tasks: none

Outcome. Publish a scoped release assurance case and residual-risk register.

Scope. Produce the normative artifact, executable evidence, decision record, and follow-up work required by AOS-VAL-005#assurance-case, AOS-ARCH-019#assurance-levels. Preserve the native Agent OS boundary: Android/Linux behavior may inform Pixel 9 experiments but must not become a portable API or runtime dependency.

Method. Start from the immutable source corpus and primary references; identify assumptions and legal constraints; perform the bounded analysis or experiment; record raw evidence and uncertainty; update claims, risks, tasks, and cross-linked specifications.

Acceptance criteria

  • The deliverable is linked to every listed specification and uses stable document/task/source identifiers.
  • The result distinguishes verified evidence, reasoned inference, unresolved assumptions, and rejected claims.
  • Acceptance evidence is reproducible from a clean environment or includes exact target, procedure, artifacts, and limitations.
  • Android, Linux, vendor, confidential, and reverse-engineered details remain behind the approved boundary with provenance and retirement metadata where applicable.

Deliverables: Normative report or implementation for Publish a scoped release assurance case and residual-risk register; machine-readable metadata; updated claim/risk/task records; review notes and follow-up issue links. Verification: Run the relevant document, schema, conformance, build, experiment, or hardware checks; independently review boundary compliance and acceptance criteria. Evidence: Versioned report, raw logs/data or source diff, checksums, reviewer identity/status, and links to the exact specification anchors. Traceability: specs: AOS-VAL-005#assurance-case;AOS-ARCH-019#assurance-levels; sources: none; claims: none; experiments: none Phase / volume: Phase 8 · Volume 10 Specialist review: independent-security